Description
Variation of condition 7 (BREEAM final certificate) on application P21/S2646/FUL (The construction of a new single storey pavilion providing sports changing rooms and a multi-functional community space together with related facilities. External hard and soft landscaping, sports and play equipment, bicycle storage and improved parking arrangements) - to change the implementation from pre occupation to within 6 months of occupation.
Location
St Edmonds Park Park Road Didcot OX11 8QE
Grid Reference
/
Applicant
Didcot Town Council
Council Offices
Britwell Road
Didcot
OX11 7HN
Agent
Oxford Architects LLP
Bagley Croft
Hinksey Hill
Oxford
OX1 5BS
Case Officer
Sharon Crawford
Telephone: 01235 422600
Email: planning@southoxon.gov.uk
Consultation / Notification
No further Representations on this application will be accepted.

Consultations / Notifications to date are shown below. If the response has been scanned, you can access the document by clicking the folder icon alongside the relevant consultee. Folders with a
*
alongside them indicate new content within the folders (i.e. new documents added within the last 7 days)

Name / Number
Date Sent
Response Date
Scanned Response
 
Didcot Town Council
Council Offices
Britwell Road
DIDCOT
Oxon
OX11 7JN
01 03 2024
 
Parklife
47A Park Road
Didcot
OX11 8QL
01 03 2024
 
47 Park Road
Didcot
OX11 8QL
01 03 2024
 
Application Type
Minor (Section 73)
Application Progress
Date Received  
26th February 2024
Registration Date  
26th February 2024
Start Consultation Period  
1st March 2024
End Consultation Period  
22nd March 2024
Target Decision Date  
22nd April 2024
Decision
Planning Permission on 22nd April 2024
Conditions / Refusal Reasons
Development has commenced. This condition has been removed.

That the development hereby approved shall be carried out in accordance with the details shown on the following approved plans, A-001, and the following approved plans from application P21/S2646/FUL, A-001, A-201, A-202, A-200, A-100 Rev A, TLS.1, TLS.2, A-002 and A-003 Rev A except as controlled or modified by conditions of this permission. Reason: To secure the proper planning of the area in accordance with Development Plan policies.

The tree protection measures set out in the Arboricultural Method Statement and Tree Protection Plan ref 22204 (15 December 2022) approved under application P22/S4635/DIS shall be put in place as approved. Thereafter the development shall be carried out in accordance with the approved details with the agreed measures being kept in place during the entire course of development. Reason: To safeguard trees which are visually important in accordance with Policies ENV1, DES1, and DES2 of the South Oxfordshire Local Plan 2035.

The surface water drainage works shall be carried out in accordance with the details submitted and approved under application P22/S4635/DIS prior to the first occupation of the development hereby approved. Reason: To prevent pollution and flooding in accordance with Policies ENV12 and EP4 of the South Oxfordshire Local Plan 2035.

The foul water drainage works shall be carried out in accordance with the details submitted and approved under application P22/S4635/DIS prior to the first occupation of the development hereby approved. Reason: To ensure the proper provision of foul water drainage and to ensure flooding and pollution is not exacerbated in the locality in accordance with policy EP4 of the South Oxfordshire Local Plan 2035.

The development shall accord with the BREEAM pre-assessment report approved via condition discharge application P22/S4635/DIS. Reason: To ensure high standards of sustainable design and construction in accordance with policy DES10 of the South Oxfordshire Local Plan 2035.

Within 6 months of the first use of the building (other than the construction phase) a final BREEAM certificate shall have been submitted to and approved in writing by the local planning authority. The final certificate must demonstrate that BREEAM (or any such equivalent national measure of sustainable national measure of sustainable building which replaces that scheme) rating 'Very Good' has been achieved for this development. The development shall achieve BREEAM level 'Very Good' unless otherwise agreed in writing by the Local Planning Authority. Reason: To ensure high standards of sustainable design and construction in accordance with policy DES10 of the South Oxfordshire Local Plan 2035.

The building shall be constructed in the materials and finishes approved under application P22/S4635/DIS prior to the first occupation of the development hereby approved unless otherwise agreed in writing. Reason: In the interests of the visual appearance of the development in accordance with Policies DES1 and DES2 of the South Oxfordshire Local Plan 2035.

Cycle parking facilities shall be provided prior to the occupation of the development hereby approved, in accordance with the details approved on drawing nos 8030 Rev P1 and 1020 Rev C5 approved under application P23/S3620/DIS. The approved cycle parking facilities shall be retained for such use thereafter. Reason: To encourage the use of cycles as a means of transport in accordance with Policy TRANS5 of the South Oxfordshire Local Plan 2035.

Within 3 months of occupation the landscaping scheme (including hard surfaces) as shown on the approved plans and the revised planting plan submitted in support of this application shall be implemented and maintained in accordance with the approved scheme. In the event of any of the soft landscaping so planted dying or being seriously damaged or destroyed within 5 years of the completion of the development, replacement planting, as the case may be, of a species first approved by the Local Planning Authority, shall be planted and properly maintained in a position or positions first approved in writing by the Local Planning Authority. Reason: To help to assimilate the development into its surroundings in accordance with Policies ENV1, DES1 and DES2 of the South Oxfordshire Local Plan 2035.

Within 3 months of occupation of the development hereby approved, the parking and turning areas shall be provided in accordance with the approved plan 1001 Rev P1 and shall be constructed, laid out, surfaced, drained and completed to be compliant with sustainable drainage (SuDS) principles, and shall be retained unobstructed except for the parking of vehicles associated with the development at all times. Reason: In the interests of highway safety and in accordance with Policy TRANS5 of the South Oxfordshire Local Plan 2035.

Condition 12 removed. Construction is at a stage where the contamination condition is no longer required.

Upon completion of the development any external lighting shall be designed and installed so the main beam angle is not directed towards any receptors. To prevent glare, the lighting sources (bulbs and reflectors) shall not be visible from any adjacent properties. The luminaire's front glazing shall be kept parallel to the ground surface (i.e. facing downwards). This scheme shall also ensure that light trespass into the windows of any light sensitive premises shall not have a Vertical Illuminance greater than 10 Lux (in accordance with the Institution of Lighting Engineers Guidance Notes for the Reduction of Obtrusive Light GN01). Reason: To protect the appearance of the area, the environment and wildlife, and local residents from light pollution in accordance with Policy ENV12 of the South Oxfordshire Local Plan 2035.
Appeal
No appeal lodged.
Updates