Application registered
Consultation
period
Application under consideration
Decision
made
Description
Confirmation that the building works comprising garage foundations and slab forming part of the development authorised by planning permission P19/S4692/HH have been lawfully carried out, and that the development authorised by that planning permission has accordingly been lawfully implemented within the timescale prescribed by condition no.1 thereof.
Location
Highwood House Upper Bolney Road Harpsden RG9 4AQ
Applicant
Mr A. McCutcheon
Highwood House Upper Bolney Road
Harpsden
Henley-on-Thames
Oxfordshire
RG9 4AQ
Agent
Domus Designs
1 Manor Cottages
Willow Court Lane
Moulsford
Walligford
OX10 9HX
Consultation / Notification
No further Representations on this application will be accepted.
Consultations / Notifications to date are shown below.
Name / Number
Date Sent
Response Date
Harpsden Parish Council
c/o Anne-Marie Scanlon
10 Horse Leys
Highland Park
Henley on Thames
RG9 1BQ
Application Type
Other
(Law. Dev. (existing))
Application Progress
Date Received
28th March 2023
Registration Date
28th March 2023
Target Decision Date
23rd May 2023
Decision
Certificate of Lawful Use or Development on 16th May 2023
Conditions / Refusal Reasons
The existing concrete foundations and slab level forming part of the approved erection of two storey side extension, infill stair tower and replacement 3 bay detached garage in relation to the development granted by planning permission P19/S4692/HH is lawful under section 191 of the Town and Country Planning Act 1990 and constitutes the material commencement of the approved development made within three years of the approval being issued.
Updates
These Planning
Application Details were returned live from our back office database,