Planning Application Details

P18/S4003/FULApplication Type: Full Application (Show Map - opens in new window)
Status Bar
 
 Completed stage
 
 Current stage
 
 Next stage
Application registered
Consultation period
Application under consideration
Decision made
Description
Proposed erection of a detached dwellinghouse with associated access and landscaping. (As amended by plans received 2019-03-14 to reduce bulk, scale and proximity to highway) (Further amended by plans 2019-05-20 to re-site the property away from woodland).
Location
Land adjacent to Red Cow House Stoke Row RG9 5NY
Grid Reference
468430/183859
Applicant
The Johnsons Group
c/o Agent
Agent
Vocalism Limited
14 Raglan Gardens
Caversham
READING
RG4 5JH
Constraints
Stoke Row Conservation Area
Case Officer
Marc Pullen
Telephone: 01235 422600
Email: planning@southoxon.gov.uk
View officers committee report (14/08/2019) here
Consultation / Notification
No further Representations on this application will be accepted.

Consultations / Notifications to date are shown below.

Name / Number
Date Sent
Response Date
 
Stoke Row Parish Council
c/o Mrs Vanessa Jones
52 Wayside Green
Woodcote
Reading
RG8 0QJ
20 05 2019
03 06 2019
 
Conservation Officer ( South )
20 05 2019
31 05 2019
 
Countryside Officer(South Oxfordshire & Vale of White Horse)
20 05 2019
31 05 2019
 
Forestry Officer (South Oxfordshire District Council)
20 05 2019
11 06 2019
 
Highways Liaison Officer (Oxfordshire County Council)
20 05 2019
17 06 2019
 
Contaminated Land
20 05 2019
23 05 2019
 
Dogmore
Stoke Row
Henley-On-Thames
RG9 5PD
20 05 2019
 
Dogmore Cottage
Stoke Row
Henley-On-Thames
RG9 5PD
20 05 2019
28 03 2019
 
Chiltern House
Stoke Row
Henley-On-Thames
RG9 5PA
20 05 2019
28 03 2019
 
The Thatched Cottage
Stoke Row
Henley-On-Thames
RG9 5PA
20 05 2019
14 01 2019
 
Woodcote
Stoke Row
Henley-On-Thames
RG9 5PA
20 05 2019
 
Orchard Green, Newlands Lane
Stoke Row
Henley-On-Thames
RG9 5PS
20 05 2019
28 03 2019
 
Application Type
Minor (Full Application)
Application Progress
Date Received  
3rd December 2018
Registration Date  
3rd December 2018
Start Consultation Period  
7th December 2018
End Consultation Period  
4th June 2019
Target Decision Date  
20th August 2019
Target Committee Meeting  
14th August 2019
Decision
Planning Permission on 20th August 2019
Conditions / Refusal Reasons
The development to which this permission relates must be begun not later than the expiration of three years beginning with the date of this permission. Reason: By virtue of Sections 91 to 95 of the Town and Country Planning Act 1990 as amended by section 51 of the Planning and Compulsory Purchase Act 2004.

That the development hereby approved shall be carried out in accordance with the details shown on the following approved plans, RCSR B-PL-100F, ITB13544-GA-001 Rev K, RCSRB-PL-102F, RCSRB-PL-090J, RCSRB-PL-090K and RCSRB-PL-101E, except as controlled or modified by conditions of this permission. Reason: To secure the proper planning of the area in accordance with Development Plan policies.

Prior to the commencement of the development hereby approved samples of all materials to be used in the external construction and finishes of the development hereby permitted shall be submitted to and approved in writing by the Local Planning Authority. Reason: In the interests of the visual appearance of the development in accordance with Policies CSEN1 and CSQ3 of the South Oxfordshire Core Strategy 2027 and Policies G2, H4 and D1 of the South Oxfordshire Local Plan 2011.

The development hereby approved shall be implemented strictly in accordance with the measures stated in section 6 of the supporting Preliminary Ecological Appraisal (ACD Environmental, 19/11/2018, Ref: PRI21821_PEA). Any variation from the approved details shall first be agreed in writing by the local planning authority prior to any such changes being implemented. This condition will be discharged through the receipt of a letter from the project ecologist providing evidence that the approved measures have been implemented in accordance with this condition. Reason: To minimise the impact of development on biodiversity, in accordance with Policy CSB1 of the South Oxfordshire Core Strategy, Saved policies C6 and C8 of the South Oxfordshire Local Plan and paragraph 170 of the National Planning Policy Framework.

Prior to occupation of the development hereby permitted the proposed means of access onto Stoke Row Road, is to be formed and laid out and constructed strictly in accordance with the local highway authority's specifications and all ancillary works specified shall be undertaken. Reason: In the interest of highway safety in accordance with Policy T1 of the South Oxfordshire Local Plan 2011.

