The development to which this permission relates must be begun not later than the expiration of three years beginning with the date of this permission.
Reason: By virtue of Sections 91 to 95 of the Town and Country Planning Act 1990 as amended by section 51 of the Planning and Compulsory Purchase Act 2004.
Related application(s):
P22/S1834/DIS,
P22/S2102/DIS,
P22/S2103/DISThat the development hereby approved shall be carried out in accordance with the details shown on the following approved plans, 11.079 GA04b, 11.079 GA02, 11.079 L01, 11.079 GA01 and OP1001, except as controlled or modified by conditions of this permission.
Reason: To secure the proper planning of the area in accordance with Development Plan policies.
The exterior of the development hereby permitted shall only be constructed in the materials specified on the plans/supporting documents hereby approved or in materials which shall previously have been approved in writing by the Local Planning Authority.
Reason: In the interests of the visual appearance of the development in accordance with Policies DES1 and DES2 of the South Oxfordshire Local Plan 2035 and to safeguard the character and appearance of the Kingston Blount Conservation Area in accordance with Policies ENV6 and ENV8 of the South Oxfordshire Local Plan 2035.
Prior to the commencement of any site works (including demolition or site clearance) a protected area shall be designated for all existing trees which are shown to be retained, and the trees shall be protected in accordance with a scheme which complies with the current edition of BS 5837: "Trees in relation to design, demolition and construction" that shall first have been submitted to, and approved in writing by, the Local Planning Authority. The agreed measures shall be kept in place during the entire course of development.
Reason: To safeguard trees which are visually important in accordance with Policies ENV1, DES1, and DES2 of the South Oxfordshire Local Plan 2035.
Prior to the commencement of development, a full surface water drainage scheme based on full infiltration unless evidenced exhausted, including details of the size, position and construction of drainage works, shall be submitted to, and approved in writing by, the Local Planning Authority. The drainage scheme shall be designed on BRE365 percolation testing results and to accommodate a 1 in 30 year storm + 40% CC and shall be implemented in accordance with the approved details prior to the occupation of the development hereby approved.
Reason: To ensure the proper provision of surface water drainage and to ensure flooding is not exacerbated in the locality.
Details of the replacement wall, gate and new gate piers, including a material schedule shall be submitted to and approved in writing by the Local Planning Authority prior to the erection of the replacement wall, gate and new gate piers. The wall, gate and gate piers shall thereafter be constructed in accordance with the approved details.
Reason: In the interests of the visual appearance of the development in accordance with Policies DES1 and DES2 of the South Oxfordshire Local Plan 2035 and to safeguard the character and appearance of the Kingston Blount Conservation Area in accordance with Policies ENV6 and ENV8 of the South Oxfordshire Local Plan 2035.
The flintwork on the exterior of the development hereby permitted shall be constructed using traditional knapped flint, individually laid as part of the construction and lime mortar.
Reason: In the interests of the visual appearance of the development in accordance with Policies DES1 and DES2 of the South Oxfordshire Local Plan 2035 and to safeguard the character and appearance of the Kingston Blount Conservation Area in accordance with Policies ENV6 and ENV8 of the South Oxfordshire Local Plan 2035.
The rooflights hereby approved shall be set flush with the plane of the roof in which they are to be inserted.
Reason: In the interests of the visual appearance of the development in accordance with Policies DES1 and DES2 of the South Oxfordshire Local Plan 2035 and to safeguard the character and appearance of the Kingston Blount Conservation Area in accordance with Policies ENV6 and ENV8 of the South Oxfordshire Local Plan 2035.
Prior to the first occupation of the development hereby approved, the parking and turning areas shall be provided in accordance with the approved plan (11.079 GA01) and shall be constructed, laid out, surfaced, drained and completed to be compliant with sustainable drainage (SuDS) principles, and shall be retained unobstructed except for the parking of vehicles associated with the development at all times.
Reason: In the interests of highway safety and in accordance with Policy TRANS5 of the South Oxfordshire Local Plan 2035.