The development to which this permission relates must be begun not later than the expiration of three years beginning with the date of this permission.
Reason: By virtue of Sections 91 to 95 of the Town and Country Planning Act 1990 as amended by section 51 of the Planning and Compulsory Purchase Act 2004.
Related application(s):
P21/S0034/DIS,
P21/S1165/DIS,
P21/S1678/DISThat the development hereby approved shall be carried out in accordance with the details shown on the following approved plans, P1 Rev B, TOHA 4047 08, TOHA 4047 09, TOHA 4047 06 A, TOHA 4047 07, TOHA 4047 CS, 276.22.P1.F0, 306_PP_01, 276 22 P1F, AA TCP 01 and AA TFL 02, except as controlled or modified by conditions of this permission.
Reason: To secure the proper planning of the area in accordance with Development Plan policies.
Related application(s):
P21/S0034/DISPrior to the commencement of the development hereby permitted a landscape maintenance and management plan, including the management objectives and responsibilities and maintenance schedules that include a programme of inspections for a minimum of five years for all the landscaped areas, shall be submitted to and approved in writing by the Local Planning Authority. The management and maintenance arrangements shall be carried out in accordance with the approved schedule and details
Reason: To help to assimilate the development into its surroundings in accordance with Policies CSEN1 and CSQ3 of the South Oxfordshire Core Strategy 2027 and Policies G2, C9 and D1 of the South Oxfordshire Local Plan 2011.
Related application(s):
P21/S0034/DISPrior to the commencement of the development hereby permitted a scheme for the landscaping of the site, including the planting of live trees and shrubs and the treatment of the access road and hard standings, shall be submitted to and approved in writing by the Local Planning Authority prior to the commencement of the development hereby permitted. The scheme shall be implemented prior to the first occupation or use as approved within 12 months of the commencement of the approved development and thereafter be maintained in accordance with the approved scheme. In the event of any of the trees or shrubs so planted dying or being seriously damaged or destroyed within 5 years of the completion of the development, a new tree or shrub or equivalent number of trees or shrubs, as the case may be, of a species first approved by the Local Planning Authority, shall be planted and properly maintained in a position or positions first approved in writing by the Local Planning Authority.
Reason: To help to assimilate the development into its surroundings in accordance with Policies CSEN1 and CSQ3 of the South Oxfordshire Core Strategy 2027 and Policies G2, C9 and D1 of the South Oxfordshire Local Plan 2011.
Related application(s):
P21/S0034/DISPrior to the commencement of development, a full surface water drainage scheme shall be submitted to and approved in writing by the Local Planning Authority. The development shall be carried out in accordance with the approved details prior to the first use of the development hereby approved.
Reason: To prevent pollution and flooding in accordance with Policies EP1, EP4 and EP6 of the South Oxfordshire Local Plan 2011.
The development hereby approved shall only be accessed via the proposed pedestrian footpath provided from Shiplake College.
Reason: In the interests of highway safety and to mitigate the impact that the use of the site may have on the surrounding highway network, road infrastructure and local residents in accordance with Policy T1 of the South Oxfordshire Local Plan 2011.
That prior to the first use of the development hereby permitted, the existing pitches located alongside the River Thames (the Riverside pitches) shall be returned to agricultural use.
Reason: In the interests of the visual appearance of the site and to offset the impact of the playing fields hereby approved in accordance with Policies CSEN1 and CSQ3 of the South Oxfordshire Core Strategy 2027 and Policies G2, C9 and D1 of the South Oxfordshire Local Plan 2011.
Prior to commencement of any works, a Construction Traffic Management Plan (CTMP) shall be submitted to and approved in writing by the Local Planning Authority. The CTMP shall include details of parking facilities for all construction staff and visitors, site offices and other temporary buildings where appropriate, areas for loading/unloading of plant/ materials and associated storage facilities, wheel washing and road sweeping facilities, the means of access to the site and associated methods of control and routing for construction traffic along the adjacent highway network. Thereafter, the approved document shall be implemented and complied with throughout the construction period.
Reason: In the interests of highway safety and to mitigate the impact of construction vehicles on the surrounding highway network, road infrastructure and local residents, particularly at morning and afternoon peak traffic times and in accordance with Policy T1 of the South Oxfordshire Local Plan 2011.
