Description
Single and two storey extensions to front side and rear and formation of vehicular access. Provision of a dormer window to the front elevation and the relocation of the entrance door to the front with an open canopy porch over.(amended & additional information received 26 April 2022 and as amended by plan received 29 November 2022).
Conditions / Refusal Reasons
The development to which this permission relates must be begun not later than the expiration of three years beginning with the date of this permission.
Reason: By virtue of Sections 91 to 95 of the Town and Country Planning Act 1990 as amended by section 51 of the Planning and Compulsory Purchase Act 2004.
That the development hereby approved shall be carried out in accordance with the details shown on the following approved plans, JU-1-21, BU/2/21, CMP 001, LOC 001, BLO001A, 107-GLE-DRW-TPP-01 and 107-GLE-DRW-TCP-01, except as controlled or modified by conditions of this permission.
Reason: To secure the proper planning of the area in accordance with Development Plan policies.
The tree protection details as shown on the approved 107-GLE-DRW-TPP-01 and as detailed in the ARBORICULTURAL IMPACT ASSESSMENT ref 107-GLE-RPT-AIA shall be put in place prior to any on site works including demolition and thereafter retained in situ for the duration of development and the mitigation measures outlined in 5.21 of the report shall be undertaken prior to first occupation of the approved development.
Reason: To safeguard trees which are visually important in accordance with Policies ENV1, DES1, and DES2 of the South Oxfordshire Local Plan 2035.
Prior to occupation of the extension hereby permitted the proposed means of access onto South Bank is to be formed and laid out and constructed strictly in accordance with the local highway authority's specifications and all ancillary works specified shall be undertaken.
Reason: In the interest of highway safety in accordance with Policy TRANS5 of the South Oxfordshire Local Plan 2035.
Prior to the first occupation of the development hereby approved, the parking and turning areas shall be provided in accordance with the approved plan BLO001A and shall be constructed, laid out, surfaced, drained and completed to be compliant with sustainable drainage (SuDS) principles, and shall be retained unobstructed except for the parking of vehicles associated with the development at all times.
Reason: In the interests of highway safety and in accordance with Policy TRANS5 of the South Oxfordshire Local Plan 2035.
Before the proposed access is first used, the existing access onto South Bank shall be permanently stopped up by the means of reinstatement of the highway verge and proposed planting to the approval of the Local Planning Authority and in accordance with the local highway authority's specifications. Thereafter the closed access shall not be used by any vehicular traffic whatsoever.
Reason: In the interest of highway safety and to protect the tree subject of a Tree Preservation Order in accordance with Policies TRANS5 & ENV1 of the South Oxfordshire Local Plan 2035.
The exterior of the development hereby permitted shall only be constructed in the materials specified on the plans/supporting documents hereby approved or in materials which shall previously have been approved in writing by the Local Planning Authority.
Reason: In the interests of the visual appearance of the development in accordance with Policies DES1 and DES2 of the South Oxfordshire Local Plan 2035.