Planning Application Details

P19/S2731/FULApplication Type: Full Application (Show Map - opens in new window)
Status Bar
 
 Completed stage
 
 Current stage
 
 Next stage
Application registered
Consultation period
Application under consideration
Decision made
Description
Variation of condition 2 (approved plans) of application P18/S1475/FUL (Demolition of buildings and erection of a 70 bed care home (within class C2), parking, access, landscaping and other associated works) in line with amendments submitted and detailed in agents emails dated 18/11/2019, 22/11/2019, 13/02/2020, 27/02/2020 and 01/04/2020.
Location
Unit A Lower Broadway Broadway Didcot OX11 8ET
Grid Reference
/
Applicant
  Care Concern Group
c/o Agent
Agent
Robert Potter & Partners LLP
110 West George Street
Glasgow
G2 1QJ
Case Officer
Anne Wilkinson
Telephone: 01235 422600
Email: planning@southoxon.gov.uk
Consultation / Notification
No further Representations on this application will be accepted.

Consultations / Notifications to date are shown below.

Name / Number
Date Sent
Response Date
 
Didcot Town Council
c/o Kathy Fiander
Council Offices
Britwell Road
DIDCOT
Oxon
OX11 7JN
05 03 2020
12 03 2020
 
Network Rail
27 11 2019
 
Countryside Officer(South Oxfordshire & Vale of White Horse)
27 11 2019
11 12 2019
 
Oxfordshire County Council Single Response
05 03 2020
16 03 2020
 
Urban Design Officer (South Oxon & Vale of White Horse DC)
05 03 2020
26 03 2020
 
Aldi
Broadway
Didcot
OX11 8ET
05 03 2020
 
Didcot Garden Town Team
27 11 2019
 
Landscape Architect - SODC
05 03 2020
23 03 2020
 
Env. Protection Team
05 03 2020
06 03 2020
 
Unit 3
Building A
Broadway
Didcot
OX11 8ET
05 03 2020
 
Hrycko Carpentry
Broadway
Didcot
OX11 8ET
05 03 2020
 
Allen Power Equipment Ltd
Building A
Broadway
Didcot
OX11 8ET
05 03 2020
 
Sixt Car Hire
Unit 4
Building A
Broadway
Didcot

OX11 8ET
05 03 2020
 
Apel Holdings Ltd
Building A
Broadway
Didcot
OX11 8ET
05 03 2020
 
Origin Technical Production
Broadway
Didcot
OX11 8ET
05 03 2020
 
1 Brunstock Beck
Didcot
Oxon
OX11 7YF
05 03 2020
20 03 2020
 
5 Calder Way, Didcot
OX11 7QG
05 03 2020
 
31
Meadow Way
Didcot
Oxfordshire
OX11 0AX
05 03 2020
06 03 2020
 
Drainage - (South&Vale)
05 03 2020
19 03 2020
 
Thames Water Development Control
27 11 2019
 
Landscape Architect - SODC
27 11 2019
21 10 2019
 
Waste Management Officer (District Council)
27 11 2019
29 11 2019
 
73 St Hildas Close
Didcot
Oxfordshire
OX119UU
05 03 2020
07 01 2020
 
Application Type
Major (Full Application)
Application Progress
Date Received  
27th August 2019
Registration Date  
27th August 2019
Start Consultation Period  
6th September 2019
End Consultation Period  
19th March 2020
Target Decision Date  
3rd April 2020
Decision
Planning Permission on 2nd April 2020
Conditions / Refusal Reasons
The development to which this permission relates must be begun not later than the expiration of three years beginning with the date of permission P18/S1475/FUL (5 November 2018). Reason: By virtue of Sections 91 to 95 and section 73 (5) of the Town and Country Planning Act 1990 as amended by section 51 of the Planning and Compulsory Purchase Act 2004. Related application(s): P20/S1332/DIS, P20/S1353/DIS, P20/S3556/DIS, P20/S4135/DIS, P20/S4209/DIS

