The development to which this permission relates must be begun not later than the expiration of three years beginning with the date of this permission.
Reason: By virtue of Sections 91 to 95 of the Town and Country Planning Act 1990 as amended by section 51 of the Planning and Compulsory Purchase Act 2004.
Related application(s):
P21/S3455/DISThe development hereby approved shall be carried out in accordance with the details shown on the following approved plans except as controlled or modified by conditions of this permission:
- Location plan - drawing no. 1901 REV P04
- Pathfinder site layout - drawing no. R05
- Floor plan - drawing no. 1001 REV 11
- Roof plan - drawing no. 1002 REV P02
- Elevations and section - drawing no. 201 REV P06
Reason: To secure the proper planning of the area in accordance with Development Plan policies.
Related application(s):
P21/S3455/DISNo development shall commence until a full surface water drainage scheme, including details of the size, position and construction of drainage works, has been submitted to, and approved in writing by, the Local Planning Authority. The drainage scheme shall be designed to accommodate a 1 in 100 year storm + 40% CC and shall be implemented in accordance with the approved details prior to the occupation of the development hereby approved.
Reason: To ensure the proper provision of surface water drainage and to ensure flooding is not exacerbated in the locality in accordance with Policy EP4 of the South Oxfordshire Local Plan 2035.
Related application(s):
P21/S3455/DISNo development shall commence until a full foul water drainage scheme has been submitted to and approved in writing by the Local Planning Authority. The scheme shall include details of the size, position and construction of the drainage scheme, all coupled with calculations to evidence this. Thereafter the scheme as approved shall be implemented prior to the occupation of the development hereby approved.
Reason: To ensure the proper provision of foul water drainage and to ensure flooding and pollution is not exacerbated in the locality in accordance with policy EP4 of the South Oxfordshire Local Plan 2035.
Related application(s):
P21/S3455/DISNo development shall commence until an archaeological written scheme of investigation, relating to the application site has been submitted to and approved by the Local Planning Authority.
Reason - To safeguard the recording of archaeological matters within the site in accordance with policy ENV9 of the the South Oxfordshire Local Plan 2035 and the NPPF.
Related application(s):
P21/S3455/DISNo development shall commence until a staged programme of archaeological evaluation and mitigation has been carried out by the commissioned archaeological organisation in accordance with the approved written scheme of investigation. The programme of work shall include all processing, research and analysis necessary to produce an accessible and usable archive. Thereafter, a full report for publication shall be submitted to the local planning authority within two years of the completion of the archaeological fieldwork.
Reason - To safeguard the identification, recording, analysis and archiving of heritage assets before they are lost and to advance understanding of the heritage assets in their wider context through publication and dissemination of the evidence in accordance with policy ENV9 of the the South Oxfordshire Local Plan 2035 and the NPPF.
Prior to the commencement of any site works or operations relating to the development hereby permitted, an Arboricultural Method Statement and accompanying Tree Protection Plan shall be submitted to and approved in writing by the Local Planning Authority. Written approval must be obtained prior to commencement of any site works.
The Arboricultural Method Statement must include the following:
(1) A specification of any pruning or tree surgery works to any trees to be retained, to prevent accidental damage by construction or demolition activities;
(2) The specification and location of temporary tree protective fencing and any ground protection required to protect all retained trees in accordance with the current edition of BS 5837 ''Trees in relation to design, demolition and construction'', and details of the timing and duration of its erection;
(3) The details of materials and method of construction of any roadway, driveway, parking, pathway or other surfacing within the RPA, which is to be of a 'No Dig' construction method, in accordance with the principles with in Arboricultural Association Guidance Note 12 "The use of cellular confinement systems near trees", and in accordance with current industry best practice; and is appropriate for the type of roadway required in relation to its usage.
Thereafter the development shall be carried out in accordance with the approved details with the agreed measures being kept in place during the entire course of development.
Reason: To safeguard trees which are visually important in accordance with Policies ENV1, DES1, and DES2 of the South Oxfordshire Local Plan 2035.
The development hereby permitted shall only be constructed in the materials specified on the plan hereby approved or in materials which shall previously have been approved in writing by the Local Planning Authority.
Reason: In the interests of the visual appearance of the development in accordance with policies DES1 and DES2 of the South Oxfordshire Local Plan 2035.