Parapet works to various structures (5 total) Great Western mainline(GWML) Electrification.
Grid Reference
452906/195189
Applicant
Network Rail
Western Town Planning
3rd Floor, Temple Point
Redcliffe Way
Bristol
BS1 6NL
Agent
Network Rail
Western Town Planning
3rd Floor, Temple Point
Redcliffe Way
Bristol
BS1 6NL
Consultation / Notification
No further Representations on this application will be accepted.
Consultations / Notifications to date are shown below.
Name / Number
Date Sent
Response Date
Application Type
None
(Screening Opinion)
Application Progress
Date Received
5th March 2012
Registration Date
5th March 2012
Target Decision Date
26th March 2012
Decision
EIA not required on 2nd May 2012