Conditions / Refusal Reasons
That the development must be begun not later than the expiration of five
years beginning with the date of this permission and if this condition
is not complied with this permission shall lapse.
Reason: By virtue of Sections 91 to 95 of the Town and Country Planning
Act 1990.
That samples of the materials to be used for the roof shall be submitted
to and approved in writing by the Local Planning Authority before any
development commences.
Reason: To ensure that the details of the development are satisfactory.
That the development shall be carried out strictly in accordance with the
description of the development, plans and specifications contained in the
application, subject to the amendments referred to above, and subject to
the conditions hereby imposed.
Reason: To secure the proper planning of the locality.
That a scheme for the landscaping of the site, including the planting of
live trees and shrubs, the treatment of the access road and hardstandings,
and the provision of boundary fencing and screen walling shall be
submitted to and approved in writing by the Local Planning Authority
prior to the commencement of the development hereby permitted. The
scheme shall be implemented as approved within 12 months of the
commencement of the approved development and thereafter be maintained in
accordance with the approved scheme to the complete satisfaction of the
Local Planning Authority. In the event of any of the trees or shrubs so
planted dying or being seriously damaged or destroyed within 3 years of
the completion of the development, a new tree or shrub or equivalent
number of trees or shrubs, as the case may be, of a species first
approved by the Local Planning Authority, be planted and properly
maintained in a position or positions first approved by the Local
Planning Authority.
Reason: To help to assimilate the development into its surroundings.
That the parking provision shall be as shown on the deposited drawing,
reference 9709 04 A all constructed, surfaced and laid out, retained
and maintained to the satisfaction of the Local Planning Authority.
Reason: To comply with the Local Planning Authority's vehicle parking
standards and to protect local amenities.
That no rooflights shall be inserted in the north west or north east
elevations of the building without the prior approval of the Local
Planning Authority.
Reason: To ensure that the details of the development are satisfactory.
That development shall not begin until a detailed specification of the
type, design and external finish of all windows and external doors has
been submitted to and approved in writing by the Local Planning
Authority.
Reason: To ensure that the details of the development are satisfactory.
That the development shall not begin until ventilation details are
submitted to and approved in writing by the Local Planning Authority.
Reason: To ensure that the details of the development are satisfactory.