The development to which this permission relates must be begun not later than the expiration of three years beginning with the date of this permission.
Reason: By virtue of Sections 91 to 95 of the Town and Country Planning Act 1990 as amended by section 51 of the Planning and Compulsory Purchase Act 2004.
Related application(s):
P22/S4486/DISThat the development hereby approved shall be carried out in accordance with the details shown on the following approved plans, 1252-5E, 382-01, 1252-3A, 1252-2A, 1252-6C, 1252-4C and 1252-1, except as controlled or modified by conditions of this permission.
Reason: To secure the proper planning of the area in accordance with Development Plan policies.
Related application(s):
P22/S4486/DISThe exterior of the development hereby permitted shall only be constructed in the materials specified on the plans/supporting documents hereby approved or in materials which shall previously have been approved in writing by the Local Planning Authority.
Reason: In the interests of the visual appearance of the development in accordance with Policies DES1 and DES2 of the South Oxfordshire Local Plan 2035.
Related application(s):
P22/S4486/DISPrior to the commencement of the development hereby approved a scheme for the landscaping of the site, including the planting of live trees and shrubs, shall be submitted to and approved in writing by the Local Planning Authority. These details shall include schedules of new trees and shrubs to be planted (noting species, plant sizes and numbers/densities), the identification of the existing trees and shrubs on the site to be retained (noting species, location and spread), any earth moving operations and finished levels/contours, and an implementation programme. The scheme shall be implemented prior to the first occupation or use of the development hereby approved and thereafter be maintained in accordance with the approved scheme. In the event of any of the trees or shrubs so planted dying or being seriously damaged or destroyed within 5 years of the completion of the development, a new tree or shrub or equivalent number of trees or shrubs, as the case may be, of a species first approved by the Local Planning Authority, shall be planted and properly maintained in a position or positions first approved in writing by the Local Planning Authority.
Reason: To help to assimilate the development into its surroundings in accordance with Policies ENV1, DES1 and DES2 of the South Oxfordshire Local Plan 2035.
Prior to the commencement of any site works (including demolition or site clearance) a protected area shall be designated for all existing trees which are shown to be retained, and the trees shall be protected in accordance with a scheme which complies with the current edition of BS 5837: "Trees in relation to design, demolition and construction" that shall first have been submitted to, and approved in writing by, the Local Planning Authority. The agreed measures shall be kept in place during the entire course of development.
Reason: To safeguard trees which are visually important in accordance with Policies ENV1, DES1, and DES2 of the South Oxfordshire Local Plan 2035.
The development hereby approved shall be implemented strictly in accordance with section 4.2 and table 5 of the Bat Emergence and Re-entry Survey Report received 7th October 2022. . All ecological mitigation and enhancement features shall be delivered on site prior to first use and retained as such thereafter. Any variation shall be agreed in writing by the Local Planning Authority before such change is made.
Reason: To protect the important species on the site, in accordance with Policies ENV2 and ENV3 of the South Oxfordshire Local Plan 2035.
Prior to the commencement of any development on site (including site clearance), a watercourse protection plan should be submitted to and approved in writing by the Local Planning Authority. The Watercourse Protection Plan should include a construction and storage exclusion zone defined by temporary fencing and describe measures to protect the watercourse from damage and pollution. Thereafter, the development shall be implemented in accordance with the Watercourse Protection Plan.
Reason: To protect the watercourse from harmful development in accordance with Policies ENV2 and ENV4 of the South Oxfordshire Local Plan 2035.