Description
Two storey side extension to existing property in HMO (as amplified by arboricultural tree survey and tree protection plan received 2 November 2020). (as per amended arboricultural impact assessment and tree protection plan received 26 November 2020). (Foul & surafec water to connect into existing system as confirmed by the agents email and amended plans received 12 Januray 2021)
Conditions / Refusal Reasons
The development to which this permission relates must be begun not later than the expiration of three years beginning with the date of this permission.
Reason: By virtue of Sections 91 to 95 of the Town and Country Planning Act 1990 as amended by section 51 of the Planning and Compulsory Purchase Act 2004.
That the development hereby approved shall be carried out in accordance with the details shown on the following approved plans, 1A, HTS-TCP-01A and HTS-TPP-01A, except as controlled or modified by conditions of this permission.
Reason: To secure the proper planning of the area in accordance with Development Plan policies.
The exterior of the development hereby permitted shall only be constructed in the materials specified on the plans/supporting documents hereby approved or in materials which shall previously have been approved in writing by the Local Planning Authority.
Reason: In the interests of the visual appearance of the development in accordance with Policies DES1 and DES2 of the South Oxfordshire Local Plan 2035.
The tree protection details as shown on the approved Arboricultural Method Statement V 1 and Tree protection plan HTS-TPP-01A shall be put in place prior to any on site works including demolition and thereafter retained in situ for the duration of development.
Reason: To safeguard trees which are visually important in accordance with Policies DES1, DES2, ENV5 and HEN1 of the South Oxfordshire Local Plan 2035.
Prior to the commencement of development, a full surface water drainage scheme, including details of the size, position and construction of drainage works, shall be submitted to, and approved in writing by, the Local Planning Authority. The drainage scheme shall be designed to accommodate a 1 in 100 year storm + 40% CC and shall be implemented in accordance with the approved details prior to the occupation of the development hereby approved.
Reason: To ensure the proper provision of surface water drainage and to ensure flooding is not exacerbated in the locality in accordance with Policies ENV12 and EP4 of the South Oxfordshire Local Plan 2035.