Application registered
Consultation
period
Application under consideration
Decision
made
Description
Demolition of all existing buildings except for the lodge and erection of new single and two storey buildings of 4856 sq mtrs for light industrial and B.1 office use. Construction of access roads and car parking. (Renewal of planning permission ref:P93/N0500)
Location
Siarey's Yard, Station Road, Chinnor
Grid Reference
475589/200667
Applicant
Howland Furniture Ltd
c/o Agent
Agent
Hall Needham Associates
Suite 2
Kille House
Chinnor Road, THAME
OX9 3NU
Consultation / Notification
No further Representations on this application will be accepted.
Consultations / Notifications to date are shown below.
Name / Number
Date Sent
Response Date
c/o Mrs Brenda Wilson,
Council Office,Village Centre,
High Street,
CHINNOR,
Oxon
OX9 4DH
01 04 1999
Tech.Dir,Babtie Engineering S.
21 Greenwood Meadow
CHINNOR
Oxon
29 Greenwood Meadow
CHINNOR
Oxon
OX9 4JQ
06 04 1999
7 Oakley Road
CHINNOR
Oxon
25 Church Lane
CHINNOR
Oxon
27 Church Lane
CHINNOR
Oxon
82 Station Road
CHINNOR
Oxon
OX9 4HA
84 Station Road
CHINNOR
Oxon
OX9 4HA
06 04 1999
86 Station Road
CHINNOR
Oxon
67 Station Road
CHINNOR
Oxon
69 Station Road
CHINNOR
Oxon
71 Station Road
CHINNOR
Oxon
73 Station Road
CHINNOR
Oxon
25 Ravensmead
CHINNOR
Oxon
26 Ravensmead
CHINNOR
Oxon
13 Ravensmead
CHINNOR
Oxon
14 Ravensmead
CHINNOR
Oxon
1 Meadow Road
CHINNOR
Oxon
3 Meadow Road
CHINNOR
Oxon
5 Meadow Road
CHINNOR
Oxon
7 Meadow Road
CHINNOR
Oxon
9 Meadow Road
CHINNOR
Oxon
11 Meadow Road
CHINNOR
Oxon
Technical Director, Babtie
22 04 1999
S.Clarke,Snr.Pl.Liaison Off.
23 04 1999
Tech.Information Manager-TWUL
Application Type
Major
(Renewal)
Application Progress
Date Received
17th March 1999
Registration Date
17th March 1999
Start Consultation Period
17th March 1999
End Consultation Period
16th April 1999
Target Decision Date
12th May 1999
Decision
Planning Permission on 21st April 1999
Conditions / Refusal Reasons
That this permission is subject to all the conditions imposed on
P93/N0500.
Reason: As the application is a renewal of a planning permission
previously granted.
Before the development is commenced a detailed site investigation shall
be carried out to establish if the site is contaminated, to assess the
degree and nature of the contamination present, and to determine its
potential for the pollution of the water environment. The method and
extent of this site investigation shall be agreed with the Planning
Authority prior to commencement of the work. Details of appropriate
measures to prevent pollution of groundwater and surface water, including
provisions for monitoring, shall then be submitted to and approved in
writing by the Planning Authority before development commences. The
development shall then proceed in strict accordance with the measures
approved.
Reason: To prevent pollution of the water environment.
Updates