The development to which this permission relates must be begun not later than the expiration of three years beginning with the date of this permission.
Reason: By virtue of Sections 91 to 95 of the Town and Country Planning Act 1990 as amended by section 51 of the Planning and Compulsory Purchase Act 2004.
Related application(s):
P22/S2504/DIS,
P23/S2371/DIS,
P23/S2738/DISThat the development hereby approved shall be carried out in accordance with the details shown on the following approved plans, 908 P010, 908 P011, 908 P005, 0265-200 A, 0265-100 A, 908 P001, 0265-301 A, 908 107, 0265-010 A, 908 P101, 908 P102, 0265-001 A, 908 P002, 0265-201 A, 0265-300 A, 908 P106 Rev A, 908 P105 Rev A amended Ground FFL, 908 P110 Rev A and 908 P111 Rev A, except as controlled or modified by conditions of this permission.
Reason: To secure the proper planning of the area in accordance with Development Plan policies.
Related application(s):
P22/S2504/DIS,
P23/S2371/DISPrior to any demolition and the commencement of the development a professional archaeological organisation acceptable to the Local Planning Authority shall prepare an Archaeological Written Scheme of Investigation, relating to the application site area, which shall be submitted to and approved in writing by the Local Planning Authority.
Reason - To safeguard the recording of archaeological matters within the site in accordance with Policy ENV9 of the South Oxfordshire Local Plan 2035.
Related application(s):
P23/S2371/DISFollowing the approval of the Written Scheme of Investigation referred to in condition 3, and prior to any demolition on the site and the commencement of the development (other than in accordance with the agreed Written Scheme of Investigation), a staged programme of archaeological evaluation and mitigation shall be carried out by the commissioned archaeological organisation in accordance with the approved Written Scheme of Investigation. The programme of work shall include all processing, research and analysis necessary to produce an accessible and useable archive and a full report for publication which shall be submitted to the Local Planning Authority within two years of the completion of the archaeological fieldwork.
Reason To safeguard the identification, recording, analysis and archiving of heritage assets before they are lost and to advance understanding of the heritage assets in their wider context through publication and dissemination of the evidence in accordance with Policy ENV9 of the of the South Oxfordshire Local Plan 2035.
Related application(s):
P23/S2371/DISPrior to the commencement of development, a full surface water drainage scheme in accordance with the surface water drainage hierarchy as set out in Part H of the Building Regulations, including details of the size, position and construction of drainage works, shall be submitted to, and approved in writing by, the Local Planning Authority. The drainage scheme shall be designed to accommodate a 1 in 100 year storm + 40% CC and shall be implemented in accordance with the approved details prior to the occupation of the development hereby approved.
Reason: To ensure the proper provision of surface water drainage and to ensure flooding is not exacerbated in the locality in accordance with Policies ENV12 and EP4 of the South Oxfordshire Local Plan 2035.
That, prior to the commencement of development, a full foul water drainage scheme shall be submitted to and approved in writing by the Local Planning Authority. The scheme shall include details of the size, position and construction of the drainage scheme. Thereafter the scheme as approved shall be implemented prior to the occupation of the development hereby approved.
Reason: To ensure the proper provision of foul water drainage, to ensure no encroachment with the surface water drainage system and to ensure flooding and pollution is not exacerbated in the locality in accordance with policy EP4 of the South Oxfordshire Local Plan 2035.
Prior to the commencement of any site works (including demolition or site clearance) a protected area shall be designated for all existing trees which are shown to be retained, and the trees shall be protected in accordance with a scheme which complies with the current edition of BS 5837: "Trees in relation to design, demolition and construction" that shall first have been submitted to, and approved in writing by, the Local Planning Authority. The agreed measures shall be kept in place during the entire course of development.
Reason: To safeguard trees which are visually important in accordance with Policies ENV1, DES1, and DES2 of the South Oxfordshire Local Plan 2035.
Prior to the first occupation of the development hereby approved, the parking and turning areas shall be provided in accordance with the approved plan 100 Rev A and shall be constructed, laid out, surfaced, drained and completed to be compliant with sustainable drainage (SuDS) principles, and shall be retained unobstructed except for the parking of vehicles associated with the development at all times.
Reason: In the interests of highway safety and in accordance with Policy TRANS5 of the South Oxfordshire Local Plan 2035.
The development hereby permitted shall be implemented in accordance with the measures stated in section 4.9, 5 (assessment and recommendations section) and figure 3 of the Ecological Assessment Report (GS Ecology, 22 July 2021 REF ECO2738B). Long term replacement roost sites must be delivered prior to occupation of the development.
Reason: To minimise the impacts of development on biodiversity and achieve net gains for biodiversity, in accordance with ENV2 and ENV3 of the SOLP 2035 and paragraph 174 and 180 of the NPPF.
Prior to the first occupation of the development hereby approved, an Electric Vehicle Charging Point shall be installed and thereafter retained as such.
Reason: To ensure sustainable forms of transport in accordance with Policy TRANS5 of the South Oxfordshire Local Plan 2035.
Prior to first occupation, all carbon reduction energy efficiency measures shall be implemented in accordance with the Energy Statement '21-0032 Energy Statement dated Monday 4 October 2021 Version 2' hereby approved and a Verification Report shall be submitted to the Local Planning Authority and approved in writing. The Verification Report shall demonstrate (with photographic evidence) that the energy efficiency measures have been implemented. These measures shall be retained and maintained as such thereafter in accordance with the Energy Statement and Verification Report.
Reason: To ensure high standards of sustainable design and construction in accordance with Policy DES10 of the South Oxfordshire Local Plan 2035.
That those buildings shown to be demolished on the plans accompanying the application - specifically the existing dwelling, shall be demolished, and any demolished material which is not to be utilised in the new development shall be removed from the land, before the development hereby permitted is occupied, and this provision shall apply unless an alternative scheme for the phased demolition of the building(s) and removal of materials is first submitted to and approved in writing by the Local Planning Authority.
Reason: To ensure satisfactory comprehensive development in accordance with Policies DES1, DES2 and ENV1 of the South Oxfordshire Local Plan 2035 and Policies BCS7 and BCS9 of the Brightwell cum Sotwell Neighbourhood Plan.
The exterior of the development hereby permitted shall only be constructed in the materials specified on the plans and stated in the Design and Access Statement hereby approved or in materials which shall previously have been approved in writing by the Local Planning Authority.
Reason: In the interests of the visual appearance of the development in accordance with Policies DES1 and DES2 of the South Oxfordshire Local Plan 2035.