Planning Application Details

P98/W0802Application Type: No Type (Show Map - opens in new window)
Status Bar
 
 Completed stage
 
 Current stage
 
 Next stage
Application registered
Consultation period
Application under consideration
Decision made
Description
Replacement of existing River Thames towpath footbridge over the River Thame. (As amended by letter from applicant dated 4 December 1998).
Location
Confluence of River Thame with River Thames, Dorchester
Grid Reference
457826/193225
Applicant
Environment Agency
Thames Region
Isis House, Howbery Park
Crowmarsh
WALLINGFORD  OX10 0BD
Agent
Halcrow Group Limited
Burderop Park
SWINDON
Wilts  SN4 0QD
Case Officer
Mr M Moore
Telephone: 01235 422600
Email: planning@southoxon.gov.uk
Consultation / Notification
No further Representations on this application will be accepted.

Consultations / Notifications to date are shown below.

Name / Number
Date Sent
Response Date
 
c/o Mr G G D Russell
The Pigeons,
High Street,
Dorchester-on-Thames,
WALLINGFORD, Oxon
OX10 7HH
25 11 1998
 
Tech.Dir,Babtie Engineering S.
 
S.Clarke,Snr.Pl.Liaison Off.
19 01 1999
 
Building Control Serv.Manager
 
Public Rights of Way Officer
16 11 1998
 
CPRE (Wallingford Area)
20 11 1998
 
County Archaeologist
07 12 1998
 
The Ridgeway National Trail
National Trails Office
Countrydside Services
Holton Oxford OX33 1QQ
25 11 1998
 
Application Type
Minor
Application Progress
Date Received  
27th October 1998
Registration Date  
27th October 1998
Start Consultation Period  
27th October 1998
End Consultation Period  
3rd December 1998
Target Decision Date  
22nd December 1998
Decision
Planning Permission on 14th December 1998
Conditions / Refusal Reasons
That the development must be begun not later than the expiration of five years beginning with the date of this permission and if this condition is not complied with this permission shall lapse. Reason: By virtue of Sections 91 to 95 of the Town and Country Planning Act 1990. That details of any gates to be provided shall be submitted to and approved in writing by the Local Planning Authority prior to the commencement of the development. Reason: To ensure that the details of the development are satisfactory. That within six months of the substantial completion of the bridge, all ground restoration of the bridge approaches, site compound, temporary bridge and any access shall be completed to the satisfaction of the Local Planning Authority. Reason: To help assimilate the development into its surroundings. That a full archaeological watching brief shall be carried out during the period of construction works in accordance with details and by a professionally competent archaeological organisation which shall have been submitted to and approved in writing by the Local Planning Authority before development commences. The brief shall include the recording of any archaeological features revealed, limited archaeological excavation and the retrieval of artefactual evidence. Reason: As the site is of archaeological importance.
Appeal
No appeal lodged.
Updates
These Planning Application Details were returned live from our back office database, and as such are as up to date as when the page was retrieved.