Application registered
Consultation
period
Application under consideration
Decision
made
Description
Two-storey side extension, single storey rear extension and pitched roof over front porch and garage. (As amended by additional Plan accompanying Applicants letter dated 18 February 1998).
Grid Reference
474891/200964
Applicant
Mr G B Pitter
84 Hedgerley
CHINNOR
Oxon
OX9 4TJ
Agent
Mr G B Pitter
84 Hedgerley
CHINNOR
Oxon
OX9 4TJ
Consultation / Notification
No further Representations on this application will be accepted.
Consultations / Notifications to date are shown below.
Name / Number
Date Sent
Response Date
c/o Mrs Brenda Wilson,
Council Office,Village Centre,
High Street,
CHINNOR,
Oxon
OX9 4DH
05 03 1998
Tech.Dir,Babtie Engineering S.
82 Hedgerley
CHINNOR
Oxon
86 Hedgerley
CHINNOR
Oxon
Application Progress
Date Received
3rd February 1998
Registration Date
3rd February 1998
Start Consultation Period
3rd February 1998
End Consultation Period
5th March 1998
Target Decision Date
31st March 1998
Decision
Planning Permission on 5th March 1998
Conditions / Refusal Reasons
That the development must be begun not later than the expiration of five
years beginning with the date of this permission and if this condition
is not complied with this permission shall lapse.
Reason: By virtue of Sections 91 to 95 of the Town and Country Planning
Act 1990.
That the materials to be used for the external walls and roofs shall be
of the same colour, type and texture as those used on the existing
dwelling.
Reason: To ensure that the details of the development are satisfactory.
That notwithstanding the provisions of the Town and Country Planning
(General Permitted Development) Order 1995 (or any order revoking and
re-enacting that Order) no windows shall be constructed in the side
elevation of the extension.
Reason: To ensure that the development is not unneighbourly.
That the extension hereby approved shall not be occupied until three
parking spaces have been provided within the curtilage of the
dwellinghouse, such spaces to be retained and mainted.
Reason: In the interest of highway safety and convenience.
Updates
These Planning
Application Details were returned live from our back office database,
and as such are as up to date as when the page was retrieved.