Consultation / Notification
No further Representations on this application will be accepted.
Consultations / Notifications to date are shown below.
If the response has been scanned, you can access the document by clicking the folder icon alongside the relevant consultee. Folders with a
*
alongside them indicate new content within the folders (i.e. new documents added within the last 7 days)
Name / Number
Date Sent
Response Date
Scanned Response
Goring on Thames Parish Council
c/o Sarah Edmunds
Gardiner Pavilion
Upper Red Cross Road
Goring
READING
RG8 9BD
27 02 2024
45 Gatehampton Road
Goring
Reading
RG8 0EN
Byfield
47 Gatehampton Road
Goring
Reading
RG8 0EN
28 02 2024
Ryecroft
43 Gatehampton Road
Goring
Reading
RG8 0EN
Ecology Team (South and Vale)
26 03 2024
South -Highways Liaison Officer (Oxfordshire County Council)
07 03 2024
Conditions / Refusal Reasons
The development to which this permission relates must be begun not later than the expiration of three years beginning with the date of this permission.
Reason: By virtue of Sections 91 to 95 of the Town and Country Planning Act 1990 as amended by section 51 of the Planning and Compulsory Purchase Act 2004.
That the development hereby approved shall be carried out in accordance with the details shown on the following approved plans, 3912 - 206 H, 3912 - 200 E, 3912 - 208 D, 3912-102, 3912 - 203 F, 3912 - 204 F, 3912 - 202 D, 3912 - 101, 3912 - 201 D, 3912 - 100, 3912 - 205 D, 3912 - 209 and 3912 - 102, except as controlled or modified by conditions of this permission.
Reason: To secure the proper planning of the area in accordance with Development Plan policies.
The exterior of the development hereby permitted shall only be constructed in the materials specified on the plans/supporting documents hereby approved or in materials which shall previously have been approved in writing by the Local Planning Authority.
Reason: In the interests of the visual appearance of the development in accordance with Policies DES1 and DES2 of the South Oxfordshire Local Plan 2035.
Prior to the first occupation of the development hereby approved, the parking and turning areas shall be provided in accordance with the approved plan 3912 - 206 H and shall be constructed, laid out, surfaced, drained and completed to be compliant with sustainable drainage (SuDS) principles, and shall be retained unobstructed except for the parking of vehicles associated with the development at all times.
Reason: In the interests of highway safety and in accordance with Policy TRANS5 of the South Oxfordshire Local Plan 2035.
Prior to the construction of the development hereby approved above slab level, details of cycle parking facilities shall be submitted to and approved in writing by the Local Planning Authority. The cycle parking shall be implemented prior to first use of the development and thereafter retained in accordance with the approved details.
Reason: To encourage the use of cycles as a means of transport in accordance with Policy TRANS5 of the South Oxfordshire Local Plan 2035.
Prior to first occupation, all carbon reduction energy efficiency measures shall be implemented in accordance with the Energy Statement and SAP calculations (produced by Melin Consultants dated 03 January 2024) hereby approved and a Verification Report shall be submitted to the Local Planning Authority and approved in writing. The Verification Report shall demonstrate (with photographic evidence) that the energy efficiency measures have been implemented. These measures shall be retained and maintained as such thereafter in accordance with the Energy Statement and Verification Report.
Reason: To ensure high standards of sustainable design and construction in accordance with Policy DES10 of the South Oxfordshire Local Plan 2035.
Prior to the first occupation of the dwelling hereby approved an Electric Vehicle Charging Point shall be installed.
Reason: To ensure sustainable forms of transport are provided in accordance with Policy DES8 of the South Oxfordshire Local Plan 2035.
Prior to any works starting on site, a sensitive lighting strategy for bats shall be submitted to and approved in writing by the Local Planning Authority. The strategy shall:
a) identify those areas/features on site that are particularly sensitive for bats and that are likely to cause disturbance in or around their breeding sites or resting places or along important routes used to access key areas of their territory, for example for foraging; and
b) show how and where external lighting will be installed (through provision of appropriate lighting contour plans and technical specifications) so that it can be clearly demonstrated that areas to be lit will not disturb or prevent bats using their territory or having access to their breeding sites or resting places.
All external lighting shall be installed in accordance with the specifications and locations set out in the strategy. Under no circumstances should any other external lighting be installed without the prior consent from the local planning authority. If no external lighting is proposed, this should be confirmed in writing to the Local Planning Authority before any works start on site.
Reason: to avoid impacts on bats from insensitive external lighting in line with Policy ENV2 of the South Oxfordshire Local Plan
The first floor window in the north west elevation of the dwelling hereby permitted shall be glazed in obscure glass with a minimum of level 3 obscurity, and shall be fixed shut with the exception of a top hung openable fanlight (or other means of opening to be first agreed in writing by the Local Planning Authority) prior to the first occupation of the accommodation and it shall be retained as such thereafter.
Reason: To ensure that the development is not unneighbourly in accordance with Policy DES6 of the South Oxfordshire Local Plan 2035.