Planning Application Details

P22/S3053/FULApplication Type: Full Application (Show Map - opens in new window)
Status Bar
 
 Completed stage
 
 Current stage
 
 Next stage
Application registered
Consultation period
Application under consideration
Decision made
Description
Demolition of the existing dwelling and erection of a new detached dwelling (as amended by Bat Survey received 13 October 2022)
Location
Wood Park House Catslip RG9 5BP
Grid Reference
/
Applicant
Mrs L Layhe
Wood Park House Catslip
Nettlebed
Henley-on-thames
RG9 5BP
Agent
JCPC Ltd
5 Buttermarket
Thame
OX9 3EW
Case Officer
Victoria Clarke
Telephone: 01235 422600
Email: planning@southoxon.gov.uk
Consultation / Notification
No further Representations on this application will be accepted.

Consultations / Notifications to date are shown below.

Name / Number
Date Sent
Response Date
 
Nettlebed Parish Council
Jo Pugh (Clerk)
11 Springfield Close
Watlington
OX49 5RF
29 09 2022
07 10 2022
 
South and Vale Countryside Officer
29 09 2022
11 10 2022
 
Drainage - (South&Vale)
29 09 2022
19 10 2022
 
Forestry Officer (South and Vale)
29 09 2022
01 11 2022
 
Energy Assessor (ESE Ltd)
29 09 2022
29 09 2022
 
Application Type
Minor (Full Application)
Application Progress
Date Received  
17th August 2022
Registration Date  
23rd September 2022
Start Consultation Period  
28th September 2022
End Consultation Period  
19th October 2022
Target Decision Date  
24th November 2022
Decision
Planning Permission on 23rd November 2022
Conditions / Refusal Reasons
The development to which this permission relates must be begun not later than the expiration of three years beginning with the date of this permission. Reason: By virtue of Sections 91 to 95 of the Town and Country Planning Act 1990 as amended by section 51 of the Planning and Compulsory Purchase Act 2004.

That the development hereby approved shall be carried out in accordance with the details shown on the following approved plans, 10019-P03C, P04, 10019-P02C, 10019-L01, P101 and P05, except as controlled or modified by conditions of this permission. Reason: To secure the proper planning of the area in accordance with Development Plan policies.

No development above slab level shall take place until samples of the materials to be used for the external walls and roofs of the development hereby permitted has been submitted to and approved in writing by the Local Planning Authority. Reason: In the interests of the visual appearance of the development in accordance with Policies DES1 and DES2 of the South Oxfordshire Local Plan 2035.

That the existing dwelling and outbuilding as specified in the application plans shall be demolished within three months of the first occupation of the replacement dwelling hereby permitted and any demolished material which is not to be utilised in the new development shall be removed from the land. Reason: To ensure satisfactory comprehensive development in accordance with Policies DES1, DES2, ENV1 and H18 of the South Oxfordshire Local Plan 2035.

Notwithstanding the provisions of the Town and Country Planning (General Permitted Development) Order 2015 (or any Order revoking or re-enacting that Order), the enlargement, improvement or other alteration of any dwellinghouse as described in Schedule 2, Part 1, Class A of the Order shall not be undertaken without obtaining planning permission from the Local Planning Authority. Reason: To safeguard the character of the area in accordance with Policies DES1, DES2 and DES6 of the South Oxfordshire Local Plan 2035.

Notwithstanding the provisions of the Town and Country Planning (General Permitted Development) Order 2015 (or any Order revoking or re-enacting that Order) the provision within the curtilage of the dwelling of any building, enclosure or swimming pool as described in Schedule 2, Part 1, Class E of the Order shall not be undertaken without obtaining planning permission from the Local Planning Authority. Reason: To safeguard the character of the area in accordance with Policies DES1, DES2 and DES6 of the South Oxfordshire Local Plan 2035.

Prior to the commencement of development a detailed plan showing provision of car parking spaces to be provided within the site in accordance with the District Council's adopted car parking standards shall be submitted to and approved in writing by the Local Planning Authority and the parking spaces shall be laid out, surfaced, drained and completed to be compliant with sustainable drainage (SuDS) principles in strict accordance with the approved details prior to the first occupation of the development hereby permitted. Thereafter the car parking spaces shall be retained unobstructed except for the parking of vehicles associated with the development at all times. Reason: In the interests of highway safety and to ensure the provision of off-street car parking in accordance with Policy TRANS5 of the South Oxfordshire Local Plan 2035.

