Application registered
Consultation
period
Application under consideration
Decision
made
Description
Demolish and rebuild walls in new location with associated works (as amended by drawing nos 1 & 4a accompanying agent's letter dated 24 June 1999).
Location
The Old Manor Yard, Mapledurham.
Grid Reference
467014/176623
Applicant
The Mapledurham 1997 Trust
The Estate Office
Mapledurham
Nr READING
RG4 7TR
Agent
M Carlisle
The Estate Office
Mapledurham
Nr READING
RG4 7TR
Constraints
Mapledurham Conservation Area
Grade II* Listed Building
Consultation / Notification
No further Representations on this application will be accepted.
Consultations / Notifications to date are shown below.
Name / Number
Date Sent
Response Date
c/o Mr R. F. Penfold,
30 Venetia Close,
Caversham,
READING
RG4 8UG
23 12 1999
Tech.Dir,Babtie Engineering S.
07 05 1999
S.Clarke,Snr.Pl.Liaison Off.
15 12 1999
Counc for British Archaeology
Royal Comm. on Hist.Mon.(Eng)
Soc. for Protection Anc. Build
Ancient Monuments Society
The Chiltern Society: Planning
27 05 1999
Application Progress
Date Received
4th May 1999
Registration Date
4th May 1999
Start Consultation Period
4th May 1999
End Consultation Period
4th June 1999
Target Decision Date
29th June 1999
Decision
Planning Permission on 27th March 2000
Conditions / Refusal Reasons
That the development must be begun not later than the expiration of five years beginning with the date of this permission and if this condition is not complied with this permission shall lapse.
Reason: By virtue of Sections 91 to 95 of the Town and Country Planning Act 1990.
That samples of the materials to be used for the external walls shall be submitted to and approved in writing by the Local Planning Authority before any development commences.
Reason: To ensure that the details of the development are satisfactory.
That prior to the commencement of the development hereby approved details of the bonding shall be submitted to and approved in writing. The walls shall then be erected using the approved bonding.
Reason: To ensure that the details of the development are satisfactory.
That there shall be no raising of existing ground levels on the site.
Reason: To prevent the increased risk of flooding due to impedance of flood flows and reduction of flood storage capacity.
That no spoil or materials shall be deposited or stored on that part of the site lying within the area of land liable to flood.
Reason: To prevent the increased risk of flooding due to impedance of flood flows and reduction of flood storage capacity.
That any walls or fencing constructed within or around the site shall be designed to be permeable to flood water, and retained as such thereafter.
Reason: To prevent obstruction to the flow and storage of flood water, with a consequent increased risk of flooding.
Updates
These Planning
Application Details were returned live from our back office database,
and as such are as up to date as when the page was retrieved.