The vision splays shown on drawing no. ITB13544-GA-001, Rev K, shall not be obstructed by any object, structure, planting or other material with a height exceeding or growing above 0.9 metres as measured from carriageway level. Reason: In the interest of highway safety in accordance with Policy T1 of the South Oxfordshire Local Plan 2011.

Prior to the first occupation of the development hereby approved, the parking and turning areas shall be provided in accordance with drawing no. ITB13544-GA-001, Rev K, and shall be constructed, laid out, surfaced, drained and completed to be compliant with sustainable drainage (SuDS) principles, and shall be retained unobstructed except for the parking of vehicles associated with the development at all times. Reason: In the interests of highway safety and in accordance with Policies T1 and T2 of the South Oxfordshire Local Plan 2011.

Any gates provided shall be set back a minimum of 5.0 metres from the edge of the carriageway and shall open inwards into the site. Reason: To ensure that vehicles may wait clear of the highway while the gates are opened or closed in the interests of highway safety in accordance with Policy T1 of the South Oxfordshire Local Plan 2011.

The developer shall confirm in writing to the Local Planning Authority the presence of any unsuspected contamination encountered during the development. In the event of any contamination to the land and/or water being encountered, no development shall continue until a programme of investigation and/or remedial works to include methods of monitoring and certification of such works undertaken has been submitted to and approved in writing by the local planning authority. Reason: To ensure that any ground, water and associated gas contamination is identified and adequately addressed to ensure the safety of the development, the environment and to ensure the site is suitable for the proposed use in accordance with Policy EP8 of the South Oxfordshire Local Plan 2011.

Prior to the commencement of the development hereby permitted a scheme for the landscaping of the site, including the planting of live trees and shrubs, the treatment of the access road and hard standings, and the provision of boundary treatment shall be submitted to and approved in writing by the Local Planning Authority. The scheme shall be implemented prior to the first occupation or use of development and thereafter be maintained in accordance with the approved scheme. In the event of any of the trees or shrubs so planted dying or being seriously damaged or destroyed within 5 years of the completion of the development, a new tree or shrub or equivalent number of trees or shrubs, as the case may be, of a species first approved by the Local Planning Authority, shall be planted and properly maintained in a position or positions first approved in writing by the Local Planning Authority. Reason: To help to assimilate the development into its surroundings in accordance with Policies CSEN1 and CSQ3 of the South Oxfordshire Core Strategy 2027 and Policies G2, C9 and D1 of the South Oxfordshire Local Plan 2011.

Prior to the commencement of any site works or operations relating to the development hereby permitted, an arboricultural method statement to ensure the satisfactory protection of retained trees during the construction period shall be submitted to and approved in writing by the Local Planning Authority. Written approval must be obtained prior to commencement of any site works including demolition. The matters to be encompassed within the arboricultural method statement shall include the following:- (i) A specification for the pruning of, or tree surgery to, trees to be retained in order to prevent accidental damage by construction activities; (ii) The specification of the location, materials and means of construction of temporary protective fencing and/or ground protection in the vicinity of trees to be retained, in accordance with the recommendations of BS 5837 'Trees in relation to design, demolition and construction' and details of the timing and duration of its erection; (iii) The definition of areas for the storage or stockpiling of materials, temporary on-site parking, site offices and huts, mixing of cement or concrete, and fuel storage; (iv) The means of demolition of any existing site structures, and of the re-instatement of the area currently occupied thereby; (v) The specification of the routing and means of installation of drainage or any underground services in the vicinity of retained trees; (vi) The details and method of construction of any other structures such as boundary walls in the vicinity of retained trees and how these relate to existing ground levels; (vii) The details of the materials and method of construction of any roadway, parking, pathway or other surfacing within the RPA, which is to be of a 'no dig' construction method in accordance with the principles of Arboricultural Practice Note 12 "Through the Trees to Development", and in accordance with current industry best practice; and as appropriate for the type of roadway required in relation to its usage. (viii) Provision for the supervision of ANY works within the root protection areas of trees to be retained, and for the monitoring of continuing compliance with the protective measures specified, by an appropriately qualified arboricultural consultant, to be appointed at the developer's expense and notified to the Local Planning Authority, prior to the commencement of development; and provision for the regular reporting of continued compliance or any departure there from to the Local Planning Authority. Thereafter the development shall be carried out in accordance with the approved details with the agreed measures being kept in place during the entire course of development. Reason: To safeguard trees which are visually important in accordance with Policies CSEN1 and CSQ3 of the South Oxfordshire Core Strategy 2027 and Policies G2, C9 and D1 of the South Oxfordshire Local Plan 2011.
Appeal
No appeal lodged.
Updates
These Planning Application Details were returned live from our back office database, and as such are as up to date as when the page was retrieved.