Conditions / Refusal Reasons
The development to which this permission relates must be begun not later than the expiration of three years beginning with the date of this permission.
Reason: By virtue of Sections 91 to 95 of the Town and Country Planning Act 1990 as amended by section 51 of the Planning and Compulsory Purchase Act 2004.
That the development hereby approved shall be carried out in accordance with the details shown on the following approved plans, CME001, SA-11-003, OP1001, OP1001 Rev A, SA-11-010 Rev G, SA-11-001 Rev B, SA-11-002 Rev A, SKA02 Rev A, SK03 Rev A, SK06 Rev A, SK04 Rev A, SK05 Rev A, SK06 Rev A, SK07 Rev A and SK09 Rev A, except as controlled or modified by conditions of this permission.
Reason: To secure the proper planning of the area in accordance with Development Plan policies.
The applicant, or their agents or successors in title, shall be responsible for organising and implementing an archaeological watching brief, to be maintained during the period of construction/during any groundworks taking place on the site. The watching brief shall be carried out by a professional archaeological organisation in accordance with a Written Scheme of Investigation that has first been approved in writing by the Local Planning Authority.
Reason: To secure the protection of and proper provision for any archaeological remains in accordance with Policy ENV9 of the South Oxfordshire Local Plan 2035.
Following the approval of the Written Scheme of Investigation referred to in condition 3, no development shall commence on site without the appointed archaeologist being present. Once the watching brief has been completed its findings shall be reported to the Local Planning Authority, as agreed in the Written Scheme of Investigation, including all processing, research and analysis necessary to produce an accessible and useable archive and a full report for publication which shall be submitted to the Local Planning Authority within two years of the completion of the archaeological fieldwork.
Reason: To enable an appropriate level of archaeological investigation of the area including excavation and recording, post excavation analysis and the publication of results in accordance with Policy ENV9 South Oxfordshire Local Plan 2035.
Prior to the commencement of development, with the exception of any demolition, a full surface water drainage scheme in accordance with the surface water drainage hierarchy as set out in Part H of the Building Regulations, including details of the size, position and construction of drainage works, shall be submitted to, and approved in writing by, the Local Planning Authority. The drainage scheme shall be designed to accommodate a 1 in 100 year storm + 40% CC and shall be implemented in accordance with the approved details prior to the occupation of the development hereby approved.
Reason: To ensure the proper provision of surface water drainage and to ensure flooding is not exacerbated in the locality in accordance with Policy EP4 of the South Oxfordshire Local Plan 2035.
Prior to the commencement of the development hereby approved a scheme for the landscaping of the site, including the planting of live trees and shrubs, shall be submitted to and approved in writing by the Local Planning Authority. These details shall include schedules of new trees and shrubs to be planted (noting species, plant sizes and numbers/densities), the identification of the existing trees and shrubs on the site to be retained (noting species, location and spread), any earth moving operations and finished levels/contours, and an implementation programme. The scheme shall be implemented prior to the first occupation or use of the development hereby approved and thereafter be maintained in accordance with the approved scheme. In the event of any of the trees or shrubs so planted dying or being seriously damaged or destroyed within 5 years of the completion of the development, a new tree or shrub or equivalent number of trees or shrubs, as the case may be, of a species first approved by the Local Planning Authority, shall be planted and properly maintained in a position or positions first approved in writing by the Local Planning Authority.
Reason: To help to assimilate the development into its surroundings in accordance with Policies ENV1, DES1 and DES2 of the South Oxfordshire Local Plan 2035.
Prior to the commencement of any site works (including demolition or site clearance) a protected area shall be designated for all existing trees which are shown to be retained, and the trees shall be protected in accordance with a scheme which complies with the current edition of BS 5837: "Trees in relation to design, demolition and construction" that shall first have been submitted to, and approved in writing by, the Local Planning Authority. The agreed measures shall be kept in place during the entire course of development.
Reason: To safeguard trees which are visually important in accordance with Policies ENV1, DES1, and DES2 of the South Oxfordshire Local Plan 2035 and BCS12 of the Brightwell cum Sotwell Neighbourhood Plan.
Two bat boxes shall be erected within the garden on trees as per the specification set out in the Bat Emergence Surveys (BES) report (4 Acre Ecology Ltd, August 2023) prior to works being carried out on the barns. The bat boxes with thereafter be retained.
Reason: To protect the important species on the site, in accordance with Policies ENV2 and ENV3 of the South Oxfordshire Local Plan 2035.
Prior to occupation of the development hereby permitted the proposed means of access onto Church Lane is to be formed and laid out and constructed strictly in accordance with the local highway authority's specifications and all ancillary works specified shall be undertaken.
Reason: In the interest of highway safety in accordance with Policy TRANS5 of the South Oxfordshire Local Plan 2035.
