The development to which this permission relates must be begun not later than the expiration of three years beginning with the date of this permission.
Reason: By virtue of Sections 91 to 95 of the Town and Country Planning Act 1990 as amended by section 51 of the Planning and Compulsory Purchase Act 2004.
Related application(s):
P23/S2773/DIS,
P24/S0691/DISThat the development hereby approved shall be carried out in accordance with the details shown on the following approved plans, 3 Rev A, 4 Rev A, 1 Rev A, 5 Rev B, 6, 7 and 2 Rev A, except as controlled or modified by conditions of this permission.
Reason: To secure the proper planning of the area in accordance with Development Plan policies.
Related application(s):
P23/S2773/DIS,
P24/S0691/DISExcept in the case of any building work hereby permitted, no change in the levels of the land shall take place unless in accordance with a detailed scheme which shall have been submitted to and approved in writing by the Local Planning Authority before any development commences on site. The scheme shall include details of existing and proposed ground levels.
Reason: In the interests of the visual appearance of the development in accordance with Policies DES1 and DES2 of the South Oxfordshire Local Plan 2035.
Related application(s):
P24/S0691/DISNo development above slab level shall take place until a photographic schedule of all materials to be used in the external construction and finishes of the development hereby permitted has been submitted to and approved in writing by the Local Planning Authority.
Reason: In the interests of the visual appearance of the development in accordance with Policies DES1 and DES2 of the South Oxfordshire Local Plan 2035.
The first floor bathroom window in the west-facing side elevation facing No.12 of the development hereby permitted shall be glazed in obscure glass with a minimum of level 3 obscurity, and shall be fixed shut with the exception of a top hung openable fanlight (or other means of opening to be first agreed in writing by the Local Planning Authority) prior to the first occupation of the accommodation and it shall be retained as such thereafter.
Reason: To ensure that the development is not unneighbourly in accordance with Policy DES6 of the South Oxfordshire Local Plan 2035.
Notwithstanding the provisions of the Town and Country (General Permitted Development Order) 2015 (or any Order revoking or re-enacting that Order), no development as specified in Schedule 2, Part 1, Class A - Extensions; Class E - Outbuildings shall be undertaken without obtaining planning permission from the Local Planning Authority.
Reason: The specific circumstances of this site warrant the Local Planning Authority having control over any further development as specified in the condition to safeguard the amenities of the occupiers of the adjoining properties and the character of the area in accordance with Policies DES1, DES2 and DES6 of the South Oxfordshire Local Plan 2035.
Prior to first occupation, all carbon reduction energy efficiency measures shall be implemented in accordance with the Energy Statement hereby approved and a Verification Report shall be submitted to the Local Planning Authority and approved in writing. The Verification Report shall demonstrate (with photographic evidence) that the energy efficiency measures have been implemented. These measures shall be retained and maintained as such thereafter in accordance with the Energy Statement and Verification Report.
Reason: To ensure high standards of sustainable design and construction in accordance with Policy DES10 of the South Oxfordshire Local Plan 2035.
Details of the location and specification of any external heating or energy generation system to be used in the development hereby permitted shall be submitted to and approved in writing by the Local Planning Authority prior to installation.
Reason: To ensure high standards of sustainable design and construction and an acceptable visual and amenity impact in accordance with Policies DES1, DES2, DES6, DES10, ENV1 and ENV12 of the South Oxfordshire Local Plan 2035.
Prior to the first occupation of the development hereby approved, the parking and turning areas shall be provided in accordance with the approved plan 4 Rev A and shall be constructed, laid out, surfaced, drained and completed to be compliant with sustainable drainage (SuDS) principles, and shall be retained unobstructed except for the parking of vehicles associated with the development at all times.
Reason: In the interests of highway safety and in accordance with Policy TRANS5 of the South Oxfordshire Local Plan 2035.
Prior to the commencement of the development hereby approved/Prior to the construction of any development above slab level a scheme for the landscaping of the site, including the planting of live trees and shrubs, the treatment of the access road and hard standings, and the provision of boundary treatment shall be submitted to and approved in writing by the Local Planning Authority. These details shall include schedules of new trees and shrubs to be planted (noting species, plant sizes and numbers/densities), the identification of the existing trees and shrubs on the site to be retained (noting species, location and spread), any earth moving operations and finished levels/contours, and an implementation programme. The scheme shall be implemented prior to the first occupation or use of development and thereafter be maintained in accordance with the approved scheme. In the event of any of the trees or shrubs so planted dying or being seriously damaged or destroyed within 5 years of the completion of the development, a new tree or shrub or equivalent number of trees or shrubs, as the case may be, of a species first approved by the Local Planning Authority, shall be planted and properly maintained in a position or positions first approved in writing by the Local Planning Authority.
Reason: To help to assimilate the development into its surroundings in accordance with Policies ENV1, DES1 and DES2 of the South Oxfordshire Local Plan 2035.
Prior to the commencement of development, with the exception of any demolition, a full surface water drainage scheme following the surface water drainage hierarchy as set out in Ciria C753 and by providing infiltration testing undertaken in accordance with BRE 365, shall be submitted to, and approved in writing by, the Local Planning Authority. The design of the surface water drainage system will be in accordance with the non-statutory technical standards for sustainable drainage systems, including details of the levels, size, position and construction of drainage works. The drainage scheme shall be sized to accommodate a minimum of the worst case 1 in 30 year storm, with evidence to demonstrate that the site can accommodate the worst case 1:100 year storm + 40% Climate Change storm, without any flows exiting up to this storm event and any storage on site not causing a nuisance or flooding to property. The approved scheme shall be implemented in accordance with the approved details prior to the occupation of the development hereby approved.
Reason: To ensure the proper provision of surface water drainage and to ensure flooding is not exacerbated in the locality in accordance with Policy EP4 of the South Oxfordshire Local Plan 2035.
Prior to the first occupation of the development hereby approved, an Electric Vehicle Charging Point shall be installed for the dwelling and thereafter retained as such.