That the development hereby approved shall be carried out in accordance with the details shown on the following approved plans,except as controlled or modified by conditions of this permission: 8171111_6102 - Pedestrian Route to Didcot Town Centre 8171111_6202_A Site Access and Internal Turning Area Swept Path Analysis 11.6m Refuse Vehicle 8171111_6203_A - Site Access and Internal Turning Area Swept Path Analysis 7.5t Box Van 8171111_6204_A - Site Access and Internal Turning Area Swept Path Analysis 8.2m Fire Tender 8171111_6205_A - Site Access and Internal Turning Area Swept Path Analysis Ambulance 8171111_6206_A - Site Access and Internal Turning Area Swept Path Analysis Large Car 8171111_6207_A - Site Access and Internal Turning Area Swept Path Analysis Minibus 888.1_01L - Soft Landscape Proposals 6377_02U - Ground Floor Plan as Proposed 6377_03K - Upper Floor Plans as Proposed 6377_04G - Outline Elevations as Proposed Sheet 1 6377_05G - Outline Elevations as Proposed Sheet 1 6377_06D - Roof Plan as Proposed 6377_07 - Block Plan as Existing 6377_08D - Block Plan as Proposed 6377_09C - Cycle Stand & Bin Store 888.1.05a - Upper Floors Soft Landscape Proposals 6377.00 (LOC 001) - Location Plan 6377.01 Rev B - Topographical Site Plan Existing 6377-sk1 Boundary Retaining Wall Section 6377-103 Rev A - Bow-Top Fencing Details EDS 07-0102.01 Rev C - Sheet 1 of 2 Substation Layout Drawing EDS 07-0102.01 Rev C - Sheet 2 of 2 Substation Layout Drawing except as controlled or modified by conditions of this permission. Reason: To secure the proper planning of the area in accordance with Development Plan policies.

The development hereby approved shall be constructed using the materials approved under the discharge of conditions application ref:P19/S1937/DIS and as stated in the Local Planning Authority's letter dated 18/10/2019. Reason: In the interests of the visual appearance of the development in accordance with Policy CSQ3 of the South Oxfordshire Core Strategy 2027 and Policies G2 and D1 of the South Oxfordshire Local Plan 2011.

Prior to the first occupation of the development hereby approved all hard and soft landscape works shall be carried out in accordance with the details approved under Condition 2 above. Thereafter, the landscaped areas shall be maintained thereafter. Any trees or shrubs which die or become seriously damaged or diseased within 5 years of planting shall be replaced by trees and shrubs of similar size and species to those originally planted. Reason: To ensure the implementation of appropriate landscaping which will improve the environmental quality of the development in accordance with Policy CSQ3 of the South Oxfordshire Core Strategy 2027 and Policies G2 and D1 of the South Oxfordshire Local Plan 2011.

Prior to the first occupation of the development hereby approved, the site access onto The Broadway shall be improved and laid out and constructed in accordance with the approved plans and the local highway authority's specifications that shall be first submitted to and approved in writing by the Local Planning Authority. Thereafter the agreed improvement works to the access and all ancillary works specified shall be undertaken, prior to the occupation/use of the development hereby approved. Reason: In the interest of highway safety in accordance with Policy T1 of the South Oxfordshire Local Plan 2011.

The southern vision splay from the site access shall be formed, laid out and constructed in accordance with detailed plans which shall be submitted to and approved in writing by the Local Planning Authority, prior to the first occupation of the development. The vision splay shall not be obstructed by any object, structure, planting or other material with a height exceeding or growing above 0.6m metres as measured from carriageway level. Reason: In the interest of highway safety in accordance with Policy T1 of the South Oxfordshire Local Plan 2011.

