Conditions / Refusal Reasons
The development to which this permission relates must be begun not later than the expiration of three years beginning with the date of this permission.
Reason: By virtue of Sections 91 to 95 of the Town and Country Planning Act 1990 as amended by section 51 of the Planning and Compulsory Purchase Act 2004.
That the development hereby approved shall be carried out in accordance with the details shown on the following approved plans, 1101-PL-05B, 1101-PL-07, 1101-PL-06, 1101-PL-01B and 1101-PL-02B, except as controlled or modified by conditions of this permission.
Reason: To secure the proper planning of the area in accordance with Development Plan policies.
No development above slab level shall take place until a photographic schedule of all materials to be used in the external construction and finishes of the development hereby permitted has been submitted to and approved in writing by the Local Planning Authority.
Reason: In the interests of the visual appearance of the development in accordance with Policies DES1 and DES2 of the South Oxfordshire Local Plan 2035.
Prior to the commencement of the development hereby approved, a biodiversity mitigation and enhancement strategy (BMES) shall be submitted to and approved in writing by the local planning authority. The BMES shall detail the working methods, measures and precautions to be followed onsite during the demolition and construction phases of development to avoid and minimise ecological impacts. The BMES shall also propose a scheme of ecological enhancements for the site, including as a minimum of one integrated bat box and barn owl nest box. Thereafter, the development shall be implemented in accordance with the approved BMES and all ecological enhancements provided onsite prior to first occupation.
Reason: To minimise the ecological impacts of development and to secure biodiversity enhancements onsite, in accordance with Policies ENV2 and ENV3 of the South Oxfordshire Local Plan and paragraphs 174 and 180 of the National Planning Policy Framework.
Prior to the commencement of development, with the exception of any demolition, a full surface water drainage scheme following the surface water drainage hierarchy as set out in Ciria C753 and by providing infiltration testing undertaken in accordance with BRE 365, shall be submitted to, and approved in writing by, the Local Planning Authority. The design of the surface water drainage system will be in accordance with the non-statutory technical standards for sustainable drainage systems, including details of the levels, size, position and construction of drainage works. The drainage scheme shall be sized to accommodate a minimum of the worst case 1 in 30 year storm, with evidence to demonstrate that the site can accommodate the worst case 1:100 year storm + 40% Climate Change storm, without any flows exiting up to this storm event and any storage on site not causing a nuisance or flooding to property. The approved scheme shall be implemented in accordance with the approved details prior to the occupation of the development hereby approved.
Reason: To prevent pollution and flooding in accordance with Policies ENV12 and EP4 of the South Oxfordshire Local Plan 2035.
Prior to the commencement of development, with the exception of any demolition, a full foul water drainage scheme shall be submitted to and approved in writing by the Local Planning Authority. The drainage scheme shall include details of, method, levels, size, position and construction of the drainage scheme.
Reason: To ensure the proper provision of foul water drainage and to ensure flooding and pollution is not exacerbated in the locality in accordance with policy EP4 of the South Oxfordshire Local Plan 2035.
Prior to the construction of any development above slab level a scheme for the landscaping of the site, including the planting of live trees and shrubs, the treatment of the access road and hard standings, and the provision of boundary treatment shall be submitted to and approved in writing by the Local Planning Authority. These details shall include schedules of new trees and shrubs to be planted (noting species, plant sizes and numbers/densities), the identification of the existing trees and shrubs on the site to be retained (noting species, location and spread), any earth moving operations and finished levels/contours, and an implementation programme. The scheme shall be implemented prior to the first occupation or use of development and thereafter be maintained in accordance with the approved scheme. In the event of any of the trees or shrubs so planted dying or being seriously damaged or destroyed within 5 years of the completion of the development, a new tree or shrub or equivalent number of trees or shrubs, as the case may be, of a species first approved by the Local Planning Authority, shall be planted and properly maintained in a position or positions first approved in writing by the Local Planning Authority.
Reason: To help to assimilate the development into its surroundings in accordance with Policies ENV1, DES1 and DES2 of the South Oxfordshire Local Plan 2035.
Notwithstanding the provisions of the Town and Country Planning (General Permitted Development) Order 2015 (or any Order revoking or re-enacting that Order), development as described in Schedule 2, Part 1, Class A and Class B of the Order shall not be undertaken without obtaining planning permission from the Local Planning Authority.
Reason: To safeguard the amenities of the occupiers of the adjoining properties and the character of the area in accordance with Policies DES1, DES2 and DES6 of the South Oxfordshire Local Plan 2035.
Notwithstanding the provisions of the Town and Country Planning (General Permitted Development) Order 2015 (or any Order revoking or re-enacting that Order) the provision within the curtilage of the dwelling of any building, enclosure or swimming pool as described in Schedule 2, Part 1, Class E of the Order shall not be undertaken without obtaining planning permission from the Local Planning Authority.
Reason: To safeguard the amenities of the occupiers of the adjoining properties and the character of the area in accordance with Policies DES1, DES2 and DES6 of the South Oxfordshire Local Plan 2035.
Notwithstanding the provisions of the Town and Country Planning (General Permitted Development Order) 2015 (or any Order revoking or re-enacting that Order) the erection or construction of gates, fences, walls or other means of enclosure as described in Schedule 2, Part 2, Class A of the Order shall not be undertaken without obtaining planning permission from the Local Planning Authority.
Reason: To safeguard the character of the area in accordance with Policies DES1, and DES2 of the South Oxfordshire Local Plan 2035.
The developer shall confirm in writing to the Local Planning Authority the presence of any unsuspected contamination encountered during the development. In the event of any contamination to the land and/or water being encountered, no development shall continue until a programme of investigation and/or remedial works to include methods of monitoring and certification of such works undertaken. Where land contamination investigation/remedial works are required this must be carried out by a competent person in accordance with current government and Environment Agency Guidance and Approved Codes of Practice such as Land Contamination: Risk Management 2020 and BS10175:2011 +A2:2017 'Investigation of potentially contaminated sites' and submitted to and approved in writing by the local planning authority.
Reason: To ensure that any ground, water and associated gas contamination is identified and adequately addressed to ensure the safety of the development, the environment and to ensure the site is suitable for the proposed use in accordance with Policy ENV11 of the South Oxfordshire Local Plan 2035.