Application registered
Consultation
period
Application under consideration
Decision
made
Description
Reconstruction and extension of clubhouse. (As amplified by letters dated 29.4.98, 20.5.98, 8.6.98 and 15.6.98).
Location
Abingdon Road, Dorchester
Grid Reference
457293/195261
Applicant
Dorchester Sailing Club
c/o 16 Market Place
WALLINGFORD
Oxon
OX10 0AE
Agent
Dorchester Sailing Club
c/o 16 Market Place
WALLINGFORD
Oxon
OX10 0AE
Consultation / Notification
No further Representations on this application will be accepted.
Consultations / Notifications to date are shown below.
Name / Number
Date Sent
Response Date
c/o Mr G G D Russell
The Pigeons,
High Street,
Dorchester-on-Thames,
WALLINGFORD, Oxon
OX10 7HH
14 04 1998
Tech.Dir,Babtie Engineering S.
Orchid Lake
Abingdon Road
Dorchester-on-Thames
WALLINGFORD Oxon
Tradewinds
95 Abingdon Road
Dorchester-on-Thames
WALLINGFORD OX10 7LB
06 04 1998
97 Abingdon Road
Dorchester-on-Thames
WALLINGFORD
Oxon
101 Abingdon Road
Dorchester-on-Thames
WALLINGFORD
Oxon
103 Abingdon Road
Dorchester-on-Thames
WALLINGFORD
Oxon
Technical Director, Babtie
15 05 1998
S.Clarke,Snr.Pl.Liaison Off.
18 05 1998
2nd. Abingdon Sea Scouts
Farm Road
Abingdon
Oxon
03 06 1998
Application Progress
Date Received
23rd March 1998
Registration Date
23rd March 1998
Start Consultation Period
23rd March 1998
End Consultation Period
23rd April 1998
Target Decision Date
18th May 1998
Decision
Planning Permission on 1st July 1998
Conditions / Refusal Reasons
That the development must be begun not later than the expiration of five
years beginning with the date of this permission and if this condition
is not complied with this permission shall lapse.
Reason: By virtue of Sections 91 to 95 of the Town and Country Planning
Act 1990.
That samples of all materials to be used in the external construction and
finishes of the development hereby permitted shall be submitted to and
approved in writing by the Local Planning Authority before the
development is commenced.
Reason: To safeguard the character of the area.
That a scheme for the landscaping of the site, including the planting of
live trees and shrubs and the treatment of the access road and
hardstandings, shall be submitted to and approved in writing by the
Local Planning Authority prior to the commencement of the development
hereby permitted. The scheme shall be implemented as approved within
12 months of the commencement of the approved development and thereafter
be maintained in accordance with the approved scheme to the complete
satisfaction of the Local Planning Authority. In the event of any of
the trees or shrubs so planted dying or being seriously damaged or
destroyed within 3 years of the completion of the development, a new
tree or shrub or equivalent number of trees or shrubs, as the case may
be, of a species first approved by the Local Planning Authority, be
planted and properly maintained in a position or positions first approved
by the Local Planning Authority.
Reason: To help to assimilate the development into its surroundings.
That development shall not begin until a scheme for the disposal of
foul sewage has been submitted to and approved in writing by the
Local Planning Authority.
Reason: In the interests of public health and to avoid pollution.
That surface water shall not be disposed of other than in accordance
with a detailed surface water drainage scheme which shall first have
been submitted to and approved in writing by the Local Planning
Authority.
Reason: In the interests of public health.
That the building shall be used only for purposes directly in
association with and ancillary to the use of the adjoining lake for
sailing.
Reason: Because permission is given only in view of the special
circumstances.
That no additional works of implementation of the planning permission
dated 26 October 1994 issued in respect of application reference
P94/W0572 shall be undertaken. If building works continue (other
than completion of the existing 12m x 6m building) then this permission
shall lapse and become void.
Reason: To accord with the policy of the Local Planning Authority.
Updates
These Planning
Application Details were returned live from our back office database,
and as such are as up to date as when the page was retrieved.