Conditions / Refusal Reasons
The development to which this permission relates must be begun not later than the expiration of three years beginning with the date of this permission.
Reason: By virtue of Sections 91 to 95 of the Town and Country Planning Act 1990 as amended by section 51 of the Planning and Compulsory Purchase Act 2004.
That the development hereby approved shall be carried out in accordance with the details shown on the following approved plans, 2110413.POT.01 Rev A, 2110413.POT.02 Rev A, 2110413.POT.03 Rev A, 2110413.POT.04 Rev A, 2110413.POT.05 Rev A, 2110413.POT.06 Rev A, 2110413.POT.07 Rev A, 2110413.POT.08 Rev A and 2110413.POT.09 Rev A, except as controlled or modified by conditions of this permission.
Reason: To secure the proper planning of the area in accordance with Development Plan policies.
Prior to the commencement of development the applicant, or their agents or successors in title, shall be responsible for organising and implementing an archaeological watching brief, to be maintained during the period of construction/during any groundworks taking place on the site. The watching brief shall be carried out by a professional archaeological organisation in accordance with a Written Scheme of Investigation that has first been approved in writing by the Local Planning Authority.
Reason: To secure the protection of and proper provision for any archaeological remains in accordance with Policy ENV9 of the South Oxfordshire Local Plan 2035.
Following the approval of the Written Scheme of Investigation referred to in condition 3, no development shall commence on site without the appointed archaeologist being present. Once the watching brief has been completed its findings shall be reported to the Local Planning Authority, as agreed in the Written Scheme of Investigation, including all processing, research and analysis necessary to produce an accessible and useable archive and a full report for publication which shall be submitted to the Local Planning Authority within two years of the completion of the archaeological fieldwork.
Reason - To safeguard the recording and inspection of matters of archaeological importance on the site in accordance with Policy ENV9 South Oxfordshire Local Plan 2035.
No development above slab level shall take place until a photographic schedule of all materials to be used in the external construction and finishes of the development hereby permitted has been submitted to and approved in writing by the Local Planning Authority.
Reason: In the interests of the visual appearance of the development in accordance with Policies DES1, DES2, ENV6 and ENV8 of the South Oxfordshire Local Plan 2035.
Notwithstanding the details shown on the approved plans and prior to the construction of any development above slab level a scheme for the provision of boundary treatments shall be submitted to and approved in writing by the Local Planning Authority prior to the commencement of the development hereby permitted. Thereafter the development shall be carried out in accordance with the agreed details.
Reason: To help to assimilate the development into its surroundings in accordance with Policies DES1, DES2, EN6 and ENV8 of the South Oxfordshire Local Plan 2035.
Prior to the first occupation of the dwelling vision splays measuring 2.0 metres by 2.0 metres shall be provided to each side of the access and the vision splays shall not be obstructed by any object, structure, planting or other material with a height exceeding or growing above 0.6 metres as measured from carriageway level.
Reason: In the interest of highway safety in accordance with Policy TRANS5 of the South Oxfordshire Local Plan 2035.
Prior to first occupation, all carbon reduction energy efficiency measures shall be implemented in accordance with the Energy Statement hereby approved and a Verification Report shall be submitted to the Local Planning Authority and approved in writing. The Verification Report shall demonstrate (with photographic evidence) that the energy efficiency measures have been implemented. These measures shall be retained and maintained as such thereafter in accordance with the Energy Statement and Verification Report.
Reason: To ensure high standards of sustainable design and construction in accordance with Policy DES10 of the South Oxfordshire Local Plan 2035.
The garage accommodation hereby approved shall be retained as such and shall not be adapted for living purposes without planning permission from the Local Planning Authority.
Reason: In the interests of highway safety and to ensure the provision of adequate off-street car parking in accordance with Policy TRANS5 of the South Oxfordshire Local Plan 2035.
Prior to the first occupation of the development hereby approved, a scheme to provide an Electric Vehicle Charging Point shall be submitted to and approved in writing by the Local Planning Authority. The Electric Vehicle Charging Point shall be implemented prior to the occupation of the development and thereafter retained as such.
Reason: To ensure sustainable forms of transport in accordance with Policy TRANS5 of the South Oxfordshire Local Plan 2035.
Prior to the first occupation of the development hereby approved, the parking and turning areas shall be provided in accordance with the approved plan 2011413.POT-3 Rev A and shall be constructed, laid out, surfaced, drained and completed to be compliant with sustainable drainage (SuDS) principles, and shall be retained unobstructed except for the parking of vehicles associated with the development at all times.
Reason: In the interests of highway safety and in accordance with Policy TRANS5 of the South Oxfordshire Local Plan 2035.
The development shall be implemented in accordance with the ecological enhancement measures stated in Table 8, Section 4.2 of the supporting Preliminary Roost Assessment Survey (Arbtech Consulting Ltd, 05/02/2020, Issue 2). All ecological enhancements shall be delivered on site prior to first occupation.
Reason: To secure ecological enhancements on site, in accordance with Policies ENV2 and ENV3 of the South Oxfordshire Local Plan 2035.