The development to which this permission relates must be begun not later than the expiration of three years beginning with the date of this permission.
Reason: By virtue of Sections 91 to 95 of the Town and Country Planning Act 1990 as amended by section 51 of the Planning and Compulsory Purchase Act 2004.
Related application(s):
P24/S1479/DISThat the development hereby approved shall be carried out in accordance with the details shown on the following approved plans:
18649-HYD-XX-XX-DR-ME-9000-P01 External Lighting Layout
151966-STL-XX-00-DR-A-01003-Proposed Ground Floor Plan
151966-STL-XX-00-DR-A-80000-Fire Strategy
151966-STL-XX-00-DR-A-86000-Access and Security Strategy - External Strategy
151966-STL-XX-00-DR-A-86001-Access and Security Strategy - Internal Strategy
151966-STL-XX-RF-DR-A-01005-Proposed Roof Plan
151966-STL-XX-XX-DR-A-01000-Site Location Plan
151966-STL-XX-XX-DR-A-01001-Existing Site Plan
151966-STL-XX-XX-DR-A-01002-PL02-Proposed Site Plan
151966-STL-XX-XX-DR-A-01007-East Elevation - From Public Square
151966-STL-XX-XX-DR-A-03000-Short Sections
151966-STL-XX-XX-DR-A-03001-Long Sections
151966-STL-XX-XX-DR-A-86003-Material Key
151966-STL-XX-ZZ-DR-A-02001-Proposed Building Elevations
151966-STL-XX-ZZ-DR-L-09001-Landscape Masterplan
151966-STL-XX-ZZ-DR-L-09025-BB103 Areas Plan
151966-STL-XX-ZZ-DR-L-09025-P44-BB103 Site Areas Zones Plan
151966-STL-XX-ZZ-DR-L-09101-Tree Retention and Protection Plan
151966-STL-XX-ZZ-DR-L-09140-Landscape Planting Plan
151966-STL-XX-ZZ-DR-L-09180-Boundary Treatment Plan
151966-STL-XX-ZZ-DR-L-09405-Boundary Treatment Details
151966-STL-XX-ZZ-DR-L-09410-Sprinkler Enclosure Details
151966-STL-XX-ZZ-DR-L-09413-Timber Planter Detail
151966-STL-XX-ZZ-DR-L-09416-Timber Shelter Detail
151966-STL-XX-ZZ-DR-L-09420-Tree Pit Detail
151966-STL-XX-ZZ-DR-L-09425-Soil Profile Details
151966-STL-XX-XX-DR-A-61002-P30-Bin Store Details
151966-STL-XX-ZZ-DR-L-09412-Cycle Shelter Bespoke Details
19-346-005_REVi Highways Swept Path Drawing RM Phase 3
21-110-001_REVb Highways Swept Path Drawing Site Access
except as controlled or modified by conditions of this permission.
Reason: To secure the proper planning of the area in accordance with Development Plan policies.
Related application(s):
P24/S1479/DISNo external lighting shall be installed on the site other than in accordance with a detailed specification, which shall have first been submitted to and approved in writing by the Local Planning Authority prior to the first use of the proposed development and be based on the External Lighting Statement prepared by Hydrock dated 19 July 2021.
Details shall include the final location of the external lights and final product specification along with any measures to mitigate the impact of light spill and light pollution on the surrounding area.
Reason: To protect the appearance of the area, the environment and wildlife, and local residents from light pollution in accordance with Policies ENV1, ENV2, ENV3 and ENV12 of the South Oxfordshire Local Plan 2035.
Related application(s):
P24/S1479/DISNo development above slab level shall take place until a full photographic schedule of all materials to be used in the external construction and finishes of the development hereby permitted has been submitted to and approved in writing by the Local Planning Authority.
Reason: In the interests of the visual appearance of the development in accordance with Policies DES1 and DES2 of the South Oxfordshire Local Plan 2035.
Related application(s):
P24/S1479/DISPrior to the commencement of development, detailed plans showing the existing and proposed ground levels of the site together with the slab (finished floor levels) and ridge levels of the proposed development, relative to fixed datum points on adjoining land outside of the application site, including Chiltern Crescent, shall be submitted to and approved in writing by the Local Planning Authority. Thereafter the development shall be carried out in accordance with the approved details.