Prior to the commencement of the development a phased risk assessment shall be carried out by a competent person in accordance with current government and Environment Agency Guidance and Approved Codes of Practice. Each phase shall be submitted to and approved in writing by the Local Planning Authority.
Phase 1 shall incorporate a desk study and site walk over to identify all potential contaminative uses on site, and to inform the conceptual site model. If potential contamination is identified in Phase 1 then a Phase 2 investigation shall be undertaken.
Phase 2 shall include a comprehensive intrusive investigation in order to characterise the type, nature and extent of contamination present, the risks to receptors and if significant contamination is identified to inform the remediation strategy.
Phase 3 requires that a remediation strategy be submitted to and approved by the LPA to ensure the site will be rendered suitable for its proposed use.
Reason: To ensure that any ground, water and associated gas contamination is identified and adequately addressed to ensure the safety of the development, the environment and to ensure the site is suitable for the proposed use in accordance with Policy EP8 of the South Oxfordshire Local Plan 2011.
Prior to the commencement of any site works or operations relating to the development hereby permitted, an arboricultural method statement to ensure the satisfactory protection of retained trees during the construction period shall be submitted to and approved in writing by the Local Planning Authority. Written approval must be obtained prior to commencement of any site works including demolition. The matters to be encompassed within the arboricultural method statement shall include the following:
(i) A specification for the pruning of, or tree surgery to, trees to be retained in order to prevent accidental damage by construction activities;
(ii) The specification of the location, materials and means of construction of temporary protective fencing and/or ground protection in the vicinity of trees to be retained, in accordance with the recommendations of BS 5837 'Trees in relation to design, demolition and construction' and details of the timing and duration of its erection;
(iii) The definition of areas for the storage or stockpiling of materials, temporary on-site parking, site offices and huts, mixing of cement or concrete, and fuel storage;
(iv) The specification of the routing and means of installation of drainage or any underground services in the vicinity of retained trees; consideration will be made to avoid the siting of utilities and service runs within the Root Protection Area (RPA) of all trees to be retained. Only where it can be demonstrated that there is no alternative location for the laying of utilities, will encroachment into the RPA be considered. Methodology for any installation works within the RPA will be provided and must be in compliance with NJUG Volume 4, 2007 'Guidelines for the planning and installation and maintenance of utility apparatus in proximity to trees'.
(v) The details and method of construction of any other structures such as boundary walls in the vicinity of retained trees and how these relate to existing ground levels;
(vi) The details of the materials and method of construction of any roadway, parking, pathway or other surfacing within the RPA, which is to be of a 'no dig' construction method in accordance with the principles of Arboricultural Practice Note 12 "Through the Trees to Development", and in accordance with current industry best practice; and as appropriate for the type of roadway required in relation to its usage.
(vii) Provision for the supervision of ANY works within the root protection areas of trees to be retained, and for the monitoring of continuing compliance with the protective measures specified, by an appropriately qualified arboricultural consultant, to be appointed at the developer's expense and notified to the Local Planning Authority, prior to the commencement of development; and provision for the regular reporting of continued compliance or any departure there from to the Local Planning Authority.
Thereafter the development shall be carried out in accordance with the approved details with the agreed measures being kept in place during the entire course of development.
Reason: To safeguard trees which are visually important in accordance with Policies CSEN1 and CSQ3 of the South Oxfordshire Core Strategy 2027 and Policies G2, C9 and D1 of the South Oxfordshire Local Plan 2011.
No external lighting shall be installed to serve the development hereby permitted.
Reason: To protect the appearance of the area, the environment and wildlife, and local residents from light pollution in accordance with Policy CSEN1 of the South Oxfordshire Core Strategy and Policy EP3 of the South Oxfordshire Local Plan 2011.
Notwithstanding the provisions of the Town and Country (General Permitted Development Order) 2015 (or any Order revoking or re-enacting that Order), no development as specified in Schedule 2, Part 7, Class M shall be undertaken without obtaining planning permission from the Local Planning Authority.
Reason: The specific circumstances of this site warrant the Local Planning Authority having control over any further development as specified in the condition in the interests of amenity and in accordance with Policy CSEN1, CSQ3 of the South Oxfordshire Core Strategy 2027 and Policies G2 and D1 of the South Oxfordshire Local Plan 2011.