Planning Application Details

P22/S3497/OApplication Type: Outline (Show Map - opens in new window)
Status Bar
 
 Completed stage
 
 Current stage
 
 Next stage
Application registered
Consultation period
Application under consideration
Decision made
Description
Outline application for proposed dwelling, re-submission of P22/S0203/O.
Location
61 Church Road Wheatley OX33 1LU
Grid Reference
/
Applicant
Trustees of Mr & Mrs E Turner
65 Church Road
Wheatley
Oxford
OX33 1LU
Agent
Allister Godfrey Architects Ltd
Appledown
31 Garston Lane
Wantage
OX12 7AR
Case Officer
Kim Gould
Telephone: 01235 422600
Email: planning@southoxon.gov.uk
Consultation / Notification
No further Representations on this application will be accepted.

Consultations / Notifications to date are shown below.

Name / Number
Date Sent
Response Date
 
Wheatley Parish Council
c/o Michelle Legg
The Parish Office
The Merry Bells
89 High Street
Wheatley
OX33 1XP
06 10 2022
12 10 2022
 
County Archaeological Services (SODC)
06 10 2022
06 10 2022
 
South and Vale Countryside Officer
06 10 2022
07 11 2022
 
65 Church Road
Wheatley
Oxford
OX33 1LU
05 10 2022
 
48 London Road
Wheatley
Oxford
OX33 1YA
05 10 2022
 
50 London Road
Wheatley
Oxford
OX33 1YA
05 10 2022
 
46 London Road
Wheatley
Oxford
OX33 1YA
05 10 2022
 
South -Highways Liaison Officer (Oxfordshire County Council)
06 10 2022
20 10 2022
 
Drainage - (South&Vale)
06 10 2022
03 11 2022
 
61 Church Road
Wheatley
Oxfordshire
OX33 1LU
17 10 2022
 
Application Type
Minor (Outline)
Application Progress
Date Received  
26th September 2022
Registration Date  
26th September 2022
Start Consultation Period  
5th October 2022
End Consultation Period  
26th October 2022
Target Decision Date  
21st November 2022
Decision
Outline Planning Permission on 8th November 2022
Conditions / Refusal Reasons
Development shall not commence until details of the reserved matters (access, appearance, landscaping, layout, scale) have been submitted to and approved in writing by the Local Planning Authority. In the case of any reserved matter, application for approval must be made not later than the expiration of three years beginning with the date of the grant of outline planning permission. Thereafter the development shall commence not later than whichever is the later of the following dates: (a) the expiration of three years from the date of this permission; or (b) the expiration of two years from the final approval of the reserved matters, or in the case of approval on different dates, the final approval of the last such matter to be approved. Reason: By virtue of Sections 91 to 95 of the Town and Country Planning Act 1990 as amended by Section 51 of the Planning and Compulsory Purchase Act 2004.

An Energy Statement, including SAP calculations in line with the recognised methodology set by Government, demonstrating how the development will achieve at least a 40% reduction in carbon emissions compared with code 2013 Building Regulations and details of how this will be monitored shall be submitted to the local planning authority as part of the reserved matters application. Reason: To ensure high standards of sustainable design and construction in accordance with Policy DES10 of the South Oxfordshire Local Plan 2035.

Prior to the commencement of development, a full surface water drainage scheme shall be submitted to and approved in writing by the Local Planning Authority. The development shall be carried out in accordance with the approved details prior to the first occupation of the development hereby approved. Reason: To prevent pollution and flooding in accordance with Policies ENV12 and EP4 of the South Oxfordshire Local Plan 2035.

Prior to the commencement of development, a full foul water drainage scheme shall be submitted to and approved in writing by the Local Planning Authority. The development shall be carried out in accordance with the approved details prior to the first occupation of the development hereby approved. Reason: To ensure the proper provision of foul water drainage and to ensure flooding and pollution is not exacerbated in the locality in accordance with policy EP4 of the South Oxfordshire Local Plan 2035.

That, prior to the commencement of development, a build over agreement or confirmation in writing to state that one is not required provided by Thames Water shall be submitted to and approved in writing by the Local Planning Authority. Reason: To ensure the proper provision of existing mains sewer drainage.
Appeal
No appeal lodged.
Updates