Conditions / Refusal Reasons
The development to which this permission relates must be begun not later than the expiration of three years beginning with the date of this permission.
Reason: By virtue of Sections 91 to 95 of the Town and Country Planning Act 1990 as amended by section 51 of the Planning and Compulsory Purchase Act 2004.
That the development hereby approved shall be carried out in accordance with the details shown on the following approved plans, SHWD.P01B, except as controlled or modified by conditions of this permission.
Reason: To secure the proper planning of the area in accordance with Development Plan policies.
The exterior of the development hereby permitted shall only be constructed in the materials specified on the plans/supporting documents hereby approved or in materials which shall previously have been approved in writing by the Local Planning Authority.
Reason: In the interests of the visual appearance of the development in accordance with Policies DES1 and DES2 of the South Oxfordshire Local Plan 2035.
Prior to first occupation, all carbon reduction energy efficiency measures shall be implemented in accordance with the Energy Statement hereby approved and a Verification Report shall be submitted to the Local Planning Authority and approved in writing. The Verification Report shall demonstrate (with photographic evidence) that the energy efficiency measures have been implemented. These measures shall be retained and maintained as such thereafter in accordance with the Energy Statement and Verification Report.
Reason: To ensure high standards of sustainable design and construction in accordance with Policy DES10 of the South Oxfordshire Local Plan 2035.
Prior to first occupation of the dwelling hereby approved , the existing means of access onto Sherwood Road shall be improved and laid out and constructed strictly in accordance with the local highway authority's specifications and all ancillary works specified shall be undertaken.
Reason: In the interest of highway safety in accordance with Policy TRANS5 of the South Oxfordshire Local Plan 2035.
The vision splays shown on the approved plan SHWD P01 B shall not be obstructed by any object, structure, planting or other material with a height exceeding or growing above 0.6 metres as measured from carriageway level.
Reason: In the interest of highway safety in accordance with Policy TRANS5 of the South Oxfordshire Local Plan 2035.
Prior to the first occupation of the development hereby approved, the parking and turning areas shall be provided in accordance with the approved plan SHWD P01 B and shall be constructed, laid out, surfaced, drained and completed to be compliant with sustainable drainage (SuDS) principles, and shall be retained unobstructed except for the parking of vehicles associated with the development at all times.
Reason: In the interests of highway safety and in accordance with Policy TRANS5 of the South Oxfordshire Local Plan 2035.
Prior to the commencement of development, with the exception of any demolition, a full surface water drainage scheme following the surface water drainage hierarchy as set out in Ciria C753 and by providing infiltration testing undertaken in accordance with BRE 365, shall be submitted to, and approved in writing by, the Local Planning Authority. The design of the surface water drainage system will be in accordance with the non-statutory technical standards for sustainable drainage systems, including details of the levels, size, position and construction of drainage works. The drainage scheme shall be sized to accommodate a minimum of the worst case 1 in 30 year storm, with evidence to demonstrate that the site can accommodate the worst case 1:100 year storm +40% year Climate Change storm, without any flows exiting up to this storm event and any storage on site not causing a nuisance or flooding to property. The approved scheme shall be implemented in accordance with the approved details prior to the occupation of the development hereby approved.
Reason: To prevent pollution and flooding in accordance with Policies ENV12 and EP4 of the South Oxfordshire Local Plan 2035.
Prior to the first occupation of the development hereby approved, an Electric Vehicle Charging Point shall be installed for each dwelling and thereafter retained as such.
Reason: To ensure sustainable forms of transport in accordance with Policy TRANS5 of the South Oxfordshire Local Plan 2035.
Prior to the first occupation of the dwelling hereby approved, a bat box and a bird box shall be provided and thereafter retained.
Reason: To increase biodiversity within the site in accordance with policy ENV3 of the SOLP.