The development to which this permission relates must be begun not later than the expiration of three years beginning with the date of this permission.
Reason: By virtue of Sections 91 to 95 of the Town and Country Planning Act 1990 as amended by section 51 of the Planning and Compulsory Purchase Act 2004.
Related application(s):
P23/S0651/DISThat the development hereby approved shall be carried out in accordance with the details shown on the following approved plans, 20-010-P-010, 20-010-P-011, 20-010-P-001 and 1, except as controlled or modified by conditions of this permission.
Reason: To secure the proper planning of the area in accordance with Development Plan policies.
Related application(s):
P23/S0651/DISPrior to the commencement of the development a phased risk assessment shall be carried out by a competent person in accordance with current government and Environment Agency Guidance and Approved Codes of Practice such as Land Contamination: Risk Management 2020 and BS10175:2011 +A2:2017 'Investigation of potentially contaminated sites'. Each phase shall be submitted to and approved in writing by the Local Planning Authority.
Phase 1 shall incorporate a desk study and site walk over to identify all potential contaminative uses on site, and to inform the conceptual site model. If potential contamination is identified in Phase 1 then a Phase 2 investigation shall be undertaken.
Phase 2 shall include a comprehensive intrusive investigation in order to characterise the type, nature and extent of contamination present, the risks to receptors and if significant contamination is identified to inform the remediation strategy.
Phase 3 requires that a remediation strategy be submitted to and approved by the LPA to ensure the site will be rendered suitable for its proposed use.
Reason: To ensure that any ground, water and associated gas contamination is identified and adequately addressed to ensure the safety of the development, the environment and to ensure the site is suitable for the proposed use in accordance with Policy ENV11 of the South Oxfordshire Local Plan 2035.
Related application(s):
P23/S0651/DISPrior to the commencement of development, a full surface water drainage scheme in accordance with the surface water drainage hierarchy as set out in Part H of the Building Regulations, including details of the size, position and construction of drainage works, shall be submitted to, and approved in writing by, the Local Planning Authority. The drainage scheme shall be designed to accommodate a 1 in 30 year storm + 40% CC and shall be implemented in accordance with the approved details prior to the occupation of the development hereby approved.
Reason: To ensure the proper provision of surface water drainage and to ensure flooding is not exacerbated in the locality in accordance with Policy EP4 of the South Oxfordshire Local Plan 2035.
Related application(s):
P23/S0651/DISDetails of all boundary walls, fences and any other means of enclosure shall be submitted to and approved in writing by the Local Planning Authority prior to the commencement of any development above slab level . All such approved means of enclosure shall be erected prior to the first occupation of the development.
Reason: In the interests of the visual appearance of the development in accordance with Policies DES1 and DES2 of the South Oxfordshire Local Plan 2035 and Policy H1 of the Wheatley Neighbourhood Plan.
Related application(s):
P23/S0651/DISPrior to first occupation, all carbon reduction energy efficiency measures shall be implemented in accordance with the Energy Statement hereby approved and a Verification Report shall be submitted to the Local Planning Authority and approved in writing. The Verification Report shall demonstrate (with photographic evidence) that the energy efficiency measures have been implemented. These measures shall be retained and maintained as such thereafter in accordance with the Energy Statement and Verification Report.
Reason: To ensure high standards of sustainable design and construction in accordance with Policy DES10 of the South Oxfordshire Local Plan 2035.
Prior to occupation of the new dwelling hereby permitted the proposed means of access onto Jackies Lane is to be formed and laid out and constructed strictly in accordance with the local highway authority's specifications and all ancillary works specified shall be undertaken.
Reason: In the interest of highway safety in accordance with Policy TRANS5 of the South Oxfordshire Local Plan 2035 and Policies P1 & T1 of the Wheatley Neighbourhood Plan .
Prior to the first occupation of the development hereby approved, the parking and turning areas shall be provided in accordance with the approved plan 20-022/P/001 and shall be constructed, laid out, surfaced, drained and completed to be compliant with sustainable drainage (SuDS) principles, and shall be retained unobstructed except for the parking of vehicles associated with the development at all times.
Reason: In the interest of highway safety in accordance with Policy TRANS5 of the South Oxfordshire Local Plan 2035 and Policies P1 & T1 of the Wheatley Neighbourhood Plan
The development shall not be occupied until any previously approved remediation strategy has been carried out in full and a validation report confirming completion of these works has been submitted to and approved in writing by the Local Planning Authority.
Reason: To ensure that any ground, water and associated gas contamination is identified and adequately addressed to ensure the safety of the development, the environment and to ensure the site is suitable for the proposed use in accordance with Policy ENV11 of the South Oxfordshire Local Plan 2035.
The developer shall confirm in writing to the Local Planning Authority the presence of any unsuspected contamination encountered during the development. In the event of any contamination to the land and/or water being encountered, no development shall continue until a programme of investigation and/or remedial works to include methods of monitoring and certification of such works undertaken. Where land contamination investigation/remedial works are required this must be carried out by a competent person in accordance with current government and Environment Agency Guidance and Approved Codes of Practice such as Land Contamination: Risk Management 2020 and BS10175:2011 +A2:2017 'Investigation of potentially contaminated sites' and submitted to and approved in writing by the local planning authority.
Reason: To ensure that any ground, water and associated gas contamination is identified and adequately addressed to ensure the safety of the development, the environment and to ensure the site is suitable for the proposed use in accordance with Policy ENV11 of the South Oxfordshire Local Plan 2035.
The vision splays shown on the approved plan 20-022/P/001 shall not be obstructed by any object, structure, planting or other material with a height exceeding or growing above 0.9 metres as measured from carriageway level.
Reason: In the interest of highway safety in accordance with Policy TRANS5 of the South Oxfordshire Local Plan 2035 and Policies P1 & T1 of the Wheatley Neighbourhood Plan
Prior to the first occupation of the development hereby approved, an Electric Vehicle Charging Point shall be installed for the dwelling and thereafter retained as such.
Reason: To ensure sustainable forms of transport in accordance with Policy TRANS5 of the South Oxfordshire Local Plan 2035.
The exterior of the development hereby permitted shall only be constructed in the materials specified on the plans/supporting documents hereby approved or in materials which shall previously have been approved in writing by the Local Planning Authority.
Reason: In the interests of the visual appearance of the development in accordance with Policies DES1 and DES2 of the South Oxfordshire Local Plan 2035 and Policy H1 of the Wheatley Neighbourhood Plan.