Prior to the first occupation of the development hereby approved a turning area and car parking spaces shall be provided within the curtilage of the site so that motor vehicles may enter, turn round and leave in a forward direction and vehicles may park off the highway. The turning area and parking spaces shall be constructed, laid out, surfaced, drained and completed to be compliant with sustainable drainage (SuDS) principles in strict accordance with specification details to be submitted to and approved in writing by the Local Planning Authority prior to the commencement of development. The turning area and car parking spaces shall be retained unobstructed except for the parking and manoeuvring of motor vehicles at all times. Reason: In the interests of highway safety and to ensure the provision of off-street car parking in accordance with Policies T1 and T2 of the South Oxfordshire Local Plan 2011.

Cycle parking facilities shall be provided prior to the occupation of the development hereby approved, in accordance with details to be submitted to and approved in writing by the Local Planning Authority, prior to the commencement of works above ground level. Reason: To encourage the use of cycles as a means of transport in accordance with Policy T2 of the South Oxfordshire Local Plan 2011.

Notwithstanding the Construction Traffic Management Plan submitted in relation to condition 21 of this permission, a Construction Traffic Management Plan (CTMP) shall be submitted to and approved in writing by the Local Planning Authority prior to the commencement (except demolition works) of development. The approved CTMP shall be implemented prior to any works being carried out on site, and shall be maintained throughout the course of the development. The CTMP will include the following information: o Details of and approval of any road closures needed during construction. o Details of and approval of any traffic management needed during construction. o Details of wheel cleaning/wash facilities - to prevent mud etc, in vehicle tyres/wheels, from migrating onto adjacent highway. o Details of appropriate signing, to accord with the necessary standards/requirements, for pedestrians during construction works, including any footpath diversions. o The erection and maintenance of security hoarding / scaffolding if required. o Layout plan of the site that shows structures, roads, site storage, compound, pedestrian routes etc. o A before-work commencement highway condition survey and agreement with a representative of the Highways Depot - contact 0845 310 1111. Final correspondence is required to be submitted. Reason: In the interests of highway safety and to mitigate the impact of construction vehicles on the surrounding highway network, road infrastructure and local residents, in accordance with Policy T1 of the South Oxfordshire Local Plan 2011..

Prior to first occupation of the use of the development hereby permitted a Green Travel Plan shall be drawn up, and submitted to and approved in writing by the Local Planning Authority; such plans to include proposals for all travel by modes other than the private car for journeys to and from site .The development shall be implemented in accordance with the approved Green Travel Plan. Reason: To promote the use of non car modes of transport in accordance with Policy CSM2 of the South Oxfordshire Core Strategy 2027.

Except for demolition works, no development shall commence until a scheme for the off-site highway works has been submitted to and agreed in writing by the Local Planning Authority. The submitted scheme shall include, but not be limited to: (a) Relocation and upgrade of bus stop on the northern side of The Broadway (b) Improvement to the southern bus stop on The Broadway (c) Reinstating the kerbs and removal of tactile paving (d) informal crossing on the site access road as indicated on the approved plans or as otherwise agreed. The approved works shall be implemented in full before the first occupation/use of the development or in accordance with a programme of implementation agreed in writing with the Local Planning Authority. Reason: In the interest of highway safety in accordance with Policy T1 of the South Oxfordshire Local Plan 2011.

The development shall be implemented in accordance with the surface water drainage work details approved under the discharge of conditions application ref:P19/S1937/DIS and as stated in the Local Planning Authority's letter dated 18/10/2019 before the development is occupied. No discharge of surface water from the site shall be accepted into the public system until the drainage works referred to in the approved details have been completed. Reason: To prevent pollution and flooding in accordance with Policies EP1, EP4 and EP6 of the South Oxfordshire Local Plan 2011.

The development shall be implemented in accordance with the foul drainage detail works approved under the discharge of conditions application ref:P19/S1937/DIS and as stated in the Local Planning Authority's letter dated 18/10/2019. No discharge of foul or surface water from the site shall be accepted into the public system until the drainage works referred to in the strategy have been completed. Reason - The development may lead to sewage flooding; to ensure that sufficient capacity is made available to cope with the new development; and in order to avoid adverse environmental impact upon the community in accordance with Policy EP1 of the South Oxfordshire Local Plan 2011.