Reason: In the interests of the visual appearance of the development in accordance with Policies DES1 and DES2 of the South Oxfordshire Local Plan 2035.
Prior to commencement of the development above slab level a maintenance schedule and a long term management plan (for a minimum period of 20 years), for the approved hard and soft landscaping works shall be submitted to and approved in writing by the Local Planning Authority.
The Landscape Management Plan shall include:
a) Details of long term design principles and objectives
b) Management responsibilities, maintenance schedules and replacement provisions for existing retained landscape features and any landscape to be implemented as part of the approved landscape scheme.
c) Summary plan detailing different management procedures for the types of landscape on site e.g. native planting, boundary hedging.
d) a summary plan detailing management procedures for the biodiversity enhancements such as wildflower planting proposed in the Biodiversity Mitigation and Enhancement Strategy (BMES).
The schedule and plan shall be implemented in accordance with the agreed programme.
Reason: To help to assimilate the development into its surroundings in accordance with Policies ENV1, DES1 and DES2 of the South Oxfordshire Local Plan 2035.
Prior to commencement of the development above slab level a proportionate and specific biodiversity mitigation and enhancement strategy (BMES), as informed by a suitably qualified ecologist, shall be submitted to the Local Planning Authority. The BMES shall be based on the information and recommendations contained in the Preliminary Ecological Appraisal prepared by Windrush Ecology dated June 2021 and have regard to the approved landscaping scheme and associated management plan. Thereafter, the development shall be implemented in accordance with the approved BMES and all ecological mitigation and enhancement features shall be delivered on site prior to first use and retained as such thereafter.
Reason: To ensure that there is no net loss of biodiversity, in accordance with Policies ENV2 and ENV3 of the South Oxfordshire Local Plan 2035.
No development shall commence until a detailed sustainable drainage scheme sufficient for the associated development and any upstream catchments, has been submitted to and approved in writing by the local planning authority.
This shall be based on sustainable drainage principles and an assessment of the hydrological and hydrogeological context of the development.
No building shall be occupied until the surface drainage works to serve that section of the development have been carried out and completed in accordance with the approved details.
The scheme to be submitted shall include:
a) Information on proposed discharge rates with the overall discharge from the site restricted to the 1 in 1yr greenfield runoff rate for the worst case 1 in 1yr storm and the QBar greenfield runoff rate for the worst case 1:100yr + 40% storm.
b) A compliance report to demonstrate how the scheme complies with the "Local Standards and Guidance for Surface Water Drainage on Major Development in Oxfordshire".
c) Detailed hydraulic calculations including node references with consideration for the worst case 1:100 + 40% event based on using the latest FEH input data.
d) Fully detailed sustainable surface water drainage layouts.
e) Proposed site levels, floor levels and an exceedance plan.
f) SUDS features and sections.
g) Landscape plans with sustainable drainage features integrated and co-ordinated as appropriate.
h) Full drainage construction details.
i) A Maintenance and Management Plan covering all surface water drainage and SUDS features.
Reason: To ensure the proper provision of surface water drainage and to ensure flooding is not exacerbated in the locality in accordance with Policy EP4 of the South Oxfordshire Local Plan 2035.
No development shall be occupied until confirmation has been provided that either: all fresh water network upgrades required to accommodate the additional demand to serve the development have been completed; or a development and infrastructure phasing plan has been agreed with Thames Water to allow development to be occupied. Where a development and infrastructure phasing plan is agreed no occupation of the new buildings shall take place other than in accordance with the agreed development and infrastructure phasing plan.
Reason: To ensure the proper provision of fresh water in accordance with Policy EP4 and ENV12 of the South Oxfordshire Local Plan 2035 as the development may lead to no / low water pressure and network reinforcement works are anticipated to be necessary to ensure that sufficient capacity is made available to accommodate additional demand anticipated from the new development.
No development shall commence on site until a Construction Method Statement has been submitted to, and approved in writing by, the Local Planning Authority. The approved Statement shall be adhered to throughout the construction period. The development shall not be carried out otherwise than in accordance with the approved construction methods.
