Conditions / Refusal Reasons
The development to which this permission relates must be begun not later than the expiration of three years beginning with the date of this permission.
Reason: By virtue of Sections 91 to 95 of the Town and Country Planning Act 1990 as amended by section 51 of the Planning and Compulsory Purchase Act 2004.
That the development hereby approved shall be carried out in accordance with the details shown on the following approved plans, 3873 - 210B, 3873 - 115, 3873 - 113A, 3873 - 213B, 3873 - 114A, 3873 - 214A, 3873 - 112B, 3873 - 212B, 3873 - 111B, 3873 - 211B, C2994-01 A, 3873 - 110B, C2994-02 A and 3873 - 215C, except as controlled or modified by conditions of this permission.
Reason: To secure the proper planning of the area in accordance with Development Plan policies.
Prior to the construction of any development above slab level a scheme for the landscaping of the site, including the planting of live trees and shrubs, shall be submitted to and approved in writing by the Local Planning Authority. These details shall include schedules of new trees and shrubs to be planted (noting species, plant sizes and numbers/densities), the identification of the existing trees and shrubs on the site to be retained (noting species, location and spread), any earth moving operations and finished levels/contours, and an implementation programme. The scheme shall be implemented prior to the first occupation or use of the development hereby approved and thereafter be maintained in accordance with the approved scheme. In the event of any of the trees or shrubs so planted dying or being seriously damaged or destroyed within 5 years of the completion of the development, a new tree or shrub or equivalent number of trees or shrubs, as the case may be, of a species first approved by the Local Planning Authority, shall be planted and properly maintained in a position or positions first approved in writing by the Local Planning Authority.
Reason: To help to assimilate the development into its surroundings in accordance with Policies ENV1, DES1 and DES2 of the South Oxfordshire Local Plan 2035.
Prior to the first occupation of the development hereby approved, the parking and turning areas shall be provided in accordance with the approved plan 3873/211 Rev B and shall be constructed, laid out, surfaced, drained and completed to be compliant with sustainable drainage (SuDS) principles, and shall be retained unobstructed except for the parking of vehicles associated with the development at all times.
Reason: In the interests of highway safety and in accordance with Policy TRANS5 of the South Oxfordshire Local Plan 2035.
Prior to the construction of the development hereby approved above slab level, details of cycle parking facilities shall be submitted to and approved in writing by the Local Planning Authority. The cycle parking shall be implemented prior to first use of the development and thereafter retained in accordance with the approved details.
Reason: To encourage the use of cycles as a means of transport in accordance with Policy TRANS5 of the South Oxfordshire Local Plan 2035.
Prior to first occupation, all carbon reduction energy efficiency measures shall be implemented in accordance with the Energy Statement hereby approved and a Verification Report shall be submitted to the Local Planning Authority and approved in writing. The Verification Report shall demonstrate (with photographic evidence) that the energy efficiency measures have been implemented. These measures shall be retained and maintained as such thereafter in accordance with the Energy Statement and Verification Report.
Reason: To ensure high standards of sustainable design and construction in accordance with Policy DES10 of the South Oxfordshire Local Plan 2035.
Prior to the first occupation of the development hereby approved, an Electric Vehicle Charging Point shall be installed for the new dwelling and thereafter retained as such.
Reason: To ensure sustainable forms of transport in accordance with Policies TRANS5, ENV12 and EP1 of the South Oxfordshire Local Plan 2035.
The tree protection details as shown in the approved Arboricultural Assessment Method Statement dated 4 July 2023 shall be put in place prior to any on site works including demolition and thereafter retained in situ for the duration of development.
Reason: To safeguard trees which are visually important in accordance with Policies ENV1, DES1, and DES2 of the South Oxfordshire Local Plan 2035.
The exterior of the development hereby permitted shall only be constructed in the materials specified on the plans/supporting documents hereby approved or in materials which shall previously have been approved in writing by the Local Planning Authority.
Reason: In the interests of the visual appearance of the development in accordance with Policies DES1 and DES2 of the South Oxfordshire Local Plan 2035.
That, unless as otherwise agreed in writing by the local planning authority the development shall be carried out in accordance with the Percolation Test Report, SUDS Report and Site Plan Proposed drwgno 3873-215C.
Reason: To ensure the proper provision of surface water drainage and to ensure flooding is not exacerbated in the locality in accordance with Policy EP4 of the South Oxfordshire Local Plan 2035.
The bat and bird box shown on drawing 3873/213 Rev B and 3873/215 Rev C shall be installed prior to occupation and retained on site in perpetuity.
Reason: to secure net gains for biodiversity in accordance with Policy ENV3 of the South Oxfordshire Local Plan 2035.
The air source heat pump hereby approved shall meet Microgeneration Installation Standard: MCS 020 to qualify as permitted development. If this MCS Certification cannot be met, the approved air source heat pumps shall be so installed, maintained, and operated so as to ensure that the rating noise level from the equipment does not exceed the background noise level at the boundary of the premises. Measurement and rating of noise for the purposes of this condition shall be in accordance with BS4142 (2014) 'Method for rating industrial and commercial sound'. The measurement location shall be 1 metre from the facade of the nearest noise sensitive receptor. In the event of unacceptable noise or vibration being caused by the installed plant, machinery and equipment, the persons responsible/owner shall investigate and undertake works to resolve the problem to the satisfaction of the local planning authority.
Reason: To protect the occupants of nearby residential properties from loss of amenity due to noise disturbance and in accordance with Policy ENV12 of the South Oxfordshire Local Plan 2035.