The development to which this permission relates must be begun not later than the expiration of three years beginning with the date of this permission.
Reason: By virtue of Sections 91 to 95 of the Town and Country Planning Act 1990 as amended by section 51 of the Planning and Compulsory Purchase Act 2004.
Related application(s):
P19/S0242/DIS,
P21/S3148/DISThat the development hereby approved shall be carried out in accordance with the details shown on the following approved plans, 17150.P06, 17150.P01A, 17150.P02A, 17150.P03A, 17150.P04A, 17150.P05A, 17150.P07A, 17150.L01, 17150.SU01 and WCW.18.01, except as controlled or modified by conditions of this permission.
Reason: To secure the proper planning of the area in accordance with Development Plan policies.
Related application(s):
P19/S0242/DISPrior to the commencement of the development hereby approved, a schedule of all materials to be used in the external construction and finishes of the development hereby permitted shall be submitted to and approved in writing by the Local Planning Authority.
Reason: In the interests of the visual appearance of the development and ensure materials are sympathetic the Conservation Area and setting of the listed building in accordance with Policy CSQ3 and CSEN3 of the South Oxfordshire Core Strategy 2027 and Policies G2, CON5, CON7 D1 of the South Oxfordshire Local Plan 2011.
Related application(s):
P19/S0242/DISPrior to the commencement of the development a phased risk assessment shall be carried out by a competent person in accordance with current government and Environment Agency Guidance and Approved Codes of Practice. Each phase shall be submitted to and approved in writing by the Local Planning Authority.
Phase 2 shall include a comprehensive intrusive investigation in order to characterise the type, nature and extent of contamination present, the risks to receptors and if significant contamination is identified to inform the remediation strategy.
Phase 3 requires that a remediation strategy be submitted to and approved by the LPA to ensure the site will be rendered suitable for its proposed use.
Reason: To ensure that any ground, water and associated gas contamination is identified and adequately addressed to ensure the safety of the development, the environment and to ensure the site is suitable for the proposed use in accordance with Policy EP8 of the South Oxfordshire Local Plan 2011.
Related application(s):
P19/S0242/DISPrior to the commencement of development, a full surface water drainage scheme shall be submitted to and approved in writing by the Local Planning Authority. The scheme shall include details of the size, position and construction of the drainage scheme and results of soakage tests carried out at the site to demonstrate the infiltration rate. Three tests should be carried out for each soakage pit as per BRE 365 with the lowest infiltration rate (expressed in m/s) used for design. An exceedance plan shall be submitted. The development shall be carried out in accordance with the approved details prior to the first occupation of the development hereby approved.
Reason: To prevent pollution and flooding in accordance with Policies EP1, EP4 and EP6 of the South Oxfordshire Local Plan 2011.
Related application(s):
P19/S0242/DISPrior to the commencement of development, a full foul water drainage scheme shall be submitted to and approved in writing by the Local Planning Authority. The scheme shall include details of the size, position and construction of the drainage scheme, all coupled with calculations to evidence this. The development shall be carried out in accordance with the approved details prior to the first occupation of the development hereby approved.
Reason: To prevent pollution in accordance with Policy EP1 of the South Oxfordshire Local Plan 2011.
Related application(s):
P19/S0242/DISA Construction Traffic Management Plan (CTMP) shall be submitted to and approved in writing by the Local Planning Authority prior to the commencement of development. The approved CTMP shall be implemented prior to any works being carried out on site, and shall be maintained throughout the course of the development in accordance with the approved detail.
Reason: In the interests of highway safety and to mitigate the impact of construction vehicles on the surrounding highway network, road infrastructure and local residents, particularly at morning and afternoon peak traffic times and in accordance with Policy T1 of the South Oxfordshire Local Plan 2011.