The Construction Method Statement shall include the following:
a) The parking of vehicles of site operatives and visitors.
b) Loading and unloading of plant and materials.
c) Storage of plant and materials used in constructing the development.
d) The erection and maintenance of security hoarding including decorative displays and facilities for public viewing, where appropriate.
e) Wheel washing facilities.
f) Measures to control the emission of dust and dirt during construction.
g) A scheme for recycling/disposing of waste resulting from demolition and construction works.
h) Measures for the protection of the natural environment.
i) Hours of construction, including deliveries.
j) Specific consideration of coordination and measures to avoid conflicts and minimise potential cumulative impacts associated with the construction of the wider development site.
Reason: To ensure that the development is not unneighbourly in accordance with Policy DES6 of the South Oxfordshire Local Plan 2035.
Prior to first use details and locations of all external plant, machinery and equipment shall be submitted to and approved in writing by the Local Planning Authority. The details shall include external ventilation and watering equipment as well as any additional noise attenuation measures. The equipment shall be so installed, maintained and operated so as to ensure that the rating noise level from the equipment does not exceed the background noise level at the boundary of the premises.
Measurement and rating of noise for the purposes of this condition shall be in accordance with BS4142 (2014) 'Method for rating industrial and commercial sound'. The measurement location shall be 1 metre from the facade of the nearest noise sensitive receptor.
In the event of unacceptable noise or vibration being caused by the installed plant, machinery and equipment, the applicant or persons responsible shall investigate and undertake works to resolve the problem as soon as practicable to the satisfaction of the Local Planning Authority within a reasonable time frame first agreed in writing with the Local Planning Authority.
Reason: To protect the occupants of nearby residential properties from loss of amenity due to noise disturbance and in accordance with Policy ENV12 of the South Oxfordshire Local Plan 2035.
.
Prior to first occupation, the carbon reduction and energy efficiency measures within the approved Energy Statement (Hydrock, 19 July 2021) shall be implemented in full and a Verification Report submitted (with photographic evidence, as appropriate) to demonstrate that the measures have been implemented. Thereafter, these measures shall be retained and maintained in accordance with the Energy Statement and Verification Report.
Reason: To ensure high standards of sustainable design and construction in accordance with Policy DES10 of the South Oxfordshire Local Plan 2035.
The development hereby approved shall achieve a minimum BREEAM Rating of Very Good overall, with Excellent credits as set out in the BREEAM pre-assessment dated 31 March 2022.
Prior to completion and first occupation of the school building a Design Stage Certificate for the building (provided by a licenced Building Research Establishment Environmental Assessment Method Assessor) shall be submitted to and approved in writing by the Local Planning Authority to demonstrate compliance.
Within 9 months of occupation of the school building, evidence shall be submitted in the form of a Post Construction Certificate (provided by a licenced Building Research Establishment Environmental Assessment Method Assessor) to demonstrate full compliance with the specified BREEAM standard for the building and site.
Reason: To ensure high standards of sustainable design and construction in accordance with Policy DES10 of the South Oxfordshire Local Plan 2035.
Prior to the first occupation of the development the accesses, turning areas and car parking spaces shown on drawing 151966-STL-XX-XX-DR-A-01002-PL02-Proposed Site Plan shall be provided within the curtilage of the site so that motor vehicles may enter, turn round and leave in a forward direction and vehicles may park off the highway.
The turning area and parking spaces shall be constructed, laid out, surfaced, drained and completed to be compliant with sustainable drainage (SuDS) principles. The accesses, turning areas and car parking spaces shall be retained unobstructed except for the parking and manoeuvring of motor vehicles at all times.
Reason: In the interests of highway safety and to ensure the provision of off-street car parking in accordance with Policy TRANS5 of the South Oxfordshire Local Plan 2035.
Prior to the first occupation of the development the cycle, scooter and buggy parking facilities shown on drawing 151966-STL-XX-XX-DR-A-01002-PL02-Proposed Site Plan and 151966-STL-XX-ZZ-DR-L-09412-Cycle Shelter Bespoke Details shall be implemented to enable their safe use.
Reason: To encourage sustainable means of transport including cycles/scooters in accordance with Policy TRANS5 of the South Oxfordshire Local Plan 2035.