Application registered
Consultation
period
Application under consideration
Decision
made
Description
Construction of new swimming pool building and limited alteration works in north court yard. (As amended by Drawing Nos.96.39.1A, 3A, 4A & 5A accompanying Agents letter dated 22 July 1996 and by additional information accompanying Agents letters dated 9 September 1996, 18 September 1996 and 16 October 1996).
Location
Woodperry House, Stanton St John
Grid Reference
457670/210497
Applicant
Mr & Mrs K Moussavi
56 Old Road
Headington
OXFORD
OX3 7LL
Agent
Hall & Ensom, Chartered Surs
3 Meadow Court
High Street
WITNEY, Oxon
OX8 6LP
Constraints
Grade I Listed Building
Consultation / Notification
No further Representations on this application will be accepted.
Consultations / Notifications to date are shown below.
Name / Number
Date Sent
Response Date
c/o Mr.Godfrey Broad
99 High Street
Wheatley
OXFORD OX33 1XP
10 10 1996
Counc for British Archaeology
Royal Comm. on Hist.Mon.(Eng)
Soc. for Protection Anc. Build
Ancient Monuments Society
Application Type
Other
(Listed Bldg. Consent)
Application Progress
Date Received
21st May 1996
Registration Date
22nd May 1996
Start Consultation Period
22nd May 1996
End Consultation Period
21st June 1996
Target Decision Date
17th July 1996
Decision
Listed Building Consent on 29th November 1996
Conditions / Refusal Reasons
That the works hereby permitted shall be begun before the expiration of
five years from the date of this consent.
Reason: By virtue of Section 18 of the Planning (Listed Buildings and
Conservation Areas) Act 1990.
That the works shall be carried out strictly in accordance with the
description, plans and specifications contained in the application,
subject to the amendments referred to above, and subject to the conditions
hereby imposed.
Reason: To ensure that the details of the works are satisfactory.
That samples of all materials to be used in the external construction and
finishes of the development hereby permitted shall be submitted to and
approved in writing by the Local Planning Authority before the
development is commenced.
Reason: To safeguard the character of the area.
That cast iron rainwater goods shall be used for any alterations to the
existing buildings.
Reason: To ensure that the details of the works are satisfactory.
That works shall not begin until a detailed specification of the type,
design and external finish of all windows, gates and external doors
has been submitted to and approved in writing by the Local Planning
Authority.
Reason: To ensure that the details of the works are satisfactory.
That prior to the commencement of the works hereby approved, full
working drawings including details of all photovoltaic and solar cells
shall be submitted to and approved in writing by the Local Planning
Authority.
Reason: To ensure that the details of the works is satisfactory.
No works shall commence on site until the applicant has been
responsible for organising an archaeological watching brief, to be
maintained during the period of construction/ground works affecting
below ground archaeological deposits and the historic fabric of the
building. The watching brief shall be carried out in accordance with
a written specification and by a professional archaeological
organisation that has first been agreed in writing by the Local
Planning Authority.
Reason: To safeguard the recording and inspection of matters of
archaeological importance on the site and the identification
and recording of features of historic and/or archaeological
interest associated with the fabric of the building.