Planning Application Details

P99/S0978/LBApplication Type: Listed Bldg. Consent (Show Map - opens in new window)
Status Bar
 
 Completed stage
 
 Current stage
 
 Next stage
Application registered
Consultation period
Application under consideration
Decision made
Description
A rectangular orangery with hipped roof and central gable built against existing wall.
Location
Shiplake House, Shiplake
Grid Reference
477014/178377
Applicant
Wallbrook Trustees
Shiplake House
Shiplake
HENLEY-ON-THAMES
Oxon
RG9 4BL
Agent
Marston and Langinger
192 Ebury Street
LONDON
SW1W 8UP
Constraints
Grade II Listed Building
Case Officer
Mrs L.A.Smith
Telephone: 01235 422600
Email: planning@southoxon.gov.uk
Consultation / Notification
No further Representations on this application will be accepted.

Consultations / Notifications to date are shown below.

Name / Number
Date Sent
Response Date
 
c/o Mr J. D. Ritchie,
Beggars Roost,
Northfield Avenue,
Lower Shiplake,
HENLEY-ON-THAMES Oxon
RG9 3PD
13 01 2000
 
Tech.Dir,Babtie Engineering S.
15 12 1999
 
Conservation Officer
10 01 2000
 
County Archaeologist
 
S.Clarke,Snr.Pl.Liaison Off.
10 01 2000
 
Application Type
Other (Listed Bldg. Consent)
Application Progress
Date Received  
9th December 1999
Registration Date  
9th December 1999
Start Consultation Period  
9th December 1999
End Consultation Period  
14th January 2000
Target Decision Date  
3rd February 2000
Decision
Listed Building Consent on 21st January 2000
Conditions / Refusal Reasons
That the works hereby permitted shall be begun before the expiration of five years from the date of this consent. Reason: By virtue of Section 18 of the Planning (Listed Buildings and Conservation Areas) Act 1990. That before any work is undertaken in pursuance of this consent, such steps shall be taken and such works shall be carried out to secure the safety and stability of the building during the alterations, and to provide protection for the building against the weather during the progress of the works. Reason: To secure the safety and protection of the listed building. That no work shall commence until a detailed joinery specification of the Orangery (including its external finish) has been submitted to and approved in writing by the Local Planning Authority. Thereafter the Orangery shall be constructed in accordance with the approved specification. Reason: To ensure that the Orangery retains the character and appearance of the listed building.
Appeal
No appeal lodged.