Planning Application Details

P21/S2624/FULApplication Type: Full Application (Show Map - opens in new window)
Status Bar
 
 Completed stage
 
 Current stage
 
 Next stage
Application registered
Consultation period
Application under consideration
Decision made
Description
Conversion and extension of existing building to create a residential development of 6 apartments to provide 1 x 3-bedroom apartment, 3 x 2-bedroom apartments and 2 x 1-bedroom apartments including amenity space to the rear. (As amplified by Energy Statement received 7 July 2021, desk study regarding contamination received 10 August 2021 and as revised by plans received from agent on 8 September to address National Space Standards).
Location
114 Broadway Didcot OX11 8AB
Grid Reference
452856/189997
Applicant
Mrs Sarah Brown
34 Cedar Road
Farnborough
Hants
GU14 7AX
Agent
Middleton Top Architects
8 Pink Street
Haworth
Keighley
BD22 8AX
Case Officer
Kim Gould
Telephone: 01235 422600
Email: planning@southoxon.gov.uk
View officers committee report (22/09/2021) here
Consultation / Notification
No further Representations on this application will be accepted.

Consultations / Notifications to date are shown below.

Name / Number
Date Sent
Response Date
 
Didcot Town Council
Council Offices
Britwell Road
DIDCOT
Oxon
OX11 7JN
17 06 2021
16 07 2021
 
Contaminated Land
10 08 2021
16 08 2021
 
Grandma's Pantry
114 Broadway
Didcot
OX11 8AB
16 06 2021
 
110A Broadway
Didcot
OX11 8AB
16 06 2021
 
OXVAPE
110 Broadway
Didcot
OX11 8AB
16 06 2021
 
116 Broadway
Didcot
OX11 8AB
16 06 2021
 
108A Broadway
Didcot
OX11 8AB
16 06 2021
 
Davis Tate
108 Broadway
Didcot
OX11 8AB
16 06 2021
 
112A Broadway
Didcot
OX11 8AB
16 06 2021
 
114A Broadway
Didcot
OX11 8AB
16 06 2021
 
Vintage Turkish Barber
112 Broadway
Didcot
OX11 8AB
16 06 2021
 
South -Highways Liaison Officer (Oxfordshire County Council)
17 06 2021
01 07 2021
 
Waste Management Officer (District Council)
17 06 2021
29 07 2021
 
Strategic Property Team
07 07 2021
21 07 2021
 
Mike Andrews
07 07 2021
02 08 2021
 
Drainage - (South&Vale)
29 07 2021
17 08 2021
 
Application Type
Minor (Full Application)
Application Progress
Date Received  
7th June 2021
Registration Date  
7th June 2021
Start Consultation Period  
16th June 2021
End Consultation Period  
7th July 2021
Target Decision Date  
24th September 2021
Target Committee Meeting  
22nd September 2021
Decision
Planning Permission on 24th September 2021
Conditions / Refusal Reasons
The development to which this permission relates must be begun not later than the expiration of three years beginning with the date of this permission. Reason: By virtue of Sections 91 to 95 of the Town and Country Planning Act 1990 as amended by section 51 of the Planning and Compulsory Purchase Act 2004. Related application(s): P23/S1423/DIS, P23/S3132/DIS

That the development hereby approved shall be carried out in accordance with the details shown on the following approved plans, 20 01 PL 06A, 20 01 PL 07C, 20 01 PL 08D, 20 01 PL 09A, 20 01 PL 04, 20 01 PL 05, 20 01 PL 10, 20 01 PL 03, 20 01 PL 02, 20 01 PL 01 and 01, except as controlled or modified by conditions of this permission. Reason: To secure the proper planning of the area in accordance with Development Plan policies. Related application(s): P23/S1423/DIS

The exterior of the development hereby permitted shall only be constructed in the materials specified on the plans/supporting documents hereby approved or in materials which shall previously have been approved in writing by the Local Planning Authority. Reason: In the interests of the visual appearance of the development in accordance with Policies DES1 and DES2 of the South Oxfordshire Local Plan 2035. Related application(s): P23/S1423/DIS

Prior to first occupation, all carbon reduction energy efficiency measures shall be implemented in accordance with the Energy Statement hereby approved and a Verification Report shall be submitted to the Local Planning Authority and approved in writing. The Verification Report shall demonstrate (with photographic evidence) that the energy efficiency measures have been implemented. These measures shall be retained and maintained as such thereafter in accordance with the Energy Statement and Verification Report. Reason: To ensure high standards of sustainable design and construction in accordance with Policy DES10 of the South Oxfordshire Local Plan 2035. Related application(s): P23/S1423/DIS

That prior to the first occupation of the of any of the flats hereby approved, the existing vehicular access from Broadway shall be closed off with full face kerbing and the footway reinstated. The existing access-way shall be closed off with a pedestrian/cycle gate only. Reason: In the interest of highway safety in accordance with Policy TRANS5 of the South Oxfordshire Local Plan 2035.

