The development to which this permission relates must be begun not later than the expiration of three years beginning with the date of this permission.
Reason: By virtue of Sections 91 to 95 of the Town and Country Planning Act 1990 as amended by section 51 of the Planning and Compulsory Purchase Act 2004.
Related application(s):
P24/S1325/DISThat the development hereby approved shall be carried out in accordance with the details shown on the following approved plans, 58PKV.P11 and 58PKV.P10, except as controlled or modified by conditions of this permission.
Reason: To secure the proper planning of the area in accordance with Development Plan policies.
Related application(s):
P24/S1325/DISNo development above slab level shall take place until a photographic schedule of all materials to be used in the external construction and finishes of the development hereby permitted has been submitted to and approved in writing by the Local Planning Authority.
Reason: In the interests of the visual appearance of the development in accordance with Policies DES1 and DES2 of the South Oxfordshire Local Plan 2035.
Related application(s):
P24/S1325/DISPrior to the commencement of any site works (including demolition or site clearance) a protected area shall be designated for all existing trees which are shown to be retained, and the trees shall be protected in accordance with a scheme which complies with the current edition of BS 5837: "Trees in relation to design, demolition and construction" that shall first have been submitted to, and approved in writing by, the Local Planning Authority. The agreed measures shall be kept in place during the entire course of development. This shall also include a detailed tree work specification to accord with BS 3998 (Tree Work Recommendations) of trees to be pruned and removed.
Reason: To safeguard trees which are visually important in accordance with Policies ENV1, DES1, and DES2 of the South Oxfordshire Local Plan 2035.
Related application(s):
P24/S1325/DISPrior to the commencement of development, with the exception of any demolition, a full foul water drainage scheme shall be submitted to and approved in writing by the Local Planning Authority. The drainage scheme shall include details of, method, levels, size, position and construction of the drainage scheme.
Reason: To ensure the proper provision of foul water drainage and to ensure flooding and pollution is not exacerbated in the locality in accordance with policy EP4 of the South Oxfordshire Local Plan 2035.
Notes
Full construction details of all foul water drainage components must be provided.
Drainage layout from SVP must be provided.
Related application(s):
P24/S1325/DISPrior to the commencement of development, with the exception of any demolition, a full surface water drainage scheme shall be submitted to, and approved in writing by, the Local Planning Authority. The design of the surface water drainage system shall be in accordance with the non-statutory technical standards for sustainable drainage systems, including details of BRE 365 soakage testing, levels, size, position and construction of all drainage works. The drainage scheme shall be sized to accommodate a minimum of the worst case 1 in 30 year storm, with evidence to demonstrate that the site can accommodate the worst case 1:100 year storm + 40% Climate Change storm, without any flows exiting up to this storm event and any storage on site not causing a nuisance or flooding to property. Should an outflow be required, then this must be restricted to QBAR. A surface water discharge to a Thames Water recorded foul sewer will not be permitted under any circumstance. The approved scheme shall be implemented in accordance with the approved details prior to the occupation of the development hereby approved.
Reason: To ensure the proper provision of surface water drainage and to ensure flooding is not exacerbated in the locality in accordance with Policy EP4 of the South Oxfordshire Local Plan 2035.
Notes
The hydraulic model must be run in the latest FEH format. Currently, this is FEH 22.
Cv values must be set at 0.95.
An exceedance plan must be provided.
The building must contain a bio retention feature. This could be in the form of a rain water planter.
Full construction details of all surface water drainage components including hard standing areas, must be provided.
Drainage layout from RWP must be provided.
Prior to the construction of the development hereby approved above slab level, details of cycle parking facilities shall be submitted to and approved in writing by the Local Planning Authority. The cycle parking shall be implemented prior to first use of the development and thereafter retained in accordance with the approved details.
Reason: To encourage the use of cycles as a means of transport in accordance with Policy TRANS5 of the South Oxfordshire Local Plan 2035.
Prior to the occupation of any dwelling, a SUDS compliance report prepared by an appropriately qualified Engineer must be submitted to and approved by the Local Planning Authority. This report must evidence that a sustainable drainage system has been installed and completed in accordance with the approved scheme (or detail any minor variations). This report should as a minimum cover the following;
1) Inclusion of as-built drawings in AOD. Levels of all drainage works and FFL must be included. Asbuilt drawings must be provided in PDF and DWG format.
2) Inspection details of SUDS features such as flow controls, storage features and
volumes and critical linking features or pipework undertaken, with appropriate photographs
and evidence of inspections incorporated,
3) Maintenance responsibilities,
4) Details of any remediation works required following the initial inspection,
5) Evidence that that remedial works have been completed.
6) Full CCTV survey of the whole network.
Reason: To ensure the proper provision of surface water drainage and to ensure flooding is not exacerbated in the locality in accordance with Policy EP4 of the South Oxfordshire Local Plan 2035.
Prior to the first occupation of the development, the existing means of access onto Park Road shall be improved and laid out and constructed strictly in accordance with the local highway authority's specifications and all ancillary works specified shall be undertaken.
Reason: In the interest of highway safety in accordance with Policy TRANS5 of the South Oxfordshire Local Plan 2035.
Prior to the first occupation of the development hereby approved, the parking and turning areas shall be provided in accordance with the approved plan 58PKV.P10 and shall be constructed, laid out, surfaced, drained and completed to be compliant with sustainable drainage (SuDS) principles, and shall be retained unobstructed except for the parking of vehicles associated with the development at all times.
Reason: In the interests of highway safety and in accordance with Policy TRANS5 of the South Oxfordshire Local Plan 2035.
Prior to first occupation, all carbon reduction energy efficiency measures shall be implemented in accordance with the Energy Statement hereby approved and a Verification Report shall be submitted to the Local Planning Authority and approved in writing. The Verification Report shall demonstrate (with photographic evidence) that the energy efficiency measures have been implemented. These measures shall be retained and maintained as such thereafter in accordance with the Energy Statement and Verification Report.
Reason: To ensure high standards of sustainable design and construction in accordance with Policy DES10 of the South Oxfordshire Local Plan 2035.
Prior to the first occupation of the development hereby approved, an Electric Vehicle Charging Point shall be installed for each dwelling and thereafter retained as such.
Reason: To ensure sustainable forms of transport in accordance with Policies TRANS5, ENV12 and EP1 of the South Oxfordshire Local Plan 2035.
Prior to the first occupation of the development one bird box per dwelling shall be erected on site in a suitable location and retained on site in perpetuity.
Reason: To secure net gains for biodiversity in accordance with Policy ENV3 of the South Oxfordshire Local Plan 2035.
The first floor bathrooms window in the north and south side elevations of the dwellings hereby permitted shall be glazed in obscure glass with a minimum of level 3 obscurity, and shall be fixed shut with the exception of a top hung openable fanlight (or other means of opening to be first agreed in writing by the Local Planning Authority) prior to the first occupation of the accommodation and it shall be retained as such thereafter.
Reason: To ensure that the development is not unneighbourly in accordance with Policy DES6 of the South Oxfordshire Local Plan 2035.