The development to which this permission relates must be begun not later than 15 December 2023.
Reason: By virtue of Sections 91 to 95 of the Town and Country Planning Act 1990 as amended by section 51 of the Planning and Compulsory Purchase Act 2004.
Related application(s):
P21/S2924/DISThat the development hereby approved shall be carried out in accordance with the details shown on the following approved plans, T_110, T_112, T_111, T_113, T_ 200, T_201 and T_102A, except as controlled or modified by conditions of this permission.
Reason: To secure the proper planning of the area in accordance with Development Plan policies.
Related application(s):
P21/S2924/DISThe exterior of the development hereby permitted shall only be constructed in the materials specified on the plans/supporting documents hereby approved or in materials which shall previously have been approved in writing by the Local Planning Authority.
Reason: In the interests of the visual appearance of the development in accordance with Policies DES1 and DES2 of the South Oxfordshire Local Plan 2035.
Related application(s):
P21/S2924/DISPrior to the commencement of any site works or operations, including demolition and site clearance relating to the development hereby permitted, an Arboricultural Method Statement and accompanying Tree Protection Plan shall be submitted to and approved in writing by the Local Planning Authority.
The Arboricultural Method Statement must include the following:
(1) A specification of any pruning or tree surgery works to any trees to be retained, to prevent accidental damage by construction or demolition activities;
(2) The specification and location of temporary tree protective fencing and any ground protection required to protect all retained trees in accordance with the current edition of BS 5837 ''Trees in relation to design, demolition and construction'', and details of the timing and duration of its erection;
(3) The definition of areas for the storage or stockpiling of materials, temporary on-site parking, site offices and huts, mixing of cement or concrete, and fuel storage;
(4) The means of demolition of any existing site structures, and of the re-instatement of the area currently occupied thereby;
(5) The route and method of installation of drainage or any underground services in the vicinity of retained trees; Consideration will be made to avoid siting of utilities and service runs within the Root Protection Area (RPA) of all trees to be retained. Only where it can be demonstrated that there is no alternative location for the laying of utilities, will encroachment into the RPA be considered. Methodology for any installation works within the RPA will be provided and must be in compliance with the current edition of NJUG 'Guidelines for the planning and installation and maintenance of utility apparatus in proximity to trees'.
(6) The details and method of construction of any other structures such as boundary walls in the RPA of retained trees and how these relate to existing ground levels;
(7) The details of materials and method of construction of any roadway, driveway, parking, pathway or other surfacing within the RPA, which is to be of a 'No Dig' construction method, in accordance with the principles with in Arboricultural Association Guidance Note 12 "The use of cellular confinement systems near trees" and in accordance with current industry best practice; and is appropriate for the type of roadway required in relation to its usage.
(8) Provision for the supervision of ANY works within the RPA of trees to be retained, and for the monitoring of continuing compliance with the protective measures specified, by an appropriately qualified arboricultural consultant, to be appointed at the developer's expense and notified to the Local Planning Authority, prior to the commencement of development; and provision for the regular reporting of continued compliance or any departure there from to the Local Planning Authority.
Thereafter the development shall be carried out in accordance with the approved details with the agreed measures being kept in place during the entire course of development.
Reason: To safeguard trees which are visually important in accordance with Policies ENV1, DES1, and DES2 of the South Oxfordshire Local Plan 2035.
That telecommunication installation shall remain above ground as confirmed by the agent's email dated 29 April 2020.
Reason: To safeguard trees which are visually important in accordance with Policies ENV1, DES1, and DES2 of the South Oxfordshire Local Plan 2035.
The development hereby approved shall be implemented strictly in accordance with all of the measures stated in section 5 of the supporting Protected Species Report (Ecology by Design Ltd, 26/10/2020, Project Code: EBD01359).
Reason: To minimise the impacts of development on biodiversity, in accordance with policy ENV3 of the South Oxfordshire Local Plan 2035 and paragraphs 170 and 175 of the NPPF.
The developer shall confirm in writing to the Local Planning Authority the presence of any unsuspected contamination encountered during the development. In the event of any contamination to the land and/or water being encountered, no development shall continue until a programme of investigation and/or remedial works to include methods of monitoring and certification of such works undertaken. Where land contamination investigation/remedial works are required this must be carried out by a competent person in accordance with current government and Environment Agency Guidance and Approved Codes of Practice such as Land Contamination: Risk Management 2020 and BS10175:2011 +A2:2017 'Investigation of potentially contaminated sites' and submitted to and approved in writing by the local planning authority.
Reason: To ensure that any ground, water and associated gas contamination is identified and adequately addressed to ensure the safety of the development, the environment and to ensure the site is suitable for the proposed use in accordance with Policy DES7 of the South Oxfordshire Local Plan 2035.
Prior to the commencement of development, a full surface water drainage scheme shall be submitted to and approved in writing by the Local Planning Authority. The development shall be carried out in accordance with the approved details prior to the first occupation of the development hereby approved.
Reason: To prevent pollution and flooding in accordance with Policies EP4 and INF4 of the South Oxfordshire Local Plan 2035.
Prior to the commencement of development, a full foul water drainage scheme shall be submitted to and approved in writing by the Local Planning Authority. The development shall be carried out in accordance with the approved details prior to the first occupation of the development hereby approved.
Reason: To prevent pollution in accordance with Policy ENV12 of the South Oxfordshire Local Plan 2035.
Prior to the first occupation of the development hereby approved, the parking and turning areas shall be provided in accordance with the approved plan T_102 A, and shall be constructed, laid out, surfaced, drained and completed to be compliant with sustainable drainage (SuDS) principles, and shall be retained unobstructed except for the parking of vehicles associated with the development at all times.
Reason: In the interests of highway safety and in accordance with Policy TRANS5 of the South Oxfordshire Local Plan 2035.
The measures set out in the Energy Statement dated February 2021 prepared by Complete Oak Home, which accompanied the application, in respect of sustainable building, shall be implemented prior to the first occupation of the development, unless as may otherwise be agreed in writing by the Local Planning Authority.
Reason: To ensure high standards of sustainable design and construction in accordance with Policy DES8 of the South Oxfordshire Local Plan 2035.