Description
Sports pavillion to include changing rooms and associated facilities. (As amplified by letter from the applicant dated 15.2.99).
Location
Recreation Ground, Mackney Lane, Brightwell-cum-Sotwell
Grid Reference
458252/190432
Applicant
Brightwell-cum-Sotwell P.C.
New Barn Court
Bakers Lane
Brightwell-cum-Sotwell
WALLINGFORD OX10 0PX
Agent
Brightwell-cum-Sotwell P.C.
New Barn Court
Bakers Lane
Brightwell-cum-Sotwell
WALLINGFORD OX10 0PX
Consultation / Notification
No further Representations on this application will be accepted.
Consultations / Notifications to date are shown below.
Name / Number
Date Sent
Response Date
Mr T Peet (re Bridleways)
Tech.Dir,Babtie Engineering S.
c/o Mr A E Hayzelden,
New Barn Court,
Bakers Lane,
Brightwell-cum-Sotwell,
WALLINGFORD, Oxon
OX10 0PX
15 03 1999
Workman Cottage
Macknee Lane
BRIGHTWELL CUM SOTWELL
Oxon
10 03 1999
Tech.Information Manager-TWUL
09 04 1999
Technical Director, Babtie
26 02 1999
Wilkins Cottage
Mackney Lane
BRIGHTWELL CUM SOTWELL
Oxon
10 03 1999
Application Type
Minor
(Outline)
Application Progress
Date Received
5th February 1999
Registration Date
5th February 1999
Start Consultation Period
5th February 1999
End Consultation Period
15th March 1999
Target Decision Date
2nd April 1999
Decision
Outline Planning Permission on 7th April 1999
Conditions / Refusal Reasons
That approval of the details of the siting, design and external appearance
of the building(s), the means of access thereto and the landscaping of
the site (hereinafter called "the reserved matters") shall be obtained
from the Local Planning Authority in writing before any development is
commenced.
Reason: As the application is in outline only and not accompanied by
detailed plans.
That application for approval of the reserved matters shall be made to the
Local Planning Authority before the expiration of three years from the
date of this permission.
Reason: By virtue of Sections 91 to 95 of the Town and Country Planning
Act 1990.
That the development to which this permission relates shall be begun not
later than whichever is the later of the following dates:
(a) the expiration of five years from the date of this permission; or
(b) the expiration of two years from the final approval of the reserved
matters, or, in the case of approval on different dates, the final
approval of the last such matter to be approved.
Reason: By virtue of Sections 91 to 95 of the Town and Country Planning
Act 1990.
That no development shall commence until the foul sewage rising main
crossing the site has been located and details of the site layout
in relation to this be submitted to and agreed by the Local Planning
Authority in writing.
Reason: In the interests of public health and to avoid pollution.