Planning Application Details

P22/S2174/FULApplication Type: Full Application (Show Map - opens in new window)
Status Bar
 
 Completed stage
 
 Current stage
 
 Next stage
Application registered
Consultation period
Application under consideration
Decision made
Description
Erection of a single storey dwelling (energy statement received 26th October 2022).
Location
24 Fairmile Henley-on-Thames RG9 2LA
Grid Reference
/
Applicant
Mr David Wright
10 Rylett Road
London
W12 9NL
Agent
MGA Architects
PO Box 43
High Wycombe
HP15 7FN
Constraints
Henley Main Area Conservation Area
Grade II Listed Building
Case Officer
Paul Lucas
Telephone: 01235 422600
Email: planning@southoxon.gov.uk
Consultation / Notification
No further Representations on this application will be accepted.

Consultations / Notifications to date are shown below.

Name / Number
Date Sent
Response Date
 
Henley-on-Thames Town Council
c/o Sheridan Jacklin-Edward
Council Offices
Town Hall
Market Place
HENLEY-ON-THAMES
RG9 2AQ
15 06 2022
23 06 2022
 
28 Fairmile
Henley-On-Thames
RG9 2LA
14 06 2022
29 06 2022
 
22 Fairmile
Henley-On-Thames
RG9 2LA
14 06 2022
 
Drainage - (South&Vale)
15 06 2022
07 07 2022
 
24 Fairmile
Henley-On-Thames
RG9 2LA
14 06 2022
 
26 Fairmile
Henley-On-Thames
RG9 2LA
14 06 2022
 
The Henley Society (Planning)
21 06 2022
 
Energy Assessor (ESE Ltd)
27 10 2022
14 11 2022
 
Application Type
Minor (Full Application)
Application Progress
Date Received  
8th June 2022
Registration Date  
8th June 2022
Start Consultation Period  
14th June 2022
End Consultation Period  
15th July 2022
Target Decision Date  
13th January 2023
Decision
Planning Permission on 12th January 2023
Conditions / Refusal Reasons
The development to which this permission relates must be begun not later than the expiration of three years beginning with the date of this permission. Reason: By virtue of Sections 91 to 95 of the Town and Country Planning Act 1990 as amended by section 51 of the Planning and Compulsory Purchase Act 2004.

That the development hereby approved shall be carried out in accordance with the details shown on the following approved plans, 871 03 Rev A, 871 04 Rev A, 871 02 Rev A, 871 01 and 871 06, except as controlled or modified by conditions of this permission. Reason: To secure the proper planning of the area in accordance with Development Plan policies.

Prior to the commencement of development detailed plans showing the existing and proposed ground levels of the site together with the slab and ridge levels of the proposed development, relative to a fixed datum point on adjoining land outside of the application site, shall be submitted to and approved in writing by the Local Planning Authority. Thereafter the development shall be carried out in accordance with the approved details. Reason: To ensure a satisfactory form of development in accordance with Policies DES1, DES2, ENV1, ENV6 and ENV8 of the South Oxfordshire Local Plan 2035.

Prior to the commencement of the development above slab level, a photographic schedule of all materials to be used in the external construction and finishes of the development hereby permitted shall be submitted to and approved in writing by the Local Planning Authority. Reason: In the interests of the visual appearance of the development in accordance with Policies DES1, DES2, ENV1, ENV6 and ENV8 of the South Oxfordshire Local Plan 2035.

Notwithstanding the provisions of the Town and Country (General Permitted Development Order) 2015 (or any Order revoking or re-enacting that Order), no development as specified in Schedule 2, Part 1, Class A - Extensions; Class E - Outbuildings; Class F - Hardstandings shall be undertaken without the prior written permission of the Local Planning Authority. Reason: The specific circumstances of this site warrant the Local Planning Authority having control over any further development as specified in the condition in the interests of amenity and in accordance with Policies DES1, DES2, ENV1, ENV6 and ENV8 of the South Oxfordshire Local Plan 2035.

