Application registered
Consultation
period
Application under consideration
Decision
made
Description
Demolition of existing house and replacement with 1 single family house.(As amended by plans accompanying letter from agent dated 13 May 1997 & amplified by letters, from agent dated 15 May and from applicant dated 16 May 1997).
Grid Reference
459343/183525
Applicant
Mr & Mrs McCall
13 Old Square
Lincoln's Inn
LONDON
WC2A 3UA
Agent
John Outram Associates
44 Connaught Square
LONDON
W2 2NL
Consultation / Notification
No further Representations on this application will be accepted.
Consultations / Notifications to date are shown below.
Name / Number
Date Sent
Response Date
c/o Mrs. S. A. Abbots
9 Meadow Close,
Moulsford,
WALLINGFORD, Oxon OX10 9JL
27 05 1997
Tech.Dir,Babtie Engineering S.
The Wedges
Ferry Lane
Moulsford
WALLINGFORD Oxon
El Pirata
Ferry Lane
Moulsford
WALLINGFORD Oxon
16 04 1997
Waters Edge
Ferry Lane
Moulsford
WALLINGFORD, Oxon, OX10 9JF
24 04 1997
Huesca
Ferry Lane
Moulsford
WALLINGFORD Oxon
S.Clarke,Snr.Pl.Liaison Off.
28 04 1997
c/o Mr C E Palmer,
Oakham
Cross Keys Road
South Stoke
READING
RG8 0JT
Application Progress
Date Received
4th April 1997
Registration Date
4th April 1997
Start Consultation Period
4th April 1997
End Consultation Period
8th May 1997
Target Decision Date
30th May 1997
Decision
Planning Permission on 4th June 1997
Conditions / Refusal Reasons
That the development must be begun not later than the expiration of five
years beginning with the date of this permission and if this condition
is not complied with this permission shall lapse.
Reason: By virtue of Sections 91 to 95 of the Town and Country Planning
Act 1990.
That samples of the materials to be used for the roof shall be submitted
to and approved in writing by the Local Planning Authority before any
development commences.
Reason: To ensure that the details of the development are satisfactory.
That prior to the construction of the dwelling hereby permitted, a
sample panel of the proposed finishes for the external walls shall
be constructed on the site. The panel shall include the final
finished colours and textures of the render. Construction of the
dwelling shall not commence until the colours and textures of the
proposed render have been agreed in writing by the Local Planning
Authority and the panel shall remain on site until construction
of the dwelling has been completed.
Reason: To ensure that the details of the development are satisfactory.
That the existing trees on the land shall be protected whilst
development operations are in progress, in accordance with a scheme
to be first agreed in writing with the Local Planning Authority and
to be implemented prior to the commencement of the development. The
scheme shall include the method of construction of the footings and
foundations in the vicinity of the Coastal Redwood.
Reason: To safeguard trees which are visually important.