The development hereby permitted shall not be occupied until a minimum of two EV charging points is installed at the development site. All gas-fired boilers provided on site must meet a minimum standard of <40 mg/kWh. Reason: To ensure satisfactory standards of air quality for the residents of the development and surrounding residential properties in accordance with policies G2 and EP1 of the a South Oxfordshire Local Plan 2

Prior to first occupation or use of the development hereby permitted all mitigation methods proposed in the noise report by Paragon Acoustics on 18/04/2018 (namely Section 7.1) shall be implemented and maintained thereafter. Reason: To safeguard the amenities of the occupiers of the proposed development in accordance with Policy EP2 of the South Oxfordshire Local Plan 2011.

The hours of operation for construction and demolition works shall be restricted to 08:00-18:00 Monday to Friday and 08:00-13:00 on a Saturday. No work is permitted to take place on Sundays or Public Holidays without the prior written authority of the Local Planning Authority. Reason: To protect the occupants of nearby residential properties from noise disturbance in accordance with Policy EP2 of the South Oxfordshire Local Plan 2011.residential properties from noise disturbance in accordance with Policy EP2 of the South Oxfordshire Local Plan 2011.

Prior to the commencement (except for demolition works) of the development a phased risk assessment shall be carried out by a competent person in accordance with current government and Environment Agency Guidance and Approved Codes of Practice. Each phase shall be submitted to and approved in writing by the Local Planning Authority. Phase 2 shall include a comprehensive intrusive investigation in order to characterise the type, nature and extent of contamination present, the risks to receptors and if significant contamination is identified to inform the remediation strategy. Phase 3 requires that a remediation strategy be submitted to and approved by the LPA to ensure the site will be rendered suitable for its proposed use. Reason: To ensure that any ground, water and associated gas contamination is identified and adequately addressed to ensure the safety of the development, the environment and to ensure the site is suitable for the proposed use in accordance with Policy EP8 of the South Oxfordshire Local Plan 2011.

The development shall not be occupied until any previously approved remediation strategy has been carried out in full and a validation report confirming completion of these works has been submitted to and approved in writing by the Local Planning Authority. Reason: To ensure that any ground, water and associated gas contamination is identified and adequately addressed to ensure the safety of the development, the environment and to ensure the site is suitable for the proposed use in accordance with Policy EP8 of the South Oxfordshire Local Plan 2011.

The development hereby approved shall be implemented in accordance with the recommendations made in section 6.3.1 of the supporting Preliminary Ecological Appraisal (Windrush Ecology Ltd, 19/04/2018, Ref: W2669_rep_Broadway, Didcot_19-04-18). Reason: To secure a net-gain for biodiversity on the site, in accordance with Policy C6 of the SOLP, Policy CSB1 of the SOCS and paragraph 109 of the NPPF.

A boundary fence of at least 1.8m high shall be erected adjacent to Network Rail's boundary, in accordance with the details approved under the discharge of conditions application ref:P19/S1937/DIS and as stated in the Local Planning Authority's letter dated 18/10/2019. The fence shall be erected prior to the first occupation or use of the development and thereafter be maintained in accordance with the approved scheme and maintained in accordance with the approved details. Reason: In the interests of public safety to accord with Policy T1 of the SOLP.

Any demolition works shall be carried out in accordance with the Construction Traffic Management Plan (CTMP) ref: Issue 3 dated 17th March 2020 as approved under the discharge of condition application ref: P20/S0366/DIS on 02 April 2020. The approved CTMP shall be implemented prior to any demolition works being carried out on site, and shall be maintained throughout the course of the demolition works and any ground testing and contaminated land investigations being carried out on the site. Reason: In the interests of highway safety and to mitigate the impact of construction vehicles on the surrounding highway network, road infrastructure and local residents, in accordance with Policy T1 of the South Oxfordshire Local Plan 2011.