Prior to the commencement of any site works or operations, including demolition and site clearance relating to the development hereby permitted, an Arboricultural Method Statement and accompanying Tree Protection Plan shall be submitted to and approved in writing by the Local Planning Authority. The Arboricultural Method Statement must include the following: (1) A specification of any pruning or tree surgery works to any trees to be retained, to prevent accidental damage by construction or demolition activities; (2) The specification and location of temporary tree protective fencing and any ground protection required to protect all retained trees in accordance with the current edition of BS 5837 ''Trees in relation to design, demolition and construction'', and details of the timing and duration of its erection; (3) The definition of areas for the storage or stockpiling of materials, temporary on-site parking, site offices and huts, mixing of cement or concrete, and fuel storage; (4) The means of demolition of any existing site structures, and of the re-instatement of the area currently occupied thereby; (5) The route and method of installation of drainage or any underground services in the vicinity of retained trees; Consideration will be made to avoid siting of utilities and service runs within the Root Protection Area (RPA) of all trees to be retained. Only where it can be demonstrated that there is no alternative location for the laying of utilities, will encroachment into the RPA be considered. Methodology for any installation works within the RPA will be provided and must be in compliance with the current edition of NJUG 'Guidelines for the planning and installation and maintenance of utility apparatus in proximity to trees'. (6) The details and method of construction of any other structures such as boundary walls in the RPA of retained trees and how these relate to existing ground levels; (7) The details of materials and method of construction of any roadway, driveway, parking, pathway or other surfacing within the RPA, which is to be of a 'No Dig' construction method, in accordance with the principles with in Arboricultural Association Guidance Note 12 "The use of cellular confinement systems near trees" and in accordance with current industry best practice; and is appropriate for the type of roadway required in relation to its usage. (8) Provision for the supervision of ANY works within the RPA of trees to be retained, and for the monitoring of continuing compliance with the protective measures specified, by an appropriately qualified arboricultural consultant, to be appointed at the developer's expense and notified to the Local Planning Authority, prior to the commencement of development; and provision for the regular reporting of continued compliance or any departure there from to the Local Planning Authority. Thereafter the development shall be carried out in accordance with the approved details with the agreed measures being kept in place during the entire course of development. Reason: To safeguard trees which are visually important in accordance with Policies ENV1, DES1, and DES2 of the South Oxfordshire Local Plan 2035.

Prior to the commencement of development, with the exception of any demolition, a full surface water drainage scheme shall be submitted to and approved in writing by the Local Planning Authority. The development shall be carried out in accordance with the approved details prior to the first occupation of the development hereby approved. Reason: To prevent pollution and flooding in accordance with Policies ENV12 and EP4 of the South Oxfordshire Local Plan 2035.

Prior to the commencement of development, with the exception of any demolition, a full foul water drainage scheme shall be submitted to and approved in writing by the Local Planning Authority. The development shall be carried out in accordance with the approved details prior to the first occupation of the development hereby approved. Reason: To ensure the proper provision of foul water drainage and to ensure flooding and pollution is not exacerbated in the locality in accordance with policy EP4 of the South Oxfordshire Local Plan 2035.

Prior to first occupation, all carbon reduction energy efficiency measures shall be implemented in accordance with the Energy Statement hereby approved and a Verification Report shall be submitted to the Local Planning Authority and approved in writing. The Verification Report shall demonstrate (with photographic evidence) that the energy efficiency measures have been implemented. These measures shall be retained and maintained as such thereafter in accordance with the Energy Statement and Verification Report. Reason: To ensure high standards of sustainable design and construction in accordance with Policy DES10 of the South Oxfordshire Local Plan 2035.

The development hereby approved shall be implemented strictly in accordance with section 6 of the supporting Bat Survey Report (Ecoconsult Ltd, September 2022). This condition shall be discharged through the receipt of a letter from the project ecologist providing evidence that the development was implemented in accordance with the approved details. All ecological mitigation and enhancement features shall be delivered on site prior to first use and retained as such thereafter. Any variation shall be agreed in writing by the Local Planning Authority before such change is made. Reason: To minimise the impact of development on biodiversity and provide compensatory bat roosting provision in accordance with Policies ENV2 and ENV3 of the South Oxfordshire Local Plan 2035 and paragraphs 174 and 180 of the NPPF
Appeal
No appeal lodged.
Updates
These Planning Application Details were returned live from our back office database, and as such are as up to date as when the page was retrieved.