Conditions / Refusal Reasons
That notwithstanding any indications as to these matters which have been
given in this application, no development shall be started until full
details of the following have been submitted to, and approved in writing
by the Local Planning Authority:-
the plans and elevations of all buildings;
the colour and type of facing materials to be used for the external
walls and roofs;
the provision to be made on the site for the garaging and parking of
motor vehicles in accordance with the Local Planning Authority's
approved standards;
the layout of the site and means of access;
a scheme for the landscaping of the site including the planting of live
trees, the treatment of forecourts and driveways, and the provision of
boundary fencing and screen walling.
Reason: By virtue of Sections 91 to 95 of the Town and Country Planning
Act 1990.
That application for the approval of the reserved matters referred to in
Condition 1 above shall be made to the Local Planning Authority not later
than three years from the date of this permission, and if this condition
is not complied with this permission shall lapse.
Reason: By virtue of Sections 91 to 95 of the Town and Country Planning
Act 1990.
That the development to which this permission relates shall be begun not
later than whichever is the later of the following dates:
(a) the expiration of five years from the date of this permission; or
(b) the expiration of two years from the final approval of the reserved
matters, or, in the case of approval on different dates, the final
approval of the last such matter to be approved.
Reason: By virtue of Sections 91 to 95 of the Town and Country Planning
Act 1990.
That the existing trees on the land shall be protected to the
satisfaction of the Local Planning Authority whilst development
operations are in progress, in accordance with a scheme to be first
agreed in writing with the Local Planning Authority and to be implemented
prior to the commencement of the development.
Reason: To safeguard trees which are visually important.
That all buildings and the materials therefrom shall be removed from the
site within one month of works commencing.
Reason: To safeguard the character and appearance of the locality.