Before the proposed access is first used, the existing access onto Church Lane shall be permanently stopped up by the means of reinstatement of the highway verge and proposed planting to the approval of the Local Planning Authority and in accordance with the local highway authority's specifications. Thereafter the closed access shall not be used by any vehicular traffic whatsoever.
Reason: In the interest of highway safety in accordance with Policy TRANS5 of the South Oxfordshire Local Plan 2035.
Prior to the first occupation of the development hereby approved, the parking and turning areas shall be provided in accordance with the approved plan SA-11-010 Rev G and shall be constructed, laid out, surfaced, drained and completed to be compliant with sustainable drainage (SuDS) principles, and shall be retained unobstructed except for the parking of vehicles associated with the development at all times.
Reason: In the interests of highway safety and in accordance with Policy TRANS5 of the South Oxfordshire Local Plan 2035.
The vision splays shown on the approved plan SK02 Rev A shall not be obstructed by any object, structure, planting or other material with a height exceeding or growing above 0.9 metres as measured from carriageway level.
Reason: In the interest of highway safety in accordance with Policy TRANS5 of the South Oxfordshire Local Plan 2035.
The development herby approved shall be carried out in accordance with the working method statement for bats, as per Section 7 the Bat Emergence Survey Report (4 Acre Ecology Ltd, August 2023) and must be strictly followed during the development
Reason: To protect the important species on the site, in accordance with Policies ENV2 and ENV3 of the South Oxfordshire Local Plan 2035.
The design and construction of the development hereby permitted will carried out as per section 7.9 of the Bat Emergence Surveys (BES) report (4 Acre Ecology Ltd, August 2023) to allow access for bats and shall be completed prior to the occupation of the development hereby permitted.
Reason: To protect the important species on the site, in accordance with Policies ENV2 and ENV3 of the South Oxfordshire Local Plan 2035.
That unless otherwise agreed in writing by the local planning authority the development shall be carried out as per the lighting strategy in Section 7.11 of the Bat Emergence Surveys (BES) report (4 Acre Ecology Ltd, August 2023).
Reason: To protect the environment and wildlife in accordance with Policies ENV2 and ENV3 of the South Oxfordshire Local Plan 2035.
Prior to the first occupation of the dwelling hereby approved, a scheme to provide each dwelling with Electric Vehicle Charging Points shall be submitted to and approved in writing by the Local Planning Authority. Thereafter each Electric Vehicle Charging Point shall be implemented prior to the occupation of the dwelling it would serve.
Reason: To ensure sustainable forms of transport in accordance with Policies TRANS5, ENV12 and EP1 of the South Oxfordshire Local Plan 2035.
That, unless otherwise agreed in writing by the local planning authority the materials to be used for the external walls and roof of the extension to the building to create the new dwelling and car port hereby approved shall be of the same colour, type and texture as those used on the existing building.
Reason: To protect the architectural and historic interest of the listed building and protect the character and appearance of the Brightwell cum Sotwell Conservation Area Policies DES1, DES2, ENV6, ENV7 and ENV8 of the South Oxfordshire Local Plan 2035 and Policies BCS9 and BCS10 of the Brightwell cum Sotwell Neighbourhood Plan.
No development hereby permitted shall take place except in accordance with the terms and conditions of the Council's Organisational Licence (WML-OR112, or a Further Licence ) and with the proposals detailed on plan Middle Farm: Impact Plan for great crested newt District Licensing , Version 1 (dated 3rd May 2023).
Reason: In order to ensure that adverse impacts on great crested newts are adequately mitigated and to ensure that site works are delivered in full compliance with the organisational licence (WML-OR112, or a Further Licence), section 15 of the National Planning Policy Framework, Circular 06/2005 and the Natural Environment and Rural Communities Act 2006.
No development hereby permitted shall take place except in accordance with Part 1 of the Great Crested Newt Mitigation Principles, as set out in the District Licence WML-OR112 or a Further Licence .
Reason: In order to ensure that adverse impacts on great crested newts are adequately mitigated and to ensure that site works are delivered in full compliance with the Organisational Licence (WML-OR112, or a Further Licence ), section 15 of the National Planning Policy Framework, Circular 06/2005 and the Natural Environment and Rural Communities Act 2006.
Notwithstanding the provisions of the Town and Country Planning (General Permitted Development) Order 2015 (or any Order revoking or re-enacting that Order), the enlargement, improvement or other alteration of any dwellinghouse as described in Schedule 2, Part 1, Class C of the Order shall not be undertaken without obtaining planning permission from the Local Planning Authority.
Reason: To safeguard the amenities of the occupiers of the adjoining properties and the character of the area in accordance with Policies DES1, DES2 and DES6 of the South Oxfordshire Local Plan 2035.