Planning Application Details

P97/W0253/OApplication Type: Outline (Show Map - opens in new window)
Status Bar
 
 Completed stage
 
 Current stage
 
 Next stage
Application registered
Consultation period
Application under consideration
Decision made
Description
Demolition of 3874 sq.m of existing office (B1), warehouse (B8) and production (B2 & B1C) accommodation and the erection of modern replacement buildings and retention of an existing 1607 sq.m warehouse.
Location
Tower Road, Off Fane Drive, Berinsfield
Grid Reference
457608/196777
Applicant
Croda International Plc
Cowick Hall
Snaith
Goole
DN14 9AA
Agent
John D Wood
49 Berkeley Square
LONDON
W1X 6AL
Case Officer
Mr M.P.Brookes
Telephone: 01235 422600
Email: planning@southoxon.gov.uk
Consultation / Notification
No further Representations on this application will be accepted.

Consultations / Notifications to date are shown below.

Name / Number
Date Sent
Response Date
 
c/o Mrs Jennifer Thompson,
9 Sixpenny Lane,
Chalgrove,
OXFORD   OX44 7YD
19 05 1997
 
Tech.Dir,Babtie Engineering S.
 
Linda Currie
 
2 Glyme Drive
Berinsfield
WALLINGFORD
Oxon
 
4 Glyme Drive
Berinsfield
WALLINGFORD
Oxon
 
6 Glyme Drive
Berinsfield
WALLINGFORD
Oxon
 
8 Glyme Drive
Berinsfield
WALLINGFORD
Oxon
 
10 Glyme Drive
Berinsfield
WALLINGFORD
Oxon
 
12 Glyme Drive
Berinsfield
WALLINGFORD
Oxon
 
18 Glyme Drive
Berinsfield
WALLINGFORD
Oxon
 
20 Glyme Drive
Berinsfield
WALLINGFORD
Oxon
 
22 Glyme Drive
Berinsfield
WALLINGFORD
Oxon
 
24 Glyme Drive
Berinsfield
WALLINGFORD
Oxon
 
26 Glyme Drive
Berinsfield
WALLINGFORD
Oxon
 
28 Glyme Drive
Berinsfield
WALLINGFORD
Oxon
 
30 Glyme Drive
Berinsfield
WALLINGFORD
Oxon
 
32 Glyme Drive
Berinsfield
WALLINGFORD
Oxon
 
34 Glyme Drive
Berinsfield
WALLINGFORD
Oxon
 
36 Glyme Drive
Berinsfield
WALLINGFORD
Oxon
 
38 Glyme Drive
Berinsfield
WALLINGFORD
Oxon
 
54 Fane Drive
Berinsfield
WALLINGFORD
Oxon
 
56 Fane Drive
Berinsfield
WALLINGFORD
Oxon
 
58 Fane Drive
Berinsfield
WALLINGFORD
Oxon
 
60 Fane Drive
Berinsfield
WALLINGFORD
Oxon
 
Technical Director, Babtie
16 05 1997
 
S.Clarke,Snr.Pl.Liaison Off.
 
Tech. Support Services - TWUL
 
County Archaeologist
22 05 1997
 
Application Type
Major (Outline)
Application Progress
Date Received  
14th April 1997
Registration Date  
14th April 1997
Start Consultation Period  
14th April 1997
End Consultation Period  
23rd May 1997
Target Decision Date  
9th June 1997
Decision
Outline Planning Permission on 16th June 1997
Conditions / Refusal Reasons
That notwithstanding any indications as to these matters which have been given in this application, no development shall be started until full details of the following have been submitted to, and approved in writing by, the Local Planning Authority:- the layout of the site, including roads and buildings, access to the site and buildings, surface water drainage; the plans and elevations of all buildings; the colour and type of facing materials to be used for the external walls and roofs; the provision to be made on the site for the garaging and parking of motor vehicles in accordance with the Local Planning Authority's approved standards; the stages in which the development shall take place; a scheme for the landscaping of the site including the planting of live trees, the treatment of forecourts and driveways, and the provision of boundary fencing and screen walling. Reason: As the application is in outline only and not accompanied by detailed plans. That application for the approval of the reserved matters referred to in Condition 1 above shall be made to the Local Planning Authority not later than three years from the date of this permission, and if this condition is not complied with this permission shall lapse. Reason: By virtue of Sections 91 to 95 of the Town and Country Planning Act 1990. That the development hereby permitted shall be begun either before the expiration of five years from the date of this permission, or before the expiration of two years from the date of approval of the last of the reserved matters to be approved, whichever is the later. Reason: By virtue of Sections 91 to 95 of the Town and Country Planning Act 1990. That, notwithstanding the general phasing provisions in Condition 1, no new building shall be occupied until at least an equivalent area of floorspace of building devoted to the same Use Class as defined in the schedule and plan accompanying the application has been demolished and the materials therefrom re-used or removed from the site. Reason: To ensure satisfactory comprehensive development and to protect local amenities. That no new building shall be occupied until provision for car parking and servicing has been made in accordance with details submitted to and approved in writing by the Local Planning Authority. The parking and servicing areas shall thereafter be kept available at all times for those purposes. Reason: To comply with the Local Planning Authority's vehicle parking standards and to protect local amenities. That details of surface water drainage works shall be submitted to and approved in writing by the Local Planning Authority prior to the development commencing. Reason: In the interests of public health. That development shall not begin until a scheme for the disposal of foul sewage has been submitted to and approved in writing by the Local Planning Authority. Reason: In the interests of public health and to avoid pollution. Before the development is commenced a detailed site investigation shall be carried out to establish if the site is contaminated, to assess the degree and nature of the contamination present, and to determine its potential for the pollution of the water environment. The method and extent of this investigation shall be agreed with the Local Planning Authority prior to commencement of the work. Details of appropriate measures to prevent pollution of groundwater and surface water, including provisions for monitoring, shall then be submitted to and approved in writing by the Local Planning Authority before the development commences. The development shall then proceed in strict accordance with the measures approved. Reason: To prevent pollution of the water environment.
Appeal
No appeal lodged.
Updates
These Planning Application Details were returned live from our back office database, and as such are as up to date as when the page was retrieved.