Description
Installation of 19.2m of sheet piling, two 150mm x 150mm mooring piles, three 2m x 3m landing stages (as amplified by Site Visit Report from Environment Agency received on 10/01/2020).
Conditions / Refusal Reasons
The development to which this permission relates must be begun not later than the expiration of three years beginning with the date of this permission.
Reason: By virtue of Sections 91 to 95 of the Town and Country Planning Act 1990 as amended by section 51 of the Planning and Compulsory Purchase Act 2004.
That the development hereby approved shall be carried out in accordance with the details shown on the following approved plans, LOC-001 and KAT05, the Proposed Riverbank Work & Landing Stages document, and the Method Statement produced by Cook Piling Ltd except as controlled or modified by conditions of this permission.
Reason: To secure the proper planning of the area in accordance with Development Plan policies.
Prior to the commencement of any site works (including demolition or site clearance) a protected area shall be designated for all existing trees which are shown to be retained, and the trees shall be protected in accordance with a scheme which complies with the current edition of BS 5837: "Trees in relation to design, demolition and construction" that shall first have been submitted to, and approved in writing by, the Local Planning Authority. The agreed measures shall be kept in place during the entire course of development.
Reason: To safeguard trees which are visually important in accordance with Policies CSEN1 and CSQ3 of the South Oxfordshire Core Strategy 2027, Policies C9, D1 and G2 of the South Oxfordshire Local Plan 2011 and Policies 11 and 12 of the Goring on Thames Neighbourhood Plan.
Three bat boxes shall be erected on trees within the boundary of the application site, in a suitable location, and retained as such in perpetuity. The bat boxes shall be erected prior to the first use of the development hereby permitted.
Reason: To ensure that there is no net loss of biodiversity, in accordance with provisions of the NPPF and Policies CSB1 of the South Oxfordshire Core Strategy 2027, C6 of the South Oxfordshire Local Plan 2011 and Policy 12 of the Goring on Thames Neighbourhood Plan.