Planning Application Details

P99/S0135Application Type: No Type (Show Map - opens in new window)
Status Bar
 
 Completed stage
 
 Current stage
 
 Next stage
Application registered
Consultation period
Application under consideration
Decision made
Description
Erection of replacement workshop building (as amended by drawing no PW/2/2 A accompanying letter from Agent dated 16 March 1999 and amplified by drawing accompanying letter from Agent dated 9 April 1999).
Location
The Log House, Kiln Lane, Binfield Heath.
Grid Reference
475470/178685
Applicant
Mr Patrick Watts
The Log House
Kiln Lane
Binfield Heath
HENLEY-ON-THAMES   RG9 4EN
Agent
McCoy Associates
31 Station Road
HENLEY-ON-THAMES
Oxon
RG9 1AT
Case Officer
Ms S Spencer
Telephone: 01235 422600
Email: planning@southoxon.gov.uk
Consultation / Notification
No further Representations on this application will be accepted.

Consultations / Notifications to date are shown below.

Name / Number
Date Sent
Response Date
 
c/o Mr J. D. Ritchie,
Beggars Roost,
Northfield Avenue,
Lower Shiplake,
HENLEY-ON-THAMES Oxon
RG9 3PD
07 04 1999
 
Tech.Dir,Babtie Engineering S.
23 02 1999
 
Kiln Cottage
Kiln Lane
Binfield Heath
HENLEY ON THAMES, Oxon
RG9 4ES
05 03 1999
 
Silver Birches
Kiln Lane
Binfield Heath
HENLEY ON THAMES, Oxon
 
Application Type
Minor
Application Progress
Date Received  
19th February 1999
Registration Date  
19th February 1999
Start Consultation Period  
19th February 1999
End Consultation Period  
18th March 1999
Target Decision Date  
16th April 1999
Decision
Planning Permission on 16th April 1999
Conditions / Refusal Reasons
That the development must be begun not later than the expiration of five years beginning with the date of this permission and if this condition is not complied with this permission shall lapse. Reason: By virtue of Sections 91 to 95 of the Town and Country Planning Act 1990. That no development shall take place until there has been submitted to and approved in writing by the Local Planning Authority a schedule of materials and finishes for the external walls and roof. Reason: To ensure that the details of the development are satisfactory. That prior to the first use of the building the existing workshop building and container workshop shown on the drawing accompanying the letter from the Agent dated 9 April 1999, shall be demolished and be removed from the land. Reason: The proposed building is intended as a replacement for the existing building and storage unit and their removal would enhance the character and appearance of the area. That the building shall be occupied and used only in connection with the existing business on the site, which includes forestry, forestry contractor's and tree surgeons yard and the manufacture and sale of wooden articles and structures, and shall not be occupied or used separately. Reason: To safeguard the character of the area. That prior to the commencement of the development details of the slab level of the building shall be submitted to and approved in writing by the Local Planning Authority and the building shall be constructed in all respects in accordance with the approved details. Reason: In view of the differences in the level of the site and to protect local amenities.
Appeal
No appeal lodged.
Updates