Demolition of existing car repair workshop and erection of replacement commercial building comprising 4 units, with associated works including access, parking and landscaping. (As amplified by Noise Impact Assessment received 26 November 2020).
Conditions / Refusal Reasons
The development to which this permission relates must be begun not later than the expiration of three years beginning with the date of this permission.
Reason: By virtue of Sections 91 to 95 of the Town and Country Planning Act 1990 as amended by section 51 of the Planning and Compulsory Purchase Act 2004.
That the development hereby approved shall be carried out in accordance with the details shown on the following approved plans, 8200383-5009 Rev PA1, 8200383-5008 Rev PA1, 8200383-5006 Rev PA1, LOC001, 8200383-5007 Rev PA1, 8200383-5001 Rev PA1, 8200383-5005 Rev PA2 and 8200383-5010 Rev PA1, except as controlled or modified by conditions of this permission.
Reason: To secure the proper planning of the area in accordance with Development Plan policies.
A Construction Traffic Management Plan (CTMP) shall be submitted to and approved in writing by the Local Planning Authority prior to the commencement of development. The approved CTMP shall be implemented prior to any works being carried out on site, and shall be maintained throughout the course of the development.
Reason: In the interests of highway safety and to mitigate the impact of construction vehicles on the surrounding highway network, road infrastructure and local residents, particularly at morning and afternoon peak traffic times and in accordance with Policy TRANS5 of the South Oxfordshire Local Plan 2035.
Prior to the construction of the new building, a full surface water drainage scheme shall be submitted to and approved in writing by the Local Planning Authority. The development shall be carried out in accordance with the approved details prior to the first occupation of the development hereby approved.
Reason: To prevent pollution and flooding in accordance with Policies ENV12 and EP4 of the South Oxfordshire Local Plan 2035.
Prior to the construction of the new building, a full foul water drainage scheme shall be submitted to and approved in writing by the Local Planning Authority. The development shall be carried out in accordance with the approved details prior to the first occupation of the development hereby approved.
Reason: To ensure the proper provision of foul water drainage and to ensure flooding and pollution is not exacerbated in the locality in accordance with policy EP4 of the South Oxfordshire Local Plan 2035.
Prior to the construction of the building hereby approved a phased risk assessment shall be carried out by a competent person in accordance with current government and Environment Agency Guidance and Approved Codes of Practice such as Land Contamination: Risk Management 2020 and BS10175:2011 +A2:2017 'Investigation of potentially contaminated sites'. Each phase shall be submitted to and approved in writing by the Local Planning Authority.
Phase 2 shall include a comprehensive intrusive investigation in order to characterise the type, nature and extent of contamination present, the risks to receptors and if significant contamination is identified to inform the remediation strategy.
Phase 3 requires that a remediation strategy be submitted to and approved by the LPA to ensure the site will be rendered suitable for its proposed use.
Reason: To ensure that any ground, water and associated gas contamination is identified and adequately addressed to ensure the safety of the development, the environment and to ensure the site is suitable for the proposed use in accordance with Policy ENV11 of the South Oxfordshire Local Plan 2035.
The development shall not be occupied until any previously approved remediation strategy has been carried out in full and a validation report confirming completion of these works has been submitted to and approved in writing by the Local Planning Authority.
Reason: To ensure that any ground, water and associated gas contamination is identified and adequately addressed to ensure the safety of the development, the environment and to ensure the site is suitable for the proposed use in accordance with Policy ENV11 of the South Oxfordshire Local Plan 2035.
Prior to the first occupation of the building, the existing means of access onto A40 shall be improved and laid out and constructed strictly in accordance with the local highway authority's specifications and all ancillary works specified shall be undertaken.
Reason: In the interest of highway safety in accordance with Policy TRANS5 of the South Oxfordshire Local Plan 2035.
Prior to the first occupation of the development hereby approved, the parking and turning areas shall be provided in accordance with the approved plan 8200383-5005 Rev PA2 and shall be constructed, laid out, surfaced, drained and completed to be compliant with sustainable drainage (SuDS) principles, and shall be retained unobstructed except for the parking of vehicles associated with the development at all times.
Reason: In the interests of highway safety and in accordance with Policy TRANS5 of the South Oxfordshire Local Plan 2035.
The exterior of the development hereby permitted shall only be constructed in the materials specified on the plans hereby approved or in materials which shall previously have been approved in writing by the Local Planning Authority.
Reason: In the interests of the visual appearance of the development in accordance with Policy DES1 and DES2 of the South Oxfordshire Local Plan 2035.
That, unless otherwise agreed in writing by the local planning authority, the approved development will meet BREEAM 'Excellent Standard'.
Reason: To ensure that the development meets the high standard of sustainable design in accordance with Policy DES10 of the South Oxfordshire Local Plan 2035.