Description
Demolition of existing log store, erection of two storey side extension, replacement of existing corrugated metal roof and make modification to include elevational changes. (As amplified by additional information received 25 July 2022.)
Conditions / Refusal Reasons
The development to which this permission relates must be begun not later than the expiration of three years beginning with the date of this permission.
Reason: By virtue of Sections 91 to 95 of the Town and Country Planning Act 1990 as amended by section 51 of the Planning and Compulsory Purchase Act 2004.
That the development hereby approved shall be carried out in accordance with the details shown on the following approved plans, 21-012-S-001, 21-012-P-001 A and 21-012-P-002 A, except as controlled or modified by conditions of this permission.
Reason: To secure the proper planning of the area in accordance with Development Plan policies.
The development hereby permitted shall be implemented in accordance with the recommendations of the Bat Emergence Survey submitted with the application in all respects. All ecological mitigation and enhancement features shall be delivered on site prior to first use and retained as such thereafter. Any variation shall be agreed in writing by the Local Planning Authority before such change is made.
Reason: To protect the important species on the site, in accordance with Policies ENV2 and ENV3 of the South Oxfordshire Local Plan 2035.
The exterior of the development hereby permitted shall only be constructed in the materials specified on the plans/supporting documents hereby approved or in materials which shall previously have been approved in writing by the Local Planning Authority.
Reason: In the interests of the visual appearance of the development in accordance with Policies DES1 and DES2 of the South Oxfordshire Local Plan 2035.
Prior to the commencement of the development a phased risk assessment shall be carried out by a competent person in accordance with current government and Environment Agency Guidance and Approved Codes of Practice such as Land Contamination: Risk Management 2020 and BS10175:2011 +A2:2017 'Investigation of potentially contaminated sites'. Each phase shall be submitted to and approved in writing by the Local Planning Authority.
Phase 1 shall incorporate a desk study and site walk over to identify all potential contaminative uses on site, and to inform the conceptual site model. If potential contamination is identified in Phase 1 then a Phase 2 investigation shall be undertaken.
Phase 2 shall include a comprehensive intrusive investigation in order to characterise the type, nature and extent of contamination present, the risks to receptors and if significant contamination is identified to inform the remediation strategy.
Phase 3 requires that a remediation strategy be submitted to and approved by the LPA to ensure the site will be rendered suitable for its proposed use.
Reason: To ensure that any ground, water and associated gas contamination is identified and adequately addressed to ensure the safety of the development, the environment and to ensure the site is suitable for the proposed use in accordance with Policy ENV11 of the South Oxfordshire Local Plan 2035.
The development shall not be occupied until any previously approved remediation strategy has been carried out in full and a validation report confirming completion of these works has been submitted to and approved in writing by the Local Planning Authority.
Reason: To ensure that any ground, water and associated gas contamination is identified and adequately addressed to ensure the safety of the development, the environment and to ensure the site is suitable for the proposed use in accordance with Policy ENV11 of the South Oxfordshire Local Plan 2035.