The development to which this permission relates must be begun not later than the expiration of three years beginning with the date of this permission.
Reason: By virtue of Sections 91 to 95 of the Town and Country Planning Act 1990 as amended by section 51 of the Planning and Compulsory Purchase Act 2004.
Related application(s):
P23/S1676/DISThat the development hereby approved shall be carried out in accordance with the details shown on the following approved plans, 3737-230, 3737-220, 3737-200, 3737-100B, 3737-221D, 3737-222E, 3737-223F, 3737-224E, 3737-225D and 3737-226Q, except as controlled or modified by conditions of this permission.
Reason: To secure the proper planning of the area in accordance with Development Plan policies.
Related application(s):
P23/S1676/DISPrior to the commencement of development, a full surface water drainage scheme based on full infiltration unless evidenced exhausted, including details of the size, position and construction of drainage works, shall be submitted to, and approved in writing by, the Local Planning Authority. The drainage scheme shall be designed on BRE365 percolation testing results and to accommodate a 1in 100 year storm + 40% CC and will be implemented in accordance with the approved details prior to the commencement of the development hereby approved.
Reason: To ensure the proper provision of surface water drainage and to ensure flooding is not exacerbated in the locality in accordance with Policies ENV12 and EP4 of the South Oxfordshire Local Plan 2035.
Related application(s):
P23/S1676/DISThat, prior to the commencement of development, a full foul water drainage scheme shall be submitted to and approved in writing by the Local Planning Authority. The scheme shall include details of the size, position and construction of the drainage scheme. Note: The PTP must comply with BS EN 12566 achieving a minimum discharge effluent quality of 20:30:20. Furthermore, we will expect to see a Drainage Field designed in accordance with BS 6297.
Reason: To ensure the proper provision of foul water drainage and to ensure flooding and pollution is not exacerbated in the locality in accordance with policy EP4 of the South Oxfordshire Local Plan 2035.
Related application(s):
P23/S1676/DISNo development above slab level shall take place until a photographic schedule of all materials to be used in the external construction and finishes of the development hereby permitted has been submitted to and approved in writing by the Local Planning Authority.
Reason: In the interests of the visual appearance of the development in accordance with Policies DES1 and DES2 of the South Oxfordshire Local Plan 2035.
No development above slab level shall take place until the development details of the specification of the specification of the glass coating shall be provided. The visible light transmission VLT value should be 70% max to prevent illumination and light spill shown to be fitted on the dwelling hereby approved shall be submitted to and approved in writing by the Local Planning Authority and thereafter implemented and retained in accordance with the approved details.
Reason: To protect the appearance of the dark skies of Chilterns Area of Outstanding Natural Beauty, the environment and wildlife, and local residents from light pollution in accordance with Policies DES1, DES2, DES6, ENV1 and ENV3 of the South Oxfordshire Local Plan 2035.
Any external lighting will only be permitted in accordance with a lighting scheme to be submitted to and approved in writing by the Local Planning Authority prior to the commencement of development above slab level hereby approved. The scheme shall be designed to an E1: Natural Environmental Zone as defined by the Institute of Lighting Professional Guidance for the reduction of obtrusive light and details shall include:
a) Details of all the equipment uses, specific lamps, luminaries and columns with images.
b) For each luminaire a full technical specification (e.g. wattage, colour rating)
c) Isolux diagrams overlaid over the site and adjacent areas
d) Details of lighting operation hours
Any such lighting shall be implemented in accordance with the approved details and directed downwards to prevent nuisance to adjoining residential occupiers from light spillage.
Reason: To protect the appearance of the dark skies of Chilterns Area of Outstanding Natural Beauty, the environment and wildlife, and local residents from light pollution in accordance with Policies DES1, DES2, DES6, ENV1 and ENV3 of the South Oxfordshire Local Plan 2035.
The tree protection details as shown on the approved Drawing: 3737/226 Rev Q shall be put in place prior to any on site works including demolition and thereafter retained in situ for the duration of development.
Reason: To safeguard trees which are visually important in accordance with Policies ENV1, DES1, and DES2 of the South Oxfordshire Local Plan 2035.
The landscaping scheme as shown on the approved plan 3737/226 Rev Q shall be implemented prior to the first occupation or use of the approved development and thereafter be maintained in accordance with the approved scheme. In the event of any of the soft landscaping so planted dying or being seriously damaged or destroyed within 5 years of the completion of the development, replacement planting, as the case may be, of a species first approved by the Local Planning Authority, shall be planted and properly maintained in a position or positions first approved in writing by the Local Planning Authority.
Reason: To help to assimilate the development into its surroundings in accordance with Policies ENV1, DES1 and DES2 of the South Oxfordshire Local Plan 2035.
Prior to the first occupation of the development hereby approved, the bird boxes and one bat box shall be erected onsite in accordance with the approved details shown on plan 3737/226 Rev Q and shall be retained on site in perpetuity.
Reason: To achieve a net gain for biodiversity, in accordance with ENV3 of the South Oxfordshire Local Plan 2035 and paragraph 170 of the National Planning Policy Framework.
Prior to first occupation, all carbon reduction energy efficiency measures shall be implemented in accordance with the Energy Statement hereby approved and a Verification Report shall be submitted to the Local Planning Authority and approved in writing. The Verification Report shall demonstrate (with photographic evidence) that the energy efficiency measures have been implemented. These measures shall be retained and maintained as such thereafter in accordance with the Energy Statement and Verification Report.
Reason: To ensure high standards of sustainable design and construction in accordance with Policy DES10 of the South Oxfordshire Local Plan 2035.
Prior to occupation of the development hereby permitted the proposed means of access onto Wood Lane is to be formed and laid out and constructed strictly in accordance with the local highway authority's specifications and all ancillary works specified shall be undertaken.
Reason: In the interest of highway safety in accordance with Policy TRANS5 of the South Oxfordshire Local Plan 2035.
The vision splays shown on the approved plan on drawing no. 3737/206, Rev C within application no. P21/S0956/O, shall not be obstructed by any object, structure, planting or other material with a height exceeding or growing above 0.9 metres as measured from carriageway level.
Reason: In the interest of highway safety in accordance with Policy TRANS5 of the South Oxfordshire Local Plan 2035.
Prior to the first occupation of the development hereby approved, the parking and turning areas shall be provided in accordance with the approved plan 3737/221, Rev B and shall be constructed, laid out, surfaced, drained and completed to be compliant with sustainable drainage (SuDS) principles, and shall be retained unobstructed except for the parking of vehicles associated with the development at all times.
Reason: In the interests of highway safety and in accordance with Policy TRANS5 of the South Oxfordshire Local Plan 2035.
The cill level of the roof lights in the front and side elevations shall be at least 1.7 metres above the floor level of the associated rooms and shall be retained as such. No additional rooflights shall be inserted into the any part of the roof of the development hereby approved without planning permission from the Local Planning Authority.
Reason: To ensure that the development is not unneighbourly in accordance with Policy DES6 of the South Oxfordshire Local Plan 2035.
Notwithstanding the provisions of the Town and Country Planning (General Permitted Development) Order 2015 (or any Order revoking or re-enacting that Order), the enlargement, improvement or other alteration of any dwellinghouse or any building incidental to the enjoyment of the dwellinghouse as described in Schedule 2, Part 1, Classes A, B, C and E of the Order shall not be undertaken without obtaining planning permission from the Local Planning Authority.
Reason: To safeguard the amenities of the occupiers of the adjoining properties and the character of the area in accordance with Policies DES1, DES2 and DES6 of the South Oxfordshire Local Plan 2035.