The development to which this permission relates must be begun not later than the expiration of three years beginning with the date of this permission.
Reason: By virtue of Sections 91 to 95 of the Town and Country Planning Act 1990 as amended by section 51 of the Planning and Compulsory Purchase Act 2004.
Related application(s):
P21/S1383/DIS,
P23/S0303/DISThat the development hereby approved shall be carried out in accordance with the details shown on the following approved plans, 2c and 1b, except as controlled or modified by conditions of this permission.
Reason: To secure the proper planning of the area in accordance with Development Plan policies.
Related application(s):
P21/S1383/DIS,
P23/S0303/DISExcept in the case of any building work hereby permitted, no change in the levels of the land shall take place unless in accordance with a detailed scheme which shall have been submitted to and approved in writing by the Local Planning Authority before any development commences on site. The scheme shall include details of existing and proposed ground levels.
Reason: To ensure a satisfactory form of development in accordance with Policies DES1, DES2, DES6 and ENV1 of the South Oxfordshire Local Plan 2035.
Related application(s):
P21/S1383/DISPrior to the construction of the development hereby approved above foundation level, a photographic schedule of all materials to be used in the external construction and finishes of the development hereby permitted shall be submitted to and approved in writing by the Local Planning Authority.
Reason: In the interests of the visual appearance of the development in accordance with Policies DES1, DES2 and ENV1 of the South Oxfordshire Local Plan 2035.
Related application(s):
P21/S1383/DISNotwithstanding the provisions of the Town and Country (General Permitted Development Order) 2015 (or any Order revoking or re-enacting that Order), no development as specified in Schedule 2, Part 1, Class A - Extensions, Class B - Roof Extensions and Class E - Outbuildings shall be undertaken without obtaining planning permission from the Local Planning Authority.
Reason: The specific circumstances of this site warrant the Local Planning Authority having control over any further development as specified in the condition in the interests of visual and residential amenity and in accordance with Policies DES1, DES2, DES6 and ENV1 of the South Oxfordshire Local Plan 2035.
Related application(s):
P21/S1383/DISPrior to the commencement of development an Energy Statement demonstrating how the development will achieve at least a 40% reduction in carbon emissions compared with code 2013 Building Regulations and details of how this will be monitored shall be submitted to the local planning authority and approved in writing.
Reason: To ensure a reduction in carbon emissions in accordance with Policy DES10 of the South Oxfordshire Local Plan 2035.
Related application(s):
P21/S1383/DISPrior to the first occupation of the development, the existing means of access onto Chinnor Road/Garden City shall be improved and laid out and constructed strictly in accordance with the local highway authority's specifications and all ancillary works specified shall be undertaken to incorporate a minimum increase in width of 0.5 metre.
Reason: In the interest of highway safety in accordance with Policy TRANS5 of the South Oxfordshire Local Plan 2035.
Prior to the first occupation of the development hereby approved, the parking and turning areas shall be provided in accordance with the approved plan 1b and shall be constructed, laid out, surfaced, drained and completed to be compliant with sustainable drainage (SuDS) principles, and shall be retained unobstructed except for the parking of vehicles associated with the development at all times.
Reason: In the interests of highway safety and in accordance with Policy TRANS5 of the South Oxfordshire Local Plan 2011.
Prior to the construction of the development hereby permitted above foundation level, a scheme for the landscaping of the site, including the planting of live trees and shrubs and the provision of boundary treatment shall be submitted to and approved in writing by the Local Planning Authority. The scheme shall be implemented prior to the first occupation or use of development and thereafter be maintained in accordance with the approved scheme. In the event of any of the trees or shrubs so planted dying or being seriously damaged or destroyed within 5 years of the completion of the development, a new tree or shrub or equivalent number of trees or shrubs, as the case may be, of a species first approved by the Local Planning Authority, shall be planted and properly maintained in a position or positions first approved in writing by the Local Planning Authority.
Reason: To help to assimilate the development into its surroundings in accordance with Policies DES1, DES2 and ENV1 of the South Oxfordshire Local Plan 2035.
Prior to the commencement of any site works (including demolition or site clearance) a protected area shall be designated for all existing trees which are shown to be retained, and the trees shall be protected in accordance with a scheme which complies with the current edition of BS 5837: "Trees in relation to design, demolition and construction" that shall first have been submitted to, and approved in writing by, the Local Planning Authority. The agreed measures shall be kept in place during the entire course of development.
Reason: To safeguard trees which are visually important in accordance with Policies ENV1, DES1, and DES2 of the South Oxfordshire Local Plan 2035.
Prior to the commencement of development, a full surface water drainage scheme, including details of the size, position and construction of drainage works, coupled with PPG measures shall be submitted to, and approved in writing by, the Local Planning Authority. The drainage scheme shall be designed to accommodate a 1 in 100 year storm + 40% CC and will be implemented in accordance with the approved details prior to the occupation of the development hereby approved.
Reason: To ensure the proper provision of surface water drainage and to ensure flooding is not exacerbated in the locality in accordance with Policy EP4 of the South Oxfordshire Local Plan 2035.
Prior to the commencement of development, a full foul water drainage scheme shall be submitted to and approved in writing by the Local Planning Authority. The scheme shall include details of the size, position and construction of the drainage scheme, all coupled with calculations to evidence this. The foul drainage works shall be implemented in accordance with the approved details prior to the occupation of the development hereby approved.
Reason: To ensure the proper provision of foul water drainage and to ensure flooding and pollution is not exacerbated in the locality in accordance with Policy EP4 of the South Oxfordshire Local Plan 2035.