Prior to the commencement of the development a phased risk assessment shall be carried out by a competent person in accordance with current government and Environment Agency Guidance and Approved Codes of Practice such as Land Contamination: Risk Management 2020 and BS10175:2011 +A2:2017 'Investigation of potentially contaminated sites'. Each phase shall be submitted to and approved in writing by the Local Planning Authority. Phase 2 shall include a comprehensive intrusive investigation in order to characterise the type, nature and extent of contamination present, the risks to receptors and if significant contamination is identified to inform the remediation strategy. Phase 3 requires that a remediation strategy be submitted to and approved by the LPA to ensure the site will be rendered suitable for its proposed use. Reason: To ensure that any ground, water and associated gas contamination is identified and adequately addressed to ensure the safety of the development, the environment and to ensure the site is suitable for the proposed use in accordance with Policy ENV11 of the South Oxfordshire Local Plan 2035.

The development shall not be occupied until any previously approved remediation strategy has been carried out in full and a validation report confirming completion of these works has been submitted to and approved in writing by the Local Planning Authority. Reason: To ensure that any ground, water and associated gas contamination is identified and adequately addressed to ensure the safety of the development, the environment and to ensure the site is suitable for the proposed use in accordance with Policy ENV11 of the South Oxfordshire Local Plan 2035.

The developer shall confirm in writing to the Local Planning Authority the presence of any unsuspected contamination encountered during the development. In the event of any contamination to the land and/or water being encountered, no development shall continue until a programme of investigation and/or remedial works to include methods of monitoring and certification of such works undertaken. Where land contamination investigation/remedial works are required this must be carried out by a competent person in accordance with current government and Environment Agency Guidance and Approved Codes of Practice such as Land Contamination: Risk Management 2020 and BS10175:2011 +A2:2017 'Investigation of potentially contaminated sites' and submitted to and approved in writing by the local planning authority. Reason: To ensure that any ground, water and associated gas contamination is identified and adequately addressed to ensure the safety of the development, the environment and to ensure the site is suitable for the proposed use in accordance with Policy ENV11 of the South Oxfordshire Local Plan 2035.

Prior to the commencement of development, a full surface water drainage scheme in accordance with the surface water drainage hierarchy as set out in Part H of the Building Regulations, including details of the size, position and construction of drainage works, shall be submitted to, and approved in writing by, the Local Planning Authority. The drainage scheme shall be designed to accommodate a 1 in 100 year storm + 40% CC and shall be implemented in accordance with the approved details prior to the occupation of the development hereby approved. Reason: To ensure the proper provision of surface water drainage and to ensure flooding is not exacerbated in the locality in accordance with INF4 of the SOLP. .

That, prior to the commencement of development, a full foul water drainage scheme shall be submitted to and approved in writing by the Local Planning Authority. The scheme shall include details of the size, position and construction of the drainage scheme. Thereafter the scheme as approved shall be implemented prior to the occupation of the development hereby approved. Reason: To ensure the proper provision of foul water drainage, to ensure no encroachment with the surface water drainage system and to ensure flooding and pollution is not exacerbated in the locality in accordance with INF4 of the SOLP.

A Construction Traffic Management Plan (CTMP) shall be submitted to and approved in writing by the Local Planning Authority prior to the commencement of development. The approved CTMP shall be implemented prior to any works being carried out on site and shall thereafter be maintained throughout the course of the development. Reason: In the interests of highway safety and to mitigate the impact of construction vehicles on the surrounding highway network, road infrastructure and local residents, particularly at morning and afternoon peak traffic times and in accordance with Policy TRANS5 of the South Oxfordshire Local Plan 2035.
Appeal
No appeal lodged.
Updates
These Planning Application Details were returned live from our back office database, and as such are as up to date as when the page was retrieved.