Prior to first occupation of the development, the existing means of access onto Fairmile shall be improved and laid out and constructed strictly in accordance with the details shown on the site plan 871-06 and the local highway authority's specifications and all ancillary works specified shall be undertaken. Reason: In the interest of highway safety in accordance with Policy TRANS5 of the South Oxfordshire Local Plan 2035.

Prior to the first occupation of the development hereby approved, the parking and turning areas shall be provided in accordance with the approved plan 871-06 and shall be constructed, laid out, surfaced, drained and completed to be SUDS complaint, and shall be retained unobstructed except for the parking of vehicles associated with the development at all times. Reason: In the interests of highway safety and in accordance with Policy TRANS5 of the South Oxfordshire Local Plan 2035.

A Construction Traffic Management Plan (CTMP) shall be submitted to and approved in writing by the Local Planning Authority prior to the commencement of development. The approved CTMP shall be implemented prior to any works being carried out on site, and shall be maintained throughout the course of the development. Reason: In the interests of highway safety and to mitigate the impact of construction vehicles on the surrounding highway network, road infrastructure and local residents, particularly at morning and afternoon peak traffic times and in accordance with Policies DES6, ENV12 and TRANS5 of the South Oxfordshire Local Plan 2035.

Prior to the commencement of the development above slab level, a scheme for the landscaping of the site, including the planting of live trees and shrubs, the treatment of the driveway alterations and hard standings, and the provision of boundary treatment shall be submitted to and approved in writing by the Local Planning Authority. The hard landscaping scheme shall be implemented in accordance with the approved details prior to the first occupation of the development and thereafter retained as such. The soft landscaping scheme shall be implemented as approved within the first planting season of the commencement of the approved development and thereafter be maintained in accordance with the approved scheme. In the event of any of the trees or shrubs so planted dying or being seriously damaged or destroyed within 5 years of the completion of the development, a new tree or shrub or equivalent number of trees or shrubs, as the case may be, of a species first approved by the Local Planning Authority, shall be planted and properly maintained in a position or positions first approved in writing by the Local Planning Authority. Reason: To help to assimilate the development into its surroundings in accordance with Policies DES1, DES2, ENV1 and ENV8 of the South Oxfordshire Local Plan 2035.

Prior to the commencement of any site works or operations relating to the development hereby permitted, an arboricultural method statement to ensure the satisfactory protection of retained trees during the construction period shall be submitted to and approved in writing by the Local Planning Authority. Written approval must be obtained prior to commencement of any site works including demolition. The matters to be encompassed within the arboricultural method statement shall include the following:- (i) A specification for the pruning of, or tree surgery to, trees to be retained in order to prevent accidental damage by construction activities; (ii) The specification of the location, materials and means of construction of temporary protective fencing and/or ground protection in the vicinity of trees to be retained, in accordance with the recommendations of BS 5837 'Trees in relation to design, demolition and construction' and details of the timing and duration of its erection; (iii) The definition of areas for the storage or stockpiling of materials, temporary on-site parking, site offices and huts, mixing of cement or concrete, and fuel storage; (iv) The means of demolition of any existing site structures, and of the re-instatement of the area currently occupied thereby; (v) The specification of the routing and means of installation of drainage or any underground services in the vicinity of retained trees; (vi) The details and method of construction of any other structures such as boundary walls in the vicinity of retained trees and how these relate to existing ground levels; (vii) The details of the materials and method of construction of any roadway, parking, pathway or other surfacing within the RPA, which is to be of a 'no dig' construction method in accordance with the principles of Arboricultural Practice Note 12 "Through the Trees to Development", and in accordance with current industry best practice; and as appropriate for the type of roadway required in relation to its usage. (viii) Provision for the supervision of ANY works within the root protection areas of trees to be retained, and for the monitoring of continuing compliance with the protective measures specified, by an appropriately qualified arboricultural consultant, to be appointed at the developer's expense and notified to the Local Planning Authority, prior to the commencement of development; and provision for the regular reporting of continued compliance or any departure there from to the Local Planning Authority. Thereafter the development shall be carried out in accordance with the approved details with the agreed measures being kept in place during the entire course of development. Reason: To safeguard trees which are visually important in accordance with Policies DES1, DES2, ENV1 and ENV8 of the South Oxfordshire Local Plan 2035.

Details, including drawings as necessary, in respect of the following, shall be submitted to and approved in writing by the Local Planning Authority before the relevant part of the work has begun: - final structural proposal for the construction of the basement, supported by site section plans and mitigation methods for the protection of the listed wall to the rear of the plot. Thereafter the works shall be carried out in accordance with the approved details. Reason: To safeguard the special architectural or historic interest and setting of the listed wall in accordance with Policies ENV6 and ENV7 of the South Oxfordshire Local Plan 2035.

The development shall be carried out in accordance with the submitted Flood Risk Assessment, prepared by Peter Brett Associates, reference 35711/400, dated October 2015, and technical letter note to EA, prepared by Peter Brett Associates, reference 35711/4002/WP/Letters, dated 4 June 2019, and the following mitigation measures it details: - Finished floor levels will be set 150mm above external ground levels on site. These mitigation measures shall be fully implemented prior to occupation and subsequently in accordance with the scheme's timing/phasing arrangements. The measures detailed above shall be retained and maintained thereafter throughout the lifetime of the development. Reason: To reduce the risk of flooding on-site and elsewhere, in particular, to reduce the risk of flooding to the proposed development and future occupants in accordance with Policy EP4 of the South Oxfordshire Local Plan 2035.

Prior to the commencement of development, waterproofing construction details for the basement shall be submitted to and approved in writing by the Local Planning Authority. Thereafter the development shall be carried out in accordance with the approved details. Reason: To reduce the risk of flooding on-site and elsewhere, in particular, to reduce the risk of flooding to the proposed development and future occupants in accordance with Policy EP4 of the South Oxfordshire Local Plan 2035.

Prior to the commencement of development, with the exception of any demolition, a full surface water drainage scheme, including details of the size, position and construction of drainage works, shall be submitted to, and approved in writing by, the Local Planning Authority. The drainage scheme shall be designed to accommodate a 1 in 100 year storm + 40% climate change and shall be implemented in accordance with the approved details prior to the occupation of the development hereby approved. Reason: To reduce the risk of flooding on-site and elsewhere, in particular, to reduce the risk of flooding to the proposed development and future occupants in accordance with Policy EP4 of the South Oxfordshire Local Plan 2035.

Prior to the commencement of development, with the exception of any demolition, a full foul water drainage scheme shall be submitted to and approved in writing by the Local Planning Authority. The scheme shall include details of the size, position and construction of the drainage scheme, all coupled with calculations to evidence this. Thereafter the development shall be carried out in accordance with the approved details. Reason: To reduce the risk of flooding on-site and elsewhere, in particular, to reduce the risk of flooding to the proposed development and future occupants in accordance with Policy EP4 of the South Oxfordshire Local Plan 2035.

Prior to first occupation, all carbon reduction energy efficiency measures shall be implemented in accordance with the Energy Statement hereby approved and a Verification Report shall be submitted to the Local Planning Authority and approved in writing. The Verification Report shall demonstrate (with photographic evidence) that the energy efficiency measures have been implemented. These measures shall be retained and maintained as such thereafter in accordance with the Energy Statement and Verification Report. Reason: To ensure high standards of sustainable design and construction in accordance with Policy DES10 of the South Oxfordshire Local Plan 2035.

Details of any external heating or energy generation system to be used in the development hereby permitted shall be submitted to and approved in writing by the Local Planning Authority prior to installation. Reason: To ensure high standards of sustainable design and construction and an acceptable visual and amenity impact in accordance with Policies DES1, DES2, DES6, DES16, ENV1 and ENV12 of the South Oxfordshire Local Plan 2035.

Prior to the first occupation of the development hereby approved, an Electric Vehicle Charging Point shall be installed for the dwelling and thereafter retained as such. Reason: To ensure sustainable forms of transport in accordance with Policy TRANS5 of the South Oxfordshire Local Plan 2035.
Appeal
No appeal lodged.