Application registered
Consultation
period
Application under consideration
Decision
made
Description
Single storey extension to provide additional public conveniences.
Location
Mill Meadows Pavilion, Mill Meadows, Henley-on-Thames.
Grid Reference
476520/182217
Applicant
Henley-on-Thames Town Council
Council Offices
Town Hall
HENLEY-ON-THAMES
Oxon RG9 2AQ
Agent
Architect Design Partnership
Studio 36
Kingly Court
Kingly Street
LONDON W1R 5LE
Consultation / Notification
No further Representations on this application will be accepted.
Consultations / Notifications to date are shown below.
Name / Number
Date Sent
Response Date
c/o Mrs. J. E. Pickett
Town Hall,
Market Place,
HENLEY-ON-THAMES,
Oxon RG9 2AQ
28 05 1996
Tech.Dir,Babtie Engineering S.
03 05 1996
Environmental Health South
30 04 1996
Wokingham District Council
16 05 1996
Technical Director, Babtie
S.Clarke,Snr.Pl.Liaison Off.
03 05 1996
Application Progress
Date Received
16th April 1996
Registration Date
17th April 1996
Start Consultation Period
17th April 1996
End Consultation Period
24th May 1996
Target Decision Date
12th June 1996
Decision
Planning Permission on 11th June 1996
Conditions / Refusal Reasons
That the development must be begun not later than the expiration of five
years beginning with the date of this permission and if this condition
is not complied with this permission shall lapse.
Reason: By virtue of Sections 91 to 95 of the Town and Country Planning
Act 1990.
That the materials to be used for the external walls and roof shall be of
the same colour, type and texture as those used on the existing building.
Reason: To ensure that the details of the development are satisfactory.
That existing ground levels on the site shall not be raised.
Reason: To prevent the increased risk of flooding due to impedance of
flood flows and reduction of flood storage capacity.
That no spoil or materials shall be deposited or stored on that part of
the site lying within the area of land liable to flood as shown on maps
held by the Environment Agency.
Reason: To prevent the increased risk of flooding due to impedance of
flood flows and reduction of flood storage capacity.
Updates