Application registered
Consultation
period
Application under consideration
Decision
made
Description
Demolition of existing clubhouse and construction of new pavilion on two floors. (As amended by Drawing Nos. 9577/1B, 3A and 2A, and as amplified by Agents letters dated 13 May 1996, 31 May 1996 and 1 July 1996).
Location
Tiddington Cricket Club, Albury View, Tiddington
Grid Reference
465123/205020
Applicant
Tiddington Cricket Club
Albury View
TIddington
OXFORD
Agent
Michael Vaughton Associates
100 Church Road
Wheatley
OXFORD
OX33 1LZ
Consultation / Notification
No further Representations on this application will be accepted.
Consultations / Notifications to date are shown below.
Name / Number
Date Sent
Response Date
c/o Mrs. Z M Knight
24 Albury View
Tiddington
THAME
Oxon OX9 2LY
10 10 1996
Tech.Dir,Babtie Engineering S.
19 03 1996
Technical Director, Babtie
Snr.Planning Liaison Officer
13 08 1996
Dir. of Environmental Services
Application Progress
Date Received
29th February 1996
Registration Date
4th March 1996
Start Consultation Period
4th March 1996
End Consultation Period
5th April 1996
Target Decision Date
29th April 1996
Decision
Planning Permission on 8th October 1996
Conditions / Refusal Reasons
That the development must be begun not later than the expiration of five
years beginning with the date of this permission and if this condition
is not complied with this permission shall lapse.
Reason: By virtue of Sections 91 to 95 of the Town and Country Planning
Act 1990.
That the walls of the building shall be constructed with dark-stained
timber boarding.
Reason: To ensure that the details of the development are satisfactory.
That the roof of the building shall be covered with plain clay tiles
a sample of which shall first have been submitted to and approved in
writing by the Local Planning Authority before the development commences.
Reason: To ensure that the details of the development are satisfactory.
That no development shall take place until there has been submitted to
and approved in writing by the Local Planning Authority a scheme of
landscaping which shall include indications of all existing trees and
hedgerows on the land, and details of any to be retained, together with
measures for their protection in the course of development; and which
shall include provision of a five metre wide buffer zone to the
eastern boundary of the site, adjacent to the brook.
Reason: To protect local amenities.
That all planting, seeding or turfing comprised in the approved scheme
of landscaping shall be carried out in the first planting and seeding
seasons following the occupation of the buildings or the completion of
the development, whichever is the sooner; and any trees or plants which
within a period of 5 years from the completion of the development die,
are removed or become seriously damaged or diseased shall be replaced
in the next planting season with others of similar size and species,
unless the Local Planning Authority gives written consent to any
variation.
Reason: To help to assimilate the development into its surroundings.
That details of surface water drainage works shall be submitted to and
approved in writing by the Local Planning Authority prior to the
development commencing.
Reason: In the interests of public health.
That the building shall only be used by, or in conjunction with,
Tiddington Cricket Club.
Reason: In the interests of highway safety and convenience.
Updates
These Planning
Application Details were returned live from our back office database,
and as such are as up to date as when the page was retrieved.