Prior to the commencement of the development hereby permitted a scheme for the landscaping of the site, including the planting of live trees and shrubs and the provision of boundary treatment shall be submitted to and approved in writing by the Local Planning Authority prior to the commencement of the development hereby permitted. The scheme shall be implemented prior to the first occupation or use of development and thereafter be maintained in accordance with the approved scheme. In the event of any of the trees or shrubs so planted dying or being seriously damaged or destroyed within 5 years of the completion of the development, a new tree or shrub or equivalent number of trees or shrubs, as the case may be, of a species first approved by the Local Planning Authority, shall be planted and properly maintained in a position or positions first approved in writing by the Local Planning Authority.
Reason: To help to assimilate the development into its surroundings in accordance with Policies CSEN1 and CSQ3 of the South Oxfordshire Core Strategy 2027 and Policies G2, C9 and D1 of the South Oxfordshire Local Plan 2011.
The flintwork on the exterior of the development hereby permitted shall be constructed using traditional knapped flint, individually laid as part of the construction and lime mortar.
Reason: In the interests of the visual appearance of the development and ensure materials are sympathetic the Conservation Area and setting of the listed building in accordance with Policy CSQ3 and CSEN3 of the South Oxfordshire Core Strategy 2027 and Policies G2, CON5, CON7 D1 of the South Oxfordshire Local Plan 2011
The development shall not be occupied until any previously approved remediation strategy has been carried out in full and a validation report confirming completion of these works has been submitted to and approved in writing by the Local Planning Authority.
Reason: To ensure that any ground, water and associated gas contamination is identified and adequately addressed to ensure the safety of the development, the environment and to ensure the site is suitable for the proposed use in accordance with Policy EP8 of the South Oxfordshire Local Plan 2011.
The 5 high level roof light windows in the north elevation of the dwelling on plot 2 hereby permitted shall be glazed in obscure glass with a minimum of level 3 obscurity, and shall be non-opening unless the parts of the window which can be opened are more than 1.7 metres above the floor of the room in which the window is installed, prior to the first occupation of the accommodation and it shall be retained as such thereafter.
Reason: To ensure that the development is not unneighbourly in accordance with Policies D4 and H4 or H13 of the South Oxfordshire Local Plan 2011.
That the brickwork to be used for the eastern boundary wall shown to be re-built and altered either side of the access of the development hereby approved shall be of the same colour, type and texture as those used on the exsting wall.
Reason: In the interests of the visual appearance of the development and ensure materials are sympathetic the Conservation Area and setting of the listed building in accordance with Policy CSQ3 and CSEN3 of the South Oxfordshire Core Strategy 2027 and Policies G2, CON5, CON7 D1 of the South Oxfordshire Local Plan 2011
Prior to the first occupation of the development, the existing means of access onto Winterbrook shall be improved and laid out and constructed strictly in accordance with the local highway authority's specifications and all ancillary works specified shall be undertaken.
Reason: In the interest of highway safety in accordance with Policy T1 of the South Oxfordshire Local Plan 2011.
The vision splays shown on the approved plan WCW/18/01 shall not be obstructed by any object, structure, planting or other material with a height exceeding or growing above 0.9 metres as measured from carriageway level.
Reason: In the interest of highway safety in accordance with Policy T1 of the South Oxfordshire Local Plan 2011.
Prior to the first occupation of the development hereby approved, the parking and turning areas shall be provided in accordance with the approved plan 17150-P01 A, and shall be constructed, laid out, surfaced, drained and completed to be compliant with sustainable drainage (SuDS) principles, and shall be retained unobstructed except for the parking of vehicles associated with the development at all times.
Reason: In the interests of highway safety and in accordance with Policies T1 and T2 of the South Oxfordshire Local Plan 2011.
The garage accommodation hereby approved shall be retained as such and shall not be adapted for living purposes without planning permission from the Local Planning Authority.
Reason: In the interests of highway safety and to ensure the provision of adequate off-street car parking in accordance with Policies T1 and T2 of the South Oxfordshire Local Plan 2011.