Conditions / Refusal Reasons
The development to which this permission relates must be begun not later than the expiration of three years beginning with the date of this permission.
Reason: By virtue of Sections 91 to 95 of the Town and Country Planning Act 1990 as amended by section 51 of the Planning and Compulsory Purchase Act 2004.
That the development hereby approved shall be carried out in accordance with the details shown on the following approved plans, P30-020 Rev C, P30-010 Rev C, 202 Rev E, 101 Rev E, 1903_EX_102, 1903_EX_202, 1903_SD_100D, 1903_EX_101 and HTS-TPP-01C, except as controlled or modified by conditions of this permission.
Reason: To secure the proper planning of the area in accordance with Development Plan policies.
The exterior of the development hereby permitted shall only be constructed in the materials specified on the plans/supporting documents hereby approved or in materials which shall previously have been approved in writing by the Local Planning Authority.
Reason: In the interests of the visual appearance of the development in accordance with Policies ENV1, ENV6, DES1 and DES2 of the South Oxfordshire Local Plan 2035.
The garage accommodation hereby approved shall be retained as such and shall not be adapted for living purposes without planning permission from the Local Planning Authority.
Reason: In the interests of highway safety and to ensure the provision of adequate off-street car parking in accordance with Policy TRANS5 of the South Oxfordshire Local Plan 2035.
The tree protection details as shown on the approved Tree Protection Plan HTS-TPP-01C shall be put in place prior to any on site works including demolition and thereafter retained in situ for the duration of development. The excavation for the garage foundations shall be done using an Air Spade.
Reason: To safeguard trees which are visually important in accordance with Policies ENV1, DES1, and DES2 of the South Oxfordshire Local Plan 2035.
Prior to the commencement of development, a full surface water drainage scheme in accordance with the surface water drainage hierarchy as set out in Part H of the Building Regulations, including details of the size, position and construction of drainage works, shall be submitted to, and approved in writing by, the Local Planning Authority. The drainage scheme shall be designed to accommodate a 1 in 30 year storm + 40% CC and shall be implemented in accordance with the approved details prior to the occupation of the development hereby approved.
Reason: To ensure the proper provision of surface water drainage and to ensure flooding is not exacerbated in the locality in accordance with Policy EP4 of the South Oxfordshire Local Plan 2035.