That the development hereby approved shall be carried out in accordance with the details shown on the following approved plans, BLO001, PE001 and LOC001, except as controlled or modified by conditions of this permission.
Reason: To secure the proper planning of the area in accordance with Development Plan policies.
Related application(s):
P22/S3753/DISThe exterior of the development hereby permitted shall only be constructed in the materials specified on the plans/supporting documents hereby approved or in materials which shall previously have been approved in writing by the Local Planning Authority.
Reason: In the interests of the visual appearance of the development in accordance with Policies ENV8, DES1 and DES2 of the South Oxfordshire Local Plan 2035.
Within 6 months of the date of this planning permission, a phased risk assessment shall be carried out by a competent person in accordance with current government and Environment Agency Guidance and Approved Codes of Practice such as Land Contamination: Risk Management 2020 and BS10175:2011 +A2:2017 'Investigation of potentially contaminated sites'. Each phase shall be submitted to and approved in writing by the Local Planning Authority.
Phase 1 shall incorporate a desk study and site walk over to identify all potential contaminative uses on site, and to inform the conceptual site model. If potential contamination is identified in Phase 1 then a Phase 2 investigation shall be undertaken.
Phase 2 shall include a comprehensive intrusive investigation in order to characterise the type, nature and extent of contamination present, the risks to receptors and if significant contamination is identified to inform the remediation strategy.
Phase 3 requires that a remediation strategy be submitted to and approved by the LPA to ensure the site will be rendered suitable for its proposed use.
Reason: To ensure that any ground, water and associated gas contamination is identified and adequately addressed to ensure the safety of the development, the environment and to ensure the site is suitable for the proposed use in accordance with Policy ENV11 of the South Oxfordshire Local Plan 2035.
Within 12 months of the date of this planning permission any previously approved remediation strategy shall have been carried out in full and a validation report confirming completion of these works has been submitted to and approved in writing by the Local Planning Authority.
Reason: To ensure that any ground, water and associated gas contamination is identified and adequately addressed to ensure the safety of the development, the environment and to ensure the site is suitable for the proposed use in accordance with Policy ENV11 of the South Oxfordshire Local Plan 2035.
The developer shall confirm in writing to the Local Planning Authority the presence of any unsuspected contamination encountered during the development. In the event of any contamination to the land and/or water being encountered, no development shall continue until a programme of investigation and/or remedial works to include methods of monitoring and certification of such works undertaken. Where land contamination investigation/remedial works are required this must be carried out by a competent person in accordance with current government and Environment Agency Guidance and Approved Codes of Practice such as Land Contamination: Risk Management 2020 and BS10175:2011 +A2:2017 'Investigation of potentially contaminated sites' and submitted to and approved in writing by the local planning authority.
Reason: To ensure that any ground, water and associated gas contamination is identified and adequately addressed to ensure the safety of the development, the environment and to ensure the site is suitable for the proposed use in accordance with Policy ENV11 of the South Oxfordshire Local Plan 2035.
Notwithstanding the provisions of the Town and Country Planning (General Permitted Development) Order 2015 (or any Order revoking or re-enacting that Order) the provision within the curtilage of the dwelling of any building, enclosure or swimming pool as described in Schedule 2, Part 1, Class E of the Order shall not be undertaken without obtaining planning permission from the Local Planning Authority.
Reason: To safeguard the setting of the listed building,the character of the area and neighbour amenity in accordance with Policies DES1, DES2 , DES6 . ENV7 and ENV8 of the South Oxfordshire